ML20151V023

From kanterella
Jump to navigation Jump to search
Forwards Const Appraisal Team Insp Repts 50-498/85-21 & 50-499/85-19 on 851021-1101 & 12-22 & Potential Enforcement Actions.Deficiencies Noted Include Mods of Wiring for motor-operated Valves
ML20151V023
Person / Time
Site: South Texas  
Issue date: 02/05/1986
From: Taylor J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Goldberg J
HOUSTON LIGHTING & POWER CO.
Shared Package
ML20151V027 List:
References
CON-#186-041, CON-#186-41 OL, NUDOCS 8602110177
Download: ML20151V023 (15)


See also: IR 05000498/1985021

Text

d[e a%

9

jo,,

UNITED STATES

NUCLEAR REGULATORY COMMISSION

o

{ .

,E

WASHINGTON. D. C. 20555

k . . . . . .o#

February 5, 1986

D:cket Nos. 50-498

and 50-499

-

Houston Lighting and Power Company

ATTN:

'4r. J. H. Goldberg

Group Vice President - Nuclear

P. O. Box 1700

Houston, TX 77001

Gentlemen:

SUBJECT:

CONSTRUCTION APPRAISAL TEAM INSPECTION 50-498/85-21 AND 50-499/85-1

Enclosed is the report of the Construction Appraisal Team (CAT) inspection

conducted by the Office of Inspection and Enforcement (IE) on October 21-

November 1 and November 12-22, 1985, at the South Texas Project site.

The

Construction Appraisal Team was composed of members of IE, Region IV, and a-

number of consultants.

The inspection covered construction activities

authorized by NRC Construction Permits CPPR-128 and CPPR-129.

This inspection is the fourteenth in a series of construction appraisal

inspections conducted by the Office of Inspection and Enforcement.

The

results of these inspections are being used to evaluate the management control

of construction activities'and the quality of construction at nuclear plants.

The enclosed report identifies the areas examined during the inspection.

Within these areas, the effort consisted primarily of detailed inspection of

selected hardware subsequent to quality control inspections, a review of

selected portions of your Quality Assurance Program, examination of procedures

and records, and observation of work activities.

Appendix A to this letter is an Executive Summary of the results of this

inspection and of conclusions reached by this office.

This inspection identi-

fied a number of significant deficiencies.

These included hardware and design

control deficiencies which in most cas'es resulted from weaknesses in your

construction program.

The significance of the identified deficiencies was

generally acknowledged in the actions taken by your site organizations during

and immediately after the NRC CAT inspection.

These actions included:

the

initiation of appropriate nonconformance reports and other corrective action

documentation; a voluntary stop work order for all construction and startup

activities involving the modification of wiring for motor operated valves; and

your notifications to our Region IV office of certain deficiencies potentially

reportable under 10 CFR 50.55(e).

We are concerned by the significance, implications and the occurrence of

identified deficiencies in various areas of construction which were inspected.

IE01

g21bc

OIOb

90

4ggg Copy to RCPB, IE

G

PDR

1

\\

j

Houston Lighting and Power Company

-2-

February 5,1986

These areas include:

the modifications of wiring for motor operated valves;

the uncontrolled modification of design change documents; the configuration of

molded case circuit breakers with load-side terminal extensions and insulation

barriers ~in vendor supplied motor control centers; the retrievability, location

and availability of radiographic film and documentation from balance of plant

suppliers; and certain quality control accepted installations of instrumenta-

tion and tubing, socket welds in 2-inch Schedule 160 piping, mechanical equip-

ment, and bolting for structural steel sliding connections.

Additional manage-

ment attention is required for these and the other areas of construction

discussed in Appendix A to ensure that completed installations meet design

requirements and that appropriate and timely corrective action is taken to

prevent the recurrence of construction program weaknesses which were the cause

of the identified hardware deficiencies.

The significance of certain NRC CAT findings were mitigated due to the correc-

tive actions you have already initiated to resolve like findings of your

self-initiated pre-CAT inspection.

