Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217J3341999-10-19019 October 1999 Forwards Request for Addl Info Re Sale of Portion of Land Part of Oyster Creek Nuclear Generating Station Site Including Portion of Exclusion Area ML20217E0181999-10-0606 October 1999 Provides Nj Dept of Environ Protection Comments on Oyster Creek Nuclear Generating Station TS Change Request 267 Re Clarifications to Several TS Sections ML20216J7591999-09-30030 September 1999 Informs NRC That Remediation Efforts for Software Sys Etude & Rem/Aacs/Cico Have Been Completed According to Schedule & Now Y2K Ready 05000219/LER-1998-011, Forwards LER 98-011-02, Three Small Bore Pipe Lines Did Not Meet Design Bases for Siesmic & Thermal Allowables. Engineering Std Will Not Be Completed Until End of 4th Quarter of 1999 Due to Scheduling Conflicts1999-09-30030 September 1999 Forwards LER 98-011-02, Three Small Bore Pipe Lines Did Not Meet Design Bases for Siesmic & Thermal Allowables. Engineering Std Will Not Be Completed Until End of 4th Quarter of 1999 Due to Scheduling Conflicts ML20212J6721999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Oyster Creek Nuclear Generating Station on 990913.No Areas Identified in Which Licensee Performance Warranted Addl Insp Beyond Core Insp Program.Historical Listing of Plant Issues Encl ML20216K1421999-09-29029 September 1999 Provides NRC with Name of Single Point of Contact for Purpose of Accessing Y2K Early Warning Sys,As Requested by NRC Info Notice 99-025 ML20217D1661999-09-27027 September 1999 Forwards Proprietary Completed NRC Forms 396 & 398,in Support of License Renewal Applications for Listed Individuals,Per 10CFR55.57.Encl Withheld ML20217B2531999-09-24024 September 1999 Informs That on 980903,Region I Field Ofc of NRC Ofc of Investigations Initiated Investigation to Determine Whether Crane Operator Qualification/Training Records Had Been Falsified at Oyster Creek Nuclear Generating Station ML20212E1971999-09-16016 September 1999 Forwards Rev 11 of Gpu Nuclear Operational QAP, Reflecting Organizational Change in Which Functions & Responsibilities of Nuclear Safety & Technical Support Div Were Assigned to Other Divisions ML20212A7921999-09-13013 September 1999 Forwards Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, Issued on 950817 to Plant ML20212B5571999-09-10010 September 1999 Forwards Rev 11 to Oyster Creek Emergency Dose Calculation Manual, IAW 10CFR50,App E,Section V ML20211N2941999-09-0303 September 1999 Responds to NRC 990802 Telcon Request for Environ Impact Assessment of TS Change Request 251 Concerning Movement of Loads Up to 45 Tons with RB Crane During Power Operations ML20211J9831999-09-0202 September 1999 Discusses 990804 Telcon Re Sale of Portion of Oyster Creek Nuclear Generating Station Land.Requests Info Re Location of All Areas within Property to Be Released Where Licensed Radioactive Matl Present & Disposition of Radioactive Matl ML20211J6771999-08-30030 August 1999 Submits Response to NRC 990802 Telcon Request for Gpu to Provide Environ Impact Assessment for Tscr 251 ML20211K2391999-08-23023 August 1999 Forwards fitness-for-duty Performance Data Repts for TMI, Oyster Creek & Corporate Headquarters Located in Parsippany, Nj ML20211C0161999-08-19019 August 1999 Advises That Info Submitted by Ltr,Dtd 990618, Licensing Rept for Storage Capacity Expansion of Oyster Creek Spent Fuel Pool, Holtec Rept HI-981983,rev 4,will Be Withheld from Public Disclosure,Per 10CFR2.790 ML20211B9011999-08-18018 August 1999 Forwards Rev 0 to EPIP 1820-IMP-1720.01, Emergency Public Info Implementing Procedure ML20210U4341999-08-17017 August 1999 Responds to to Chairman Dicus of NRC on Behalf of Fm Massari Concern About Oyster Creek Nuclear Generating Station Not Yet Being Fully Y2K Compliant ML20210Q7331999-08-12012 