Forwards Numbering Sys to Util That NRC Intends to Use in Tracking Util Responses to RAI & Resolution of Responses
ML20154A234
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/24/1998
From: Dave Solorio
NRC (Affiliation Not Assigned)
To: Cruse C
BALTIMORE GAS & ELECTRIC CO.
References
TAC-MA2156, NUDOCS 9810020241
Download: ML20154A234 (8)


Text

, .

l September 24, 1998 l9 Mr. Charles H. Cruse, Vice President l Nuclear Energy Division l Baltimore Gas & Electric Company 1 1650 Calvert Cliffs Parkway l

Lusby, MD 20657-4702 l

SUBJECT:

RENUMBERING OF NRC REQUESTS FOR ADDITIONAL INFORMATION ON CALVERT CLIFFS NUCLEAR POWER PLANT LICENSE RENEWAL APPLICATION SUBMITTED BY THE BALTIMORE GAS AND ELECTRIC COMPANY (TAC NO. MA2156)

Dear Mr. Cruse:

By letter dated April 8,1998, Baltimore Gas and Electric Company (BGE) submitted for Nuclear Regulator Commission (NRC) review the Calvert Cliffs Nuclear Power Plant License Renewal Application (LRA).

By letters dated February 13, February 19, July 9, August 6, August 11, August 21, August 26, August 27, August 28, August 31, September 1, September 2, September 3, September 4, and September 7,1998, the NRC staff issued requests for additional information (RAl) on BGE's LRA.

In the interest of facilitating tracking and resolution of BGE's responses to the staff's RAI, we are forwarding BGE the numbering system that the staff intends to use in tracking BGE's responses to the RAI and the resolution of the responses. In responding to the staff's RAI, the staff requests that BGE use the numbering scheme as outlined in the enclosed table.

If you have any questions regarding the new numbering scheme, please contact me at 301-415-1973.

Sincerely, OdobalaredW David L. Solorio, Project Manager License Renewal Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318

Enclosure:

BGE Requests for Additional Information I Tracking Sheet k cc w/ encl: See next page p\

DISTRIBUTION:

See next page j

DOCUMENT NAME G'\WOPKING\SOLORIO\RAI NUM LTR OFFICE PDLR/DRPM:D LA:PDI-@ PDLR/DR]M NAME SLittif DSoloria% CGrimes [ '@

DATE g4Ig8 g/%8 g%g7 '

OFF lAL RECORD COPY y- - .,,

i tj (

9810020241 980924 DR ADOCK 0500 7 ((Sy

,.g Mr. Charles H. Cruse Calvert Cliffs Nuclear Power Plant l Baltimore Gas & Electric Company Unit Nos.1 and 2 cc:

President Mr. Joseph H. Walter, Chief Engineer Calvert County Board of Public Service Commission of Commissioners Maryland 175 Main Streat Engineering Division Prince Fredarick, MD 20678 6 St. Paul Centre Baltimore, MD 21202-6806 James P. Bennett, Esquire Counsel Kristen A. Burger, Esquire Baltimore Gas and Electric Company Maryland People's Counsel P.O. Box 1475 6 St. Paul Centre Baltimore, MD 21203 Suite 2102 Baltimore, MD 21202-1631 Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge Patricia T. Birnie, Esquire 2300 N Street, NW Co-Director Washington, DC 20037 Maryland Safe Energy Coalition P.O. Box 33111 Mr. Bruce S. Montgomery, Director Baltimore, MD 21218 NRM Calvert Cliffs Nuclear Power Plant Mr. Loren F. Donatell 1650 Calvert Cliffs Parkway NRC Technical Training Center Lusby, MD 20657-4702 5700 Brainerd Road Chattanooga, TN 37411-4017 Resident inspector U.S. Nuclear Regulatory Commission David Lewis P.O. Box 287 Shaw, Pittman, Potts, and Trowbridge St. Leonard, MD 20685 2300 N Street, NW Washington, DC 20037 Mr. Richard I. McLean Nuclear Programs Douglas J. Walters Power Plant Research Program Nuclear Energy Institute Maryland Dept. of Natural Resources 1776 i Street, N.W.