Examples of these include:

the planned

corrective action for the identification of deficiencies in the separation of

electrical raceways, the program improvements you have implemented for the

inspection or reinspection of piping supports / restraints, and your reported

plans for the reinspection of structural steel.

These activities are recog-

nized as contributing directly to providing the required assurance of the

quality of construction for your project.

However, we are concerned with the

timeliness of some of these planned corrective actions. An example is your

plan for delaying plant walkdowns for the identification of problems with

electrical raceway separation and the delay in implementing the program you

have developed for the identification of improper clearance between piping,

supports / restraints and other hardware.

The delay in implementation of these

corrective actions, in our opinion, increase the likelihood of further problems

and could cause delays in the satisfactory completion of construction at the

South Texas Project.

We have recently received a copy of your January 10, 1986 letter to Mr. Robert

D. Martin relating to actions being taken to address project areas requiring

improvement. Your letter will be included as part of our continuing review of

this matter.

Appendix B to this letter contains a list of potential enforcement actions

based on the NRC CAT inspection.

These are being reviewed by the Office.of

Inspection and Enforcement and the NRC Region IV Office for appropriate action.

In addition, Region IV will be following your corrective action for deficien-

cies identified during this inspection.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room.

No reply to this letter is

required at this time.

You will be required to respond to these findings

after a decision is made regarding appropriate inforcement action.

--

_

. _ . _ . , _

_ __.

__. , ---- __ . .

. . _ . - - - .

_

Houston Lighting and Power Company

-3-

February 5,1986

Should you have any questions concerning this inspection, please contact us or

'

the Region IV Office.

Sincerely,

,

Sx

/

-

ieT M.

ay1

, Director

fice of Ins ection and Enforcement

Enclosures:

1.

Appendix A, E.<ecutive Summary

2.

Appendix B, Potential Enforcement Actions

3.

Inspection Report

cc w/ enclosures:

See next page

.

p

Houston Lighting and Power Company

4-

February 5,1986

1

cc w/ enclosures:

Houston Lighting & Power Company

ATTN: Mr. M. Wisenberg, Manager

Nuclear Licensing

P. O. Box 1700

Houston, Texas 77001

Brian Berwick, Esquire

Asst. Attorney General

Environmental Protection Division

P. O. Box 12548, Capitol Station

Austin, Texas 78711

Lanny Alan Sinkin

Citizens Concerned About

Nuclear Power, Inc.

3022 Porter Street, N.W., #304

Washington, D.C.

20008

Charles Bechhoefer, Esquire

Chairman, Atomic Safety & Licensing

Board

U.S. Nuclear Regulatory Commission

Washingten, D.C.

20555

Dr. Jac.s C. Lamb, III

333 Woodhaven Road

Chapel Hill, North Carolina 27514

Frederick J. Shon

Administrative Law Judge

Atomic Safety and Licensing Board

U.S. Nuclear Regulatory Commission

Washington, D.C.

20555

Ray Goldstein, Esquire

Gray, Allison and Becker

100 Vaughn Building

807 Brazos

Austin, Texas 78701

Texas Radiation Control Program Director

(need to get address from Region IV)

.

.,

-

---n

.

-

,

-

- - - , - - , - ,

,n.,

-.-

, -,

---, --

-

o

,

Houston Lighting and Power Company

5.

February 5,1986

Distribution

DCS'(DocketNo.50-498and50-499)

NRC PDR

Local PDR

DI Reading

RCP8 Reading

JMTaylor

RVollmer

JPartlow

RSpessard

BGrimes

EJordan

JAxelrad

HThompson

TNovak

VNoonan

P. Kadambi

WPaton

AE00

-OELD

NMSS

RES

ACRS(10)

NSIC

NTIS

Regional Administrators

Regional Division Directors

HBoulden, OIA

SECY

OPE

OCA (3)

VStello

HDenton

CAT Members

Resident Inspector

RHartfield

INP0

All Licensees (Distribution IS)

i

'I:IE

RC 3:DI:IE

DD:D .IE

DI

IE

D );l

Dl'j. E

L

nich/vj

RHeishman

JPartlow

Filber

lor

RS .s,sard

j 01 p

0

Olg,ee

e y ee

y ,ee

ee

e

,

%

.