August 1999 Responds to Re TS Change Request (TSCR)264 from Oyster Creek Nuclear Generating Station.Questions Re Proposed Sale of Property within Site Boundary & Exclusion Area ML20210L6311999-08-0606 August 1999 Discusses Licensee Response to GL 92-01,Rev1,Suppl 1, Rv Structural Integrity, for Plant.Staff Has Revised Info in Rv Integrity Database & Releasing as Rvid Version 2 ML20210D2801999-07-22022 July 1999 Submits Response to Administrative Ltr 99-02 Operating Reactor Licensing Action Estimates. Estimate of Licensing Actions Projected for Fy 2000 Encl.No Projection Provided for Fy 2001 ML20209H5001999-07-14014 July 1999 Forwards Revised TS Pages 3.1-15 & 3.1-17 Which Include Ref to Note (Aa) & Approved Wording of Note H of Table 3.1.1, Respectively ML20210U4411999-07-12012 July 1999 Forwards Article from Asbury Park Press of 990708 Faxed to Legislative Officer by Mutual Constitute Fm Massari Indicating That Oyster Creek Nuclear Generating State Not Fully Y2K Compliant ML20209G1451999-07-0909 July 1999 Forwards Rev 1 to 2000-PLN-1300.01, Oyster Creek Generating Station Emergency Plan. Attachment 1 Contains Brief Summary of Changes,Which Became Effective on 990702 ML20209E0821999-07-0707 July 1999 Forwards TS Change Request 269 for License DPR-16,changing Component Surveillance Frequencies to Indicate Frequency of Once Per Three Months ML20209B7501999-07-0101 July 1999 Responds to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Generic Ltr 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Licensee Y2K Readiness Disclosure for Ocngs,Encl ML20196G1361999-06-23023 June 1999 Provides Status of Corrective Actions Proposed in in Response to Insp Rept 50-219/98-80 & Revised Schedule for Completion of Actions Which Are Not Yet Complete ML20196E6421999-06-22022 June 1999 Forwards Revised Pages of TS Change Request 261,dtd 990618. Replacement Requested Due to Several Dates Being Omitted on Certain Pages ML20195G6541999-06-0707 June 1999 Discusses 981204 Initiation to Investigate Whether Contract Valve Technician,Was Discriminated Against for Raising Concern Re Use of Untrained/Unqualified Workers Performing Valve Repairs.Technician Was Not Discriminated Against ML20195G6631999-06-0707 June 1999 Discusses 981204 Intiation to Investigate Whether Contract Valve Technician Was Discriminated Against for Raising Concern Re Use of Untrained/Unqualified Workers Performing Valve Repairs.Technician Was Not Discriminated Against ML20209B0561999-06-0404 June 1999 Informs That NRR Has Reorganized,Effective 990328.Forwards Organizational Chart ML20195D0551999-06-0303 June 1999 Forwards TS Change Request 226 to License DPR-16,permitting Operation with Three Recirculation Loops.Certificate of Svc & Tss,Encl ML20195C5511999-05-25025 May 1999 Forwards Book of Controlled Drawings Currently Ref But Not Contained in Plant Ufsar.Drawings Were Current at Time of Submittal ML20206N7711999-05-11011 May 1999 Forwards Rev 0 to Oyster Creek Emergency Plan, IAW 10CFR50.47(b) & 10CFR50.54(q).Changes Became Effective on 990413 ML20206H9441999-04-28028 April 1999 Forwards Application for Amend to License DPR-16,requesting Approval to Handle Loads Up to & Including 45 Tons Using Reactor Bldg Crane During Power Operations,Per NRC Bulletin 96-002 ML20206B6991999-04-26026 April 1999 Forwards Copy of Rev 11 to UFSAR & Rev 10 to Oyster Creek Fire Hazards Analysis Rept. Without Fire Hazard Analysis ML20206D3801999-04-26026 April 1999 Forwards Rev 11 to UFSAR, & Rev 10 to Fire Hazards Analysis Rept, for Oyster Creek Nuclear Generating Station, Per 10CFR50.712(e) ML20206A9931999-04-22022 April 1999 Forwards Number of Personnel & Person Rems by Work & Job Function Rept for Period Jan-Dec 1998. Included in Rept Is Listing of Number of Station,Util & Contractor