Requests Addl Info to Complete Review of 860103 Response to Concerns Re SER Confirmatory Item 10 Design Documentation Review,Including Drawing Describing Stiffeners Attached to 42-inch Diameter Purge Line Inside Containment
ML20154J830
Person / Time
Site: Beaver Valley
Issue date: 03/03/1986
From: Tam P
Office of Nuclear Reactor Regulation
To: Carey J
DUQUESNE LIGHT CO.
References
TAC-62893, NUDOCS 8603110072
Download: ML20154J830 (3)


Text

__. _ _ _ _ _ _ _ . _ _ _ _ _ _ _ - _ _ _ _

March 3, 1986 Docket No. 50-412 . DISTRIBUTION:

P. Tam i Docket NRC PDR No..50-412] C. Vogan Mr. J. J. Carey, Vice President Local PDR ACRS (10)

Duquesne Light Company PAD #2 R/F Tech. Branch Nuclear Group TNovak Gray File Post Office Box 4 OELD L. Rubenstein Shippingport, PA 15077 E. Jordan H. Brammer B. Grimes

Dear Mr. Carey:

J. Partlow

Subject:

Beaver Valley Unit 2 - Request for Additional Information on Design Documentation Review By letter dated January 3,1986, you provided your response to our questions on SER Confirmatory Item No.' 10, Design Documentation Review. Our review of that submittal found most of it to be acceptable. However, before we can complete our review, we would need the additional information described in the Enclosure.

Please provide your response within 45 days of receipt of this letter.

Sincerely, L

Peter S. Tam, Project Manager PWR Project Directorate #2 Division of PWR Licensing-A Office of Nuclear Reactor Regulation

Enclosure:

As stated cc: See next page PM: PAD _

i,' /)V' D: PAD #Pcfgt' PST ; -[ LSRubenstein 2 /8 2/g/86

  • ^*

31{g []

.i Mr. J. J. Carey .

Duquesne Light Company Beaver Valley 2 Power Station cc:

Gerald Charnoff, Esq. Mr. Roger Martin, Manager Jay E. Silberg, Esq. Regulatory Affairs Shaw, Pittman, Potts & Trowbridge Beaver Valley Two Project 1800 M Street, N.W. Duquesne Light Company, P.O. Box 328 Washington, DC 20036 Shippingport, PA 15077 Mr. C. W. Ewing Quality Assurance Director, Pennsylvania Emergency Manager Management Agency Quality Assurance Department Room B-151 Duquesne Light Company Transportation & Safety Building P.O. Box 186 Harrisburg, Pennsylvania 17120 Shippingport, Pennsylvania 15077 Mr. Thomas Gerusky Mr. E. J. Woolever, Vice Presidenf Bureau of Radiation Protection Special Nuclear Projects PA Department of Environmental Duquesne Light Company Resources P.O. Box 4 P.O. Box 20$3 Shippingport, Pennsylvania 15077 Harrisburg, Pennsylvania 17120 Mr. T. J. Lex BVPS-2 Records Management Supervisor Westinghouse Electric Corporation Duquesne Light Company Power Systems Post Office Box 4 P.O. Box 355 Shippingport, Pennsylvania 15077 Pittsburgh, Pennsylvania 15230 John A. Lee, Esq.

Mr. P. RaySircar Duquesne Light Company Stone & Webster Engineering Corporation 1 0xford Centre P.O. Box 2325 301 Grant Street Boston, Massachusetts 02107 Pittsburgh, Pennsylvania 15279 Mr. Glenn Walton U.S. NRC P.O. Box 181 Shippingport, Pennsylvania 15077 Mr. Thomas E. Murley, Regional Admin.

U.S. NRC, Region !

631 Park Avenue King of Prussia, Pennsylvania 15229 Mr. John P. Thomas, Manager Engineering Beaver Valley Two Project Duquesne Light Company P.O. Box 328 Shippingport, Pennsylvania 15077

,..b ENCLOSURE RE0 VEST FOR ADDITIONAL INFORMATION BEAVER VALLEY, UNIT 2 DOCKET NO. 50-412

Reference:

Letter from J.J. Carey.to L.S. Rubenstein, "MEB Questions dated November 26, 1985", dated January 3, 1986.

1. The response to Question 10 in Attachment D to the referenced letter contained only the title block for the requested drawing. Please provide a copy of the manufacturer's drawing. SWEC File No.

2006.450-76A-072K plus any other infomation that may be necessary to clearly answer Question 10.

2. The response to Question 15c in Attachment G to the referenced letter implies that stiffeners which are designed to the ASME Code requirements are attached to the 42 in, diameter purge line inside containment on a 10 foot spacing. Provide a drawing which describes these stiffeners and the spacing. In addition, either verify that the stiffeners meet the requirements of NC-3133.5, " Stiffening Rings for Cylindical Shells" and NC-4437, " Attachment of Stiffener Rings" or provide a complete justification for the design of this pipe when subjected to external pressure.