.

.

. .

.

. . .

. . .

. .

.

.

.

.

.

,

-

---

---

- - - - - - - - _ - _ _ _ _ - - - _ - -

APPENDIX A

EXECUTIVE SUMMARY

An announced NRC Construction Appraisal Team (CAT) inspection was conducted at

Houston Lighting and Power's South Texas Project (STP), Units 1 and 2, during the

period October 21-November 1 and November 12-22, 1985.

OVERALL CONCLUSIONS

Hardware and documentation for construction activities were generally in

accordance with requirements and licensee commitments.

However, the NRC CAT

did identify a number of hardware deficiencies that in most cases have resulted

from construction program weaknesses.

These include:

1.

A lack of effective design change control between the architect / engineer

(AE) and the nuclear steam system supplier (NSSS) which has resulted in

the inability to correlate the actual wiring configuration of valve motor

operators with design. The actions taken for prior site organization

audit findings involving the adequacy of AE/NSSS design interface of the

wiring design in another area also indicate a weakness in the applica-

tion of corrective action measures.

In addition, a significant number of

hardware and workmanship deficiencies were identified with the wiring of

motor operated vahes.

2.

Significant deficiencies in the configuration of Class 1E molded case

circuit breakers with load-side terminal extensions and insulating

barriers indicate that the licensee's inspection program was ineffective.

The indicators of this ineffectiveness include source surveillance,

receipt, and field cable termination inspections that failed to identify

and correct these conditions.

3.

A number of installation and procedural deficiencies were identified in

mechanical equipment and in bolting of valve flange pipe installations for

which Quality Control (QC) inspections had been completed.

The omission

of a vendor tolerance dimension on the installation instructions for the

mounting of annubar flow probe devices indicates a weakness in the design /

construction interface.

4.

The numerous instances of overtightened bolts in structural steel sliding

connections indicates that the licensee's installation and inspection

programs were particularly ineffective in this area.

Certain licensee

evaluations performed during the inspection to address NRC CAT concerns

are considered questionable.

These include questions related to the

extent the clay layer beneath the Essential Cooling Water (ECW) piping

will expand .pon cessation of the dewatering system and the potential of

this occurrence to over stress the ECW piping, the potential for addi-

tional forces to be exerted on the Unit 2 tendon access wall due to the

omission of the 3-inch seismic joint, and the effect of the practice of

cross flange welding on the design strength of loaded structural steel.

A-1

5.

A lack of traceability of fasteners for electrical equipment, certain

vendor supplied equipment assemblies and bolting used in cable tray and

conduit supports was identified by the NRC CAT.

These deficiencies were

magnified by the AE's change to a specification in the electrical area to

delete the requirement for the manufacturers' marking on fasteners.

6.

Certain areas of weakness were experienced during the inspection of

design change control.

In addition to the matter of motor operated valves

discussed above, these included the control of the modification of design

changes during their incorporation into design drawings; .the undocumented

use of engineering judgment in lieu of explicit or generic calculations

for ensuring the adequacy of design in certain design change documents;

and the conflicting definitions for configuration control packages in

issued revisions of governing procedures (Bechtel, EDP 4.72 and

WPP-22.0, and Ebasco, ASP-17).

7.

Additional areas of weakness were found in the applicattun of correc-

tive action measures for the previously identified significant deficien-

cies in the maintenance of permanent plant equipment during the construc-

tion phase.

The operations maintenance program does not address whether

an identified deficiency could affect the equipment's ability to perform

its design function or its operational maintenance program.

Also, weak-

ness was found in the control of " HOLD" tags.

8.