Personnel as Well as Diskette Reporting 1998 Occupational Radiation ML20206C8261999-04-22022 April 1999 Submits Financial Info IAW Requirements of 10CFR50.71(b) & 10CFR140.21 ML20205P8411999-04-15015 April 1999 Forwards TS Change Request 267 to License DPR-16,modifying Items in Sections 2 & 3 of Ts,Expanding Two Definitions in Section 1 & Modifying Bases Statements in Sections 2,3 & 4. Certificate of Svc Encl ML20205P5381999-04-14014 April 1999 Ack Receipt of Re Request for Exception to App J. Intended Correction Would Need to Be Submitted as Change to TS as Exceptions to RG 1.163 Must Be Listed in Ts,Per 10CFR50,App J ML20205P9401999-04-12012 April 1999 Informs NRC That Gpu Nuclear Is Modifying Oyster Creek FSAR to Reflect Temp Gradient of 60 F & to Correct Historical Record ML20205P0651999-04-0909 April 1999 Discusses 990225 PPR & Forwards Plant Issues Matrix & Insp Plan.Results of PPR Used by NRC Mgt to Facilitate Planning & Allocation of Insp Resources 05000219/LER-1998-015, Forwards LER 98-015-01,as Original Submittal on 981028 Inadvertently Indicated That Suppl Would Be Submitted.Suppl Should Not Have Been Required as Only Change Is on Cover Page1999-04-0505 April 1999 Forwards LER 98-015-01,as Original Submittal on 981028 Inadvertently Indicated That Suppl Would Be Submitted.Suppl Should Not Have Been Required as Only Change Is on Cover Page ML20205J3281999-04-0101 April 1999 Discusses Arrangements Made on 990323 for NRC to Inspect Licensed Operator Requalification Program at Oyster Creek Nuclear Generating Station During Week of 990524 ML20205H1081999-03-31031 March 1999 Forwards Current Funding Status for Decommissioning Funds Established for OCNPP,TMI-1,TMI-2 & SNEC ML20205F0611999-03-25025 March 1999 Submits Info on Sources & Levels of Property Insurance Coverage Maintained & Currently in Effect for Oyster Creek Nuclear Generating Station,Iaw 10CFR50.54(w)(3) ML20205E1171999-03-24024 March 1999 Forwards Rev 39 to Oyster Creek Security Plan & Summary of Changes,Iaw 10CFR50.54(p).Rev Withheld ML20207F0331999-03-0404 March 1999 Forwards Insp Rept 50-219/98-12 During Periods 981214-18, 990106-07 & 20-22.Areas Examined During Insp Included Implementation of GL 89-10 & GL 96-05.No Violations Noted ML20207K2471999-02-25025 February 1999 Forwards Fitness for Duty Performance Data Repts for TMI, Oyster Creek & Corporate Headquarters Located in Parsippany, Ny 1999-09-30
[Table view] Category:NRC TO STATE/LOCAL GOVERNMENT
MONTHYEARML20055G5141990-07-18018 July 1990 Forwards Ltr Sent to Legislative Representatives Re Shoaling Problem at Forked River ML20055F6401990-07-0505 July 1990 Responds to Re Adequacy of Cooling Water Supply to Facility in Light of Severe Shoaling of Forked River.Nrc Does Not Have Necessary Regulatory Authority to Address Adverse Recreational & Economic Effects on Local Residents ML20238B2991987-08-24024 August 1987 Responds to Expressing Concern That Mgt & Safety Problems Recently Identified at Facility Could Endanger Constituents.Nrc Ready to Take Appropriate Action If Performance Degrades to Levels Endangering Public ML20235X0001987-07-20020 July 1987 Forwards Response to 861107 & 1231 Ltrs on 861023 Tech Spec Change Request 148 Re Reactor Coolant Radioiodine Monitoring.Util Request Requires Rev Prior to Final Action ML20237D2331987-02-24024 February 1987 Responds to Questions Raised at 870116 Meeting in Bethesda,Md Re Emergency Response Data Sys.Implementation Status of SPDS for State Nuclear Power Plants Listed ML20206S1701986-09-0404 September 1986 Responds to 860725 Request for Assistance in Matters Re Plant & Siting of Hazardous Waste Disposal or Storage Facilities.Nrc Has No Position on Presence of Waste Sites Near Reactor Sites.Related Info Encl ML20214M2601986-09-0404 September 1986 Responds to 860725 Request