Tawes State Office Building, B3 Suite 400 Annapolis, MD 21401 Washington, DC 20006-3708 DJW@NEl.ORG Regional Administrator, Region i U.S. Nuclear Regulatory Commission Barth W. Doroshuk 475 Allendale Road Baltimore Gas and Electric Company King of Prussia, PA 19406 Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway l NEF 1st Floor Lusby, Maryland 20657 i

?

l

b  !

l 3,0 DistributlQ0:

HARD COPY l Dochet Files .a I

PUBLIC ,

PDLR R/F l

MEl-Zeftawy l ADromerick DISTRIBUTION: E-MAIL:

FMiraglia (FJM)

JRoe (JWR)

DMatthews (DBM)

CGrimes (CIG)

TEssig (THE)

GLainas (GCL)

JStrosnider (JRS2)

GHolahan (GMH)

SNewberry (SFN)

GBagchi (GXB1)

RRothman (RLR)

JBrammer (HLB)

CGratton (CXG1)

JMoore (JEM)

MZobler/RWeisman (MLZ/RMW)

SBajwa (SSB1)

LDoerflein (LTD)

BBores (RJB)  !

SDroggitis (SCD)

RArchitzel (REA)

CCraig (CMC 1)

LSpessard (RLS)

RCorreia (RPC)

RLatta (RML1)

EHackett (EMH1)

AMurphy (AJM1)

TMartin (TOM 2)

DMartin (DAM 3) j GMeyer (GWM)

WMcDowell(WDM)

SStewart (JSS1)

THiltz (TGH)

SDroggitis (SCD)

DSolorio (DLS2)

PDLR Staff

BGE Requests for Additional information Tracking Sheet Subject Section Letter Date # Questions Remarks Feedwater 5.9 02/13/98 39 Questions 5.9.1 through 5.9.39 Feedwater 5.9 09/01/98 18 Questions 5.9.40 through 5.9.57 Feedwater(Revision) 5.9 09/07/98 7'  % E"_'**"","i" WL%o2nm .- 7 Replacement nos.: 5.9.1,5,18,19, and 35. Withdrawn nos.: 5.9.8, 9,10,15, 21, 24, 32, 33, 34, and 39.

Diesel Fuel Oil 5.7 02/19/98 16 Questions 5.7.1 through 5.7.16 Diesel Fuel Oil (Revision) 5.7 09/07/98 02  ;.ygssyy,w ama w yy_ wm Replacement Question nos.: 5.7.1 and 5.7.4 Diesel Fuel Oil 5.7 09/03/98 3 Questions 5.7.17 through 5.7.19 Cables 6.1 07/09/98 15 Questions 6.1.1 through 6.1.15 Rad Monitoring 5.14 08/06/98 3 Questions 5.14.1 through 5.14.3 Component Cooling Water 5.3 08/11/98 3 Questions 5.3.1 through 5.3.3 Enclosure i

a :

I

~

2  !

i Component Cooling Water 5.3 08/27/98- 4 Questions 5.3.4 through 5.3.7 -

Compressed Air 5.4 08/21/98 9 Questions 5.4.1 through 5.4.9 Aux Feedwater 5.1 08/21/98 3 I

Questions 5.1.1 through 5.1.3 j Aux Feedwater 5.1 09/01/98 5

. Questons 5.1.4 through 5.1.8  ;

RPV & CEDMs 4.2 08/26/98 26 Questions 4.2.1 through 4.2.26 Cranes & Fuel Handling 3.2 08/26/98 16 f Questions 3.2.1 through 3.2.16 i Mr:n Steam 5.12 08/31/98 10 Questions 5.12.1 through 5.12.10 SFP Cooling 5.18 09/01198 10 Questions 5.18.1 through 5.18.10 HVAC 5.11C3 09/01/98 1 '"*^C*"*""*"**"5"*""5"""*"""'