Weaknesses were found in the area of nondestructive examination records

for balance of plant suppliers.

This included a weakness in the licensee

program for audit review and acceptance of these records.

In addition,

after the radiographs for the reactor vessel head were discovered to

be missing in May 1985, the licensee's scope of corrective actions did

not address whether the records of balance of plant suppliers performing

nondestructive examination activities may be similarly affected.

9.

A significant number of reworked conduit installations were lacking QC

reinspection for bolt torque.

This indicates a weakness in the program

for inspection of installations reworked after initial QC acceptance.

10.

The project's response to identified deficiencies in electrical raceway

separation was questioned.

The decision was made to postpone further

separation inspections until the time of area turnover.

The NRC CAT is

concerned with modifications to correct separation deficiencies that

may adversely affect plant systems already accepted and turned over to

startup or operations, in addition to being more difficult to identify

after construction is completed.

This concern was also raised by the STP

pre-CAT verification team.

These construction program weaknesses indicate that additional management

attention is required to assure that completed installations meet design

requirements.

1

i

i

A-2

i

-

-

.

.

.

-

.

- -

.

.

.

.

.

-

-

AREAS INSPECTED AND RESULTS

Electrical and Instrumentation Construction

The samples of electrical construction inspected generally met the applicable

design requirements and installation specifications.

However, several signifi-

cant design and construction deficiencies in electrical construction, and

numerous installation discrepancies in instrumentation construction were

identified.

The configuration of molded case circuit breakers with load-side terminal

extensions and insulating barriers in installed Class IE motor control centers

was found to be deficient in that the potential for phase-to phase faulting or

inadvertent circuit interruption exist.

Relevant inspection activities, which

had been completed, including source surveillance, receipt inspection, and field

cable termination inspection did not identify these deficiencies.

Additionally,

the seismic qualification of equipment which exhibits this configuration could

not be verified.

Hardware and workmanship deficiencies were found in all of the 16 installed

motor operated valves inspected by the NRC CAT.

In addition, lack of adequate

design and installation control for the wiring of motor operators supplied by

Westinghouse Corporation (NSSS vendor) and further modified by the architect /

engineer resulted in various organizations not being supplied the required

wiring configuration documents.

Numerous dimensional and workmanship deficiencies were found in the instrumen-

tation construction sample inspected.

This included an installation which had

undergone the licensee's QC Effectiveness Inspection conducted after final

construction QC inspection and turnover to the startup organization.

Examples

of these deficiencies include dimensions exceeding tolerance limits on five

installations, an incorrect weld configuration on a support, a missing support

clamp, and a support installed in accordance with an incorrect drawing detail.

In addition, attachments were being made to existing supports without the

required engineering review and approvals.

Several items of Class 1E equipment were found to deviate from their

applicable specification requirements.

These included the mislocation of

terminal strips and fewer than the required minimum number of terminal block

points in several switchgear cubicles, the absence of required vendor installed

terminal lugs on three fan motors, and the incorrect insulation class for a

pump motor.

The conduit strap bolts for a significant number of the conduit installations

inspected did not exhibit the required torque seal.

Since this is due to

their removal and reinstallation without reinspection by QC, increased controls

are required for inspection of rework of QC accepted conduit installations.

Mechanical Construction

Piping, pipe supports / restraints, concrete expansion anchors and heating

ventilation and air conditioning hardware (supports / restraints, duct sections,

fire dampers) were generally found to be installed in accordance with require-

ments or with deficiencies that generally had previously been identified.

However, significant deficiencies were identified in two areas of piping

A-3

. -

- -

-

installation.

These included the design tolerance dimension error applicable

to the mounting of numerous annubar flow probes and the alternate bolting used

in lugged wafer valves.

A significant number of hardware deficiencies were identified in ten of the

twelve mechanical equipment items inspected.

The sample of equipment was

diverse and included:

the reactor water makeup tank, various pumps (RHR,

containment spray, and low and high head safety injection), charging pump

coolers, EAB return air fan, and a fuel handling building filter.

