Ack Receipt of Update on Milesones to Achieve Prior to start-up of Millstone Nuclear Power Station
ML20154E250
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 09/18/1997
From: Diaz N
NRC COMMISSION (OCM)
To: Carns N
NORTHEAST UTILITIES SERVICE CO.
Shared Package
ML20154E211 List:
References
FOIA-98-252 NUDOCS 9810080120
Download: ML20154E250 (1)


Text

. - . .. ._ - . -

/ o,^ UNfrO STATES 1 ,

NUCLEAR RE2ULATCRY COMMISSION

{ $ WASHINGTON, D.C. 20655 September 18, 1997 conseNasioNan Mr. Neil S. Carns Senior Vice President &

Chief Nuclear Officer Northeast Utilities Service Company P.O. Box 270 Hartford, Connecticut 06141-0270

Dear Mr. Cams:

Thank you for your update on the key milestones to schieve prior to start-up of the Millstone Nuclear Power Station. ! appreciate your and Patricia Loftus's viewpoints.

I look forward to being kept abreast of developments and to a potential visit to the power station prior to start-up.

Sincerely, f .

I Nil J. z\

1 RJD278 e

pM p% ]O 980928 CHOINIE98-252 PDR L

97/420/zo