for Assistance in Matters Re Plant & Siting of Hazardous Waste Disposal or Storage Facilities.Nrc Has No Position on Presence of Waste Sites Near Reactor Sites.Related Info Encl ML20155F1231986-04-0808 April 1986 Responds to 860218 Request for Addl Info Re Potential Water Hammer Event in Isolation Condenser Sys.Reactor Water Level Should Not Exceed 185 Inches Above Top of Active Fuel Due to Potential Damage from Water Hammer Event ML20205A4261985-04-0404 April 1985 Responds to Re Shipment of Spent Nuclear Rods from West Valley,Ny to Oyster Creek Nuclear Station.Route Will Be Resurveyed to Ensure Against Any Serious Safeguarding Dangers Over Route I-287 1990-07-05
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217J3341999-10-19019 October 1999 Forwards Request for Addl Info Re Sale of Portion of Land Part of Oyster Creek Nuclear Generating Station Site Including Portion of Exclusion Area ML20212J6721999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Oyster Creek Nuclear Generating Station on 990913.No Areas Identified in Which Licensee Performance Warranted Addl Insp Beyond Core Insp Program.Historical Listing of Plant Issues Encl ML20217B2531999-09-24024 September 1999 Informs That on 980903,Region I Field Ofc of NRC Ofc of Investigations Initiated Investigation to Determine Whether Crane Operator Qualification/Training Records Had Been Falsified at Oyster Creek Nuclear Generating Station ML20212A7921999-09-13013 September 1999 Forwards Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, Issued on 950817 to Plant ML20211J9831999-09-0202 September 1999 Discusses 990804 Telcon Re Sale of Portion of Oyster Creek Nuclear Generating Station Land.Requests Info Re Location of All Areas within Property to Be Released Where Licensed Radioactive Matl Present & Disposition of Radioactive Matl ML20211C0161999-08-19019 August 1999 Advises That Info Submitted by Ltr,Dtd 990618, Licensing Rept for Storage Capacity Expansion of Oyster Creek Spent Fuel Pool, Holtec Rept HI-981983,rev 4,will Be Withheld from Public Disclosure,Per 10CFR2.790 ML20210U4341999-08-17017 August 1999 Responds to to Chairman Dicus of NRC on Behalf of Fm Massari Concern About Oyster Creek Nuclear Generating Station Not Yet Being Fully Y2K Compliant ML20210Q7331999-08-12012 August 1999 Responds to Re TS Change Request (TSCR)264 from Oyster Creek Nuclear Generating Station.Questions Re Proposed Sale of Property within Site Boundary & Exclusion Area ML20210L6311999-08-0606 August 1999 Discusses Licensee Response to GL 92-01,Rev1,Suppl 1, Rv Structural Integrity, for Plant.Staff Has Revised Info in Rv Integrity Database & Releasing as Rvid Version 2 ML20195G6541999-06-0707 June 1999 Discusses 981204 Initiation to Investigate Whether Contract Valve Technician,Was Discriminated Against for Raising Concern Re Use of Untrained/Unqualified Workers Performing Valve Repairs.Technician Was Not Discriminated Against ML20195G6631999-06-0707 June 1999 Discusses 981204 Intiation to Investigate Whether Contract Valve Technician Was Discriminated Against for Raising Concern Re Use of Untrained/Unqualified Workers Performing Valve Repairs.Technician Was Not Discriminated Against ML20209B0561999-06-0404 June 1999 Informs That NRR Has Reorganized,Effective 990328.Forwards Organizational Chart ML20205P5381999-04-14014 April 1999 Ack Receipt of Re Request for Exception to App J. Intended Correction Would Need to Be Submitted as Change to TS as Exceptions to RG 1.163 Must Be Listed in Ts,Per 10CFR50,App J ML20205P0651999-04-0909 April 1999 Discusses 990225 PPR & Forwards Plant Issues Matrix & Insp Plan.Results of PPR Used by NRC Mgt to Facilitate Planning & Allocation of Insp Resources ML20205J3281999-04-0101 April 1999 Discusses Arrangements Made on 990323 for NRC to Inspect Licensed