The identi-

fied deficiencies included items such as:

the uncontrolled removal of speci-

fied tank cushion material (FLEXCELL), incorrect / indeterminate fastener

material, missing shim for an equipment mounting pad, a damaged foundation beam

flange, welding of a gussett plate to the edge of embed which exceeded speci-

fied tolerances, missing and undersized welds, and bolt holes not per drawing.

The number and significance of the deficiencies identified, indicated a lack of

overall effectiveness in the installation and inspection programs for mechani-

-

cal equipment.

Welding and Nondestructive Examination

Welding and nondestructive examination activities were generally found to be

conducted in accordance with the governing codes and specifications.

However

a number of examples were found where completed structural welds in pipe

supports / restraints were smaller than that specified in the design drawings

and some skewed welded connections were not supported by calculations.

Also,a

number of undersized socket welds were found in 2-inch schedule 160 piping

spools.

Some vendor supplied tanks and heat exchangers were found to have undersized

weld reinforcement in " nozzle to shell" and "manway to shell" joints.

The NRC

.

previously issued Information Notice 85-33 on the subject of undersized "ASME

'

category D" joints in tanks and heat exchangers notifying the licensees of

potentially significant deficiencies in this area.

The NRC CAT inspectors did

not find evidence that the project had reviewed the content of the information

notice for applicability to their facility.

The NRC CAT inspectors also found a small number of radiographs.which had

unacceptable weld quality.

In addition, the team encountered difficulties in

retrievability and location of vendor NDE film and documentation covering

the Balance of Plant (80P).

This indicated a need for a means to identify NDE

requirements, and the location and existence of NDE film and documentation for

,

BOP equipment supplied by vendors.

In May 1985, the project had identified

missing radiographs for the reactor head and as a result has instituted a

program requiring Westinghouse to submit monthly reports concerning status and

availability of NDE film and documentation.

The NRC CAT findings indicate that

the licensee's corrective action should have also covered the B0P suppliers.

!

Civil and Structural Construction

l

General quality of reinforced concrete construction was observed to be

l

adequate. The issue of omission of the 3-inch seismic joint relative to the

i

tendon access wall of the Unit 2 Reactor Containment Building at azimuth 304*

'

and elevation (-)13 ft and 3 inches needs to be adequately evaluated and

A-4

l

u

- - - - -

-

-

m.

-

-

... . .

n

.

_ _-____________

_

appropriate actions taken.

In general, structural steel installation appeared

to be adequate.

However, a high rate of deficiencies was identified in the

overtightening of bolting for structural steel sliding connections for which

the licensee has committed to perform a 100 percent reinspection to ensure that

bolting is torqued to the proper level.

The extent to which the underlying and adjacent clay soil layer supporting the

Essential Cooling Water (ECW) piping will swell when the dewatering system is

discontinued remains a question which requires further revi u by the licensee

and NRC.

Material Traceability and Control

The licensee's material traceability and control program was generally found

to be acceptable.

However, lack of traceability was found for fastener

materials for certain large vendor supplied mechanical equipment assemblies

mounted on skids and for certain electrical equipment.

It was also found that

engineering had deleted the requirement of the specified national standard for

manufacturers marking of fasteners intended for electrical cable tray and

conduit supports, which contributed to the resulting uncertainty of control and

traceability during and after installation.

Desian Change Control.

The design change control program was determined to be generally in accordance

with site procedures with several exceptions. These include:

The deficiencies identified with respect to the installation of

Westinghouse supplied motor operated valves indicates that a design

control weakness exists in the AE/NSSS interface at STP.

The controls for posting unincorporated design changes on design documents

were not adequately implemented at one reference station.

The control of modifications being made to change documer'.s upon their

incorporation into the design drawings.

Identified changes to the origi-

nal scope or technical content of the change document were not being

adequately documented, reviewed and approved.