Question 5.11.1

'"*^C- "*""**"5"*""5"*"""****

HVAC 5.11 A8 09/04/98 1 Question 5.11.2 <

HVAC 5.11B' 09/04/98 6 '"*^C*"""****"*"""5"'""5"*"""**""'  !

e Questions 5.11.3 through 5.11.8

3-

- t HVAC 5.11 09/04/98 11 Questions 5.11.9 through 5.11.19 RCS 4.1 09/02/98 4 l ,

t Questions 4.1.1 through 4.1.4 l I RCS 4.1 09/03/98 16 t

Questions 4.1.5 through 4.1.20 RCS With RPV & CEDMs 4.1 (& 4.2) ! 09/03/98* 6' L 5" *"_* "' *'*f,%8"* di""jdg L*'e,'"' " 8"* * "" """*""5 Questions 4.1.21 through 4.1.26  ;

Safety injection 5.15 09/02/98 3 l Questions 5.15.1 through 5.15.3

~ " " " * * * " " * " " " * " " * " " " " "

Safety injection 5.15 09/03/98* 10 t

i Questions 5.15.4 through 5.15.13 t Fire Protection 5.10 09/02/98, 4 Questions 5.10.1 through 5.10.4 Fire Protection 5.10 09/04/98 4 i Questxms 5.10.5 through 5.10.8 j Service Water 5.17 09/03/98 7 i r

F Questions 5.17.1 through 5.17.7 TLAA 2.1 09/02/98 4  ;

Questions 2.1.1 through 2.1.4 7 09/02/98 225 5"'= "r ""' * * *=ead '" *=*= e i Fatigue  :

Questions 7.1 through 7.22  ;

r

4 ,

8 09/04/98 * ***"*"""'****"""'*""5 GSl & EQ 35 Questions 8.1 through 8.3 2

RPV Intemals 4.3 09/03/98 24 Questions 4.3.1 through 4.3.24 m s- ns,4 Supports 3.1 09/07/98 28s Questions 3.1.1 through 3.1.28 Containment isolation 5.5 09/02/98 5 i Questions 5.5.1 through 5.5.5 Containment Spray 5.6 09/02/98 5 Questions 5.6.1 through 5.6.5  ;

Containment Spray 5.6 09/03/98 5 Questions 5.6.6 through 5.6.10 Structures 3.3A 09/07/98 267 wouco. n. n .s.a33=,o, nn.

! Questions 3.3.1 through 3.3.26 Structures 3.38 09/07/98 57 w mucu. n. - se 3 3 = nn.

Questions 3.3.27 through 3.3.31 i Structures 3.3C 09/07/98 77 w - n. , a-s.a33wr _.

I a

Questions 3.3.31 through 3.3.37 Structures 3.3D 09/07/98 47 w ,uco. n. n - s.a 3 3 = -- ,

i Questions 3.3.38 through 3.3.41 ,

1  !

, Structures 3.3E 09/07/98 15 7 wm,uco. n.o n a-s.a3=ru .

l ,

Questions 3.3.42 through 3.3.56 i i

I

4 5 -

-t Electrical Commodities 6.2 l- 00ln7/oa 1e I Questions 6.2.1 through 6.2.6 l 3

Emerg. Desel Generator 5.8 08/27/98 9 Questions 5.8.1 through 5.8.9 '

Chemistry 9 08/27/98 45 'S"*"" *****"*""""*-a  ;

i Questions 9.1 through 9.4 '

Scoping 10 08/27/98 15 * * * * * * -"*"=a l

Question 10.1 t CVCS 5.2 09/03/98* 8 **"*"-""**"o-*

. Questions 5.2.1 through 5.2.8 Saltwater 5.16 08/28/98 3 1

Questions 5.16.1 through 5.16.3 t

Saltwater 5.16 09/03/98* 3 **"*"""~""""*"*"'"8-*

Questions 5.16.4 through 5.16.6 11 08/28/98 65 * *****"""*"*"a Generic (ARDI)

Questions 11.1 through 11.6 Instrument Lines 6.4 None 0 NSSS Sample 5.13 None 0 .

l Total 453 l 1 i