Operator Requalification Program at Oyster Creek Nuclear Generating Station During Week of 990524 ML20207F0331999-03-0404 March 1999 Forwards Insp Rept 50-219/98-12 During Periods 981214-18, 990106-07 & 20-22.Areas Examined During Insp Included Implementation of GL 89-10 & GL 96-05.No Violations Noted ML20206U3551999-02-0505 February 1999 Refers to Concerns Recipient Expressed to V Dricks on 990126 Related to Oyster Creek About Event Which Occurred on 970801 & About Administrative Control of EDG Vendor Manuals ML20199L2471999-01-22022 January 1999 Discusses GL 96-01, Testing of Safety-Related Logic Circuits, Issued on 960110 & Gpu Nuclear 960418 & 981202 Responses for Ocngs.Informs That Based on Confirming GL 96-01 Commitments Review Effort Closed ML20199G8241999-01-12012 January 1999 Responds to Ltr to Senator Lt Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20199G8631999-01-0707 January 1999 Responds to Ltr to Senator Lt Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20198B2121998-12-0909 December 1998 Advises of Planned Insp Efforts Resulting from Licensee Irpm Review.Historical Listing of Plant Issues & Details of Insp Plan for Next 6 Months Encl ML20196C6001998-11-25025 November 1998 Forwards Insp Rept 50-219/98-09 on 980914-1025 & Notice of Violation.Inspector Identified That Security Force Member Left Running Unlocked Vehicle Unattended in Protected Area ML20195G8901998-11-17017 November 1998 Responds to to Lt Connors Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20195G9101998-11-17017 November 1998 Responds to to Lt Connors Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20195G8801998-11-17017 November 1998 Responds to to Senator Lt Conners Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20195G9181998-11-17017 November 1998 Responds to to Lt Connors Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community IR 05000219/19980031998-11-13013 November 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-219/98-03 Issued on 980717.Corrective Actions Will Be Examined During Future Insp of Licensed Program ML20196D1431998-11-10010 November 1998 Forwards Exam Forms with Answers,Results Summary for Plant & Individual Answer Sheets of GFE Section of Written Operator Licensing Exam,Administered on 981007.Without Encl ML20195C4111998-11-0606 November 1998 Discusses 980825 Gpu Submittal of Proposed Mod for Ocnpp Core Support Plate Which Involved Installation of Wedges During 17R Outage.Licensee Intends to Use Recommendations of BWRVIP-25 & BWRVIP-50.SE Accepting Proposed Mod Encl ML20195B7981998-11-0505 November 1998 Discusses Alternative Evaluation of Flaws in Ferritic Piping.Core Spray Sys Test Line Was Concluded to Have Acceptable Level of Quality & Safety ML20155C6881998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7201998-10-29029 October 1998 Responds to Ltr to Assemblyman Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7051998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7481998-10-29029 October 1998 Responds to Ltr to Assemblyman Morgan, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C6241998-10-29029 October 1998 Responds to Ltr to Senator Connors,Dtd 980926,re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7021998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C6661998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C6841998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C6721998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7251998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7371998-10-29029 October 1998 Responds to Ltr to Senator Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C6981998-10-29029 October 1998 Responds to Recent Ltr to Senator Connors Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C6481998-10-29029 October 1998 Responds to