The conflicting definitions for configuration control packages in issued

revisions of governing procedures of the AE and constructor organiza-

tions.

Corrective Action Systems

Appropriate corrective action systems and procedures were generally found

to be in place except for certain areas.

These include:

weaknesses in areas

involving control of fastener materials, preventive maintenance, audits and

records of radiographs, unidentified deficiencies with certain electrical

l

items (motor operated valves, motor control centers, and instrumentation

!

construction), and control of " HOLD" tags.

l

l

A-5

_

.

-

-

-

.

-____________ .

APPENDIX B

POTENTIAL ENFORCEMENT ACTIONS

As a result of the NRC CAT inspection of October 21-November 1 and November 12-

22, 1985 at the South Texas Project site, the following items are being referred

to Region IV as Potential Enforcement Actions.

Section references are to the

detailed portion of the inspection report.

1.

10 CFR 50 Appendix B, Criterion III, as implemented by the South Texas

Project (STP) Quality Assurance Plan (QAP) Section 3.0, requires that

measures be established for the identification and control of design

interfaces and coordination among design organizations.

These measures

shall include the review, approval, release, distribution, and revision

of documents involving design interfaces.

Contrary to these requirements, at the time of this inspection:

a.

The licensee failed to provide adequate interface between the design

organizations (architect / engineer (AE), and the nuclear steam system

supplier (NSSS)), and the organizations performing the physical work.

This was evidenced by the inability of the licensee to provide a

design baseline wiring drawing for NSSS supplied motor operated

valves, the AE's revised designs not being provided to the NSSS for

their review and incorporation into NSSS drawings, and the inability

to correlate the actual wiring with current design documents.

(Section II.B.3.b.(8))

b.

Vendor tolerance requirements for the mounting dimension of the

annubar flow probe on essential cooling water piping were not

included on installation drawings and subsequently a number of

annubar mounting flanges were mislocated with respect to the distance

from the pipe outer wall.

(Section III.B.I.b).

2.

10 CFR 50 Appendix 8, Criterion III, as implemented by the STP QAP

Section 3.0, requires that design control measures provide for verifying or

checking the adequacy of design and that design changes, including field

changes, shall be subject to design control measures ccmmensurate with

those applied to the original design.

Contrary to these requirements, at the time of this inspection:

a.

The licensee could not provide calm stions or documented engineering

jtdgment to substantiate the design edequacy of the addition of four

bays of structural steel detailed on the November 5, 1984 revision of

Bechtel drawing No. 3M01-9-S-4043. (dection VII.B.3.b.(5))

b.

Six field change request (Nos. BC-01202, CC-03426, CC-04949,

CC-04461, BS-1-0194, and 85-1-0235) and one drawing change notice

(No. 7) were modified upon incorporation into the design drawings

without being adequately reviewed, approved and documented to reflect

l

changes in technical content or scope.

(Section VII.B.3.b.(2))

i

l

B-1

-

-

-

.

.

-

.

-

3.

10 CFR 50 Appendix B, Criteria VII, as implemented by the STP QAP Section

,

7.0., requires that measures be established to assure that purchased

equipment conform to the procurement documents.

These measures shall

provide objective evidence of the quality furnished by the contractor or

subcontractor.

<

Contrary to these requirements, at the time of this inspection:

a.

The licensee failed to identify the deficiencies in the bolting of

load-side terminal extensions and in the insulating barriers supplied

with certain molded case breakers in motor control centers.

These

deficiencies have the potential for causing phase-to phase faulting

or inadvertent circuit interruption.

Further, the licensee was not

able to confirm that the load-side terminal extensions or insulating

barriers were seismically qualified.

(Section II.B.3.b.(4))

b.

The NRC CAT inspectors found several deficiencies in vendor supplied

components.

The deficiencies included undersized welds in tanks and

heat exchangers and radiographs which did not have the required weld

and film qua'ity. These also include SKV switchgear cubicles with

mislocated terminal strips and terminal blocks with less than the

minimum required terminal points, fan motors which did not have the

required vendor installed terminal lugs, and a pump motor without the

i

required class of insulation.