Ltr to Sentor Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C7091998-10-29029 October 1998 Responds to Ltr to Assemblyman Connors, Re Possible Closure of Oyster Creek Nuclear Generating Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155C8781998-10-29029 October 1998 Informs That Oyster Creek Generating Station Operating License,Paragraph 2.C.5 Re Evaluation of Core Spray Internals Insp Requires Authorization from NRC Before Plant Is Restarted from Refueling Outage.Plant Restart Authorized ML20155C7301998-10-29029 October 1998 Responds to Ltr to 9th District Legislative Offices, Re Possible Closure of Oyster Creek Nuclear Station & Possible Impact That Closure May Have on Economy & Environ of Community ML20155D2041998-10-26026 October 1998 Forwards Synopsis of 980604 Investigation Rept 1-98-027 Re Possible Discrimination Against Employee for Contacting NRC in Nov 1997 with Security & Safety Concerns ML20154Q9021998-10-20020 October 1998 Forwards Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted.Licensee Have Established & Implemented Effective Programs for Initial & Continuing Training of Workers, Especially Those Having Access to Controlled Areas ML20154L3001998-10-14014 October 1998 Forwards Safety Evaluation Re Reduced Scope of IGSCC Insp, During Refueling Outage 17 ML20154J8251998-10-0707 October 1998 Discusses Concerns Raised to NRC on 980913 Re Oyster Creek. Thoroughness of NRC Insps as Documented in NRC Integrated Insp Rept 50-219/98-03 Was of Concern 1999-09-30
[Table view] |
Text
_ _
i
. .g APR 81986 berald P. Nicholls, Ph. D.
Acting Chief Bureau of Radiation Protection Department of Environmental Protection 380 Scotch Road Trenton, New Jersey 08628
Dear Dr. Nicholls:
I am pleased to respond to your letter dated February 18, 1986, in which you requested information relating to a potential water hammer event in the Oyster Creek Isolation Condenser (IC) system.
As I recall water hammer events were discussed at the November 25, 1985, meet-ing held at Region I. However, I believe a misunderstanding exists if your staff believes that at the meeting it was stated a water hammer event would not take place in the IC system. As you know all water hammer events in both BWR and PWR reactors have been extensively reviewed by the NRC. Four instances of water hammer in IC systems have been evaluated in detail. None of these events occurred at Oyster Creek and none resulted in through-wall pipe failures. In addition, the Oyster Creek FSAR states, because of the potential damage due to water hammer in the IC system, reactor water level should not be allowed to ex-ceed 185 inches above the top of active fuel. The June 12 event is an example of a case where operators took action in response to a concern about the poten-tial for water hammers during the period when reactor water level was uncertain.
Facility procedures and the operator training program emphasize this precaution.
Also, the licensee's IC system repair and failure analysis discusses procedure reviews which were conducted to minimize the probability of water hammer.
As noted in NUREG 1061 a total of approximately 150 water hammer occurrences have been reported. Two of these events, the Indian Point feedwater line rupture .in 1972 and the Maine Yankee feedwater line event in 1983, resulted in pressure boundary failure. Our recollection of the November 25 meeting is that we pointed out that it is inappropriate; because of the materials, temperatures and pressures, and configurations involved; to draw analogies between these two events and a hypothesized water hammer in the Oyster Creek Core Spray or IC systems. The Maine Yankee and Indian Point events resulted from steam-bubble collapse or mixing of subcooled water and steam, conditions not probable in an IC system.
Since water hammer occurrences have resulted in damage to piping and piping supports in nuclear plants, water hammer was designated an Unresolved Safety Issue and was technically resolved in March 1984 (See NUREG 0927). We expect the frequency of water hammer events to decrease due to the actions taken to prevent it; however, the events are still possible, as acknowledged in NUREG 0927.
With regard to your staff concern that the IC piping might not be able to with-stand a water hammer or other severe transient due to identified Intergranular GFFICIAL RECORD COPY 247BAUNACK3/21/86 - 0001.0.0 8604210331 86040s 04/07/86 L eo)
PDR ADOCK 05000219 3 O PDR- g
v s~ ,
e .
.( ,
Gerald P. Nicholls, Ph. D. 2 Stress Corrosion Cracking, the NRR Safety Evaluation of the inspection and re-pair of the IC system concluded the piping has been inspected and repaired ir, accordance with all current staff guidelines and that the plant can be safely 4
operated until the next refueling. Also, the NRR staff believes, based on the reported operating history, that the cracking probably occurred during a period when extensive leakage through isolation valves was observed. This conclusion was arrived at as a result of a review of the licensee's repair of the 27 crack-like indications in the IC system outside the containment. All 15 welds inside the containment were inspected and no indications identified.
The licensee's repair consisted of a weld overlay on 18 of the indications and the removal and replacement of the remaining 9 indications. The licensee will inspect each overlay repair during the next refueling outage. Region I review-ed the licensee's NDE procedure, selected radiographic films, ultrasonic test data, NDE personnel qualifications / certification records and the licensee's evaluation and disposition of NDE results to verify an acceptable evaluation and repair of IC system piping was conducted.
~
I hope this letter is responsive to your concerns. If I can be of any further assistance please feel free to contact me.
Sincerely, Ortgtnal SL8ned Bys Richard W. Starostecki, Director Division of Reactor Projects 4
RI *RI:DRP SI:DRP HI: SLO RI:DRS Blough Durr stecki
\h *sau:DRP nack 4/]/86 4/ 7 /86 Kister 4/ /86 Lohaus 4/ /86 4/ /86 T/86 l W
4
- b h' % OFFICIAL RECORD COPY 247BAUNACK3/21/86 - 0001.1.0 04/07/86 V L[ \/
y
- SEE PREVIOUS CONCURRENCES
. is .
Gerald P. Nicholls, Ph. O. 2 operated until the next refueling. Also, the NRR staff believes, based on the reported operating history, that the cracking probably occurred during a period when extensive leakage through isolation valves was observed. This conclusion was arrived at as a result of a review of the licensees repair of the 27 crack-like indications in the IC system outside the containment. All 15 welds inside the containment were inspected and no indications identified. '
! The licensees repair consisted of a weld overlay on 18 of the indications and the removal and replacement of the remaining 9 indications. The licensee will inspect each overlay repair during the next refueling outage. Region I review-ed the licensees NDE procedure, selected radiographic films, ultrasonic test data, NDE personnel qualifications / certification records and the licensee's evaluation and disposition of NDE results to verify an acceptable evaluation and repair of IC system piping was conducted.
l I hope this letter is responsive to your concerns. If I can be of any further assistance please feel free to contact me.
Sincerely, Richard W. Starostecki, Director Division of Reactor Projects l
t i
i c RI:DRP RI:DRP RI:DRP R 3w RI:DRS RI:DRP 92.6 Baunack Blough x Kister Lohaus Durr Starostecki-4/1/86 4/2/86 4/ (/86 4/3 /86 4/,2 /86 4/ /86 MkeCafN afk aBMw 0FFICIAL RECORD COPY 2GBAUNACK3/21/86 - 0002.0.0 03.'21/86 L