(Sections II.B.3.b and IV.B.10.b with

Table IV-5 and Table IV-6)

4.

10 CFR 50 Appendix B, Criterion VII, as implemented by the STP QAP Section

7.0, requires documentary evidence that material and equipment conform to

the procurement requirements shall be available at the plant site prior to

installation or use of such material and equipment.

This documentary

evidence shall be retained at the nuclear power plant site and be suffi-

cient to identify the specific requirements, such as codes, standards, or

specifications, met by the purchase material and equipment.

Contrary to the requirements, at the time of this inspection the licensee

could not determine the location of NDE film and documentation required by

engineering specifications as documented evidence of the quality of welding

for equipment and hardware procured from various vendors for the balance

of plant equipment.

(Section IV.B.10.b)

5.

10 CFR 50 Appendix B, Criterion VIII, as implemented by the STP QAP

Section 8.0, requires that measures be established for the control of

materials, parts and components to prevent the use of incorrect or defec-

tive items.

Contrary to these requirements, at the time of this inspection it was

determined that traceability and control of some fasteners, including

bolting for mechanical and electrical equipment of various types, and

the unmarked bolting for electrical cable tray and conduit supports, has

not been adequate to assure the use of correct materials.

Also, the

deletion of the requirement for marking of fasteners required to comply

with national standards contributed to the loss of traceability and

control of the referenced unmarked bolting.

[Section VI.B.1.b (3)(c), (d)

and (f)]

B-2

-

- -

-

-

-

- _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _

,

6.

10 CFR 50 Appendix B, Criterion X, as implemented by the STP QAP Section

10.0, requires that a program for inspection of activities affecting

quality be established and executed by or for the organization performing

the activity to verify conformance with the documented instructions,

procedures and drawings for accomplishing the activity.

Contrary to the above requirements, at the time of this inspection, the

licensee's inspection program was ineffective in that:

a.

Numerous deficiencies were identified with the installation of QC

accepted instrumentation and instrument tubing.

Examples of these

deficiencies include dimensions exceeding tolerance limits on five

installations inspected, an incorrect weld configuration on a tubing

support, a missing support clamp, and a support installed in accord-

ance with an incorrect drawing detail.

The specific installations

'

and deficiencies are detailed on Table II-7 of the report.

(Section

II.B.4.b)

b.

A number of undersized socket welds were found in 2-inch schedule

160 piping.

Additional examinations of approximately 200 QC accepted

field welds of this type found at least 15 percent to be undersized.

(Sections III.B.1.b and IV.B.1.b)

c.

On six lugged wafer valves, hex-head cap screws had been substituted

for threaded studs and nuts inconsistent with the applicable essen-

i

tial cooling water piping installation isometric drawing and/or bill

of materials.

(Section III.B.1.b)

.

d.

Ten of the twelve mechanical equipment items selected for NRC CAT

-examination included components which were not constructed or other-

wise installed in accordance with applicable design or specified

installation requirements.

(Section III.B.4.b. and Table III-5)

e.

A number of examples were found where completed structural welds in

pipe supports / restraints in welded joints were smaller than that

specified in the design drawings.

The list of these welds is in

Table IV-1.

(Section IV.B.1.b)

f.

More than 60 percent of the inspection sample of 68 high strength

bolts for structural steel sliding connections were installed over-

tight.

Installation and inspection requirements had not been

l

translated into appropriate procedures ensuring proper installation

of the bolts in a ' snug tight" condition.

(Section V.B.2.b)

,

g.

Strap bolts on 8 of the 28 conduit runs inspected did not exhibit

the required torque seal.

Reinspections for torque had not been

,

accomplished following rework to QC accepted conduit installations.

(Section II.B.1.b.(2))

7.

10 CFR 50 Appendix B, Criterion XVI, as implemented by the STP QAP Section

16.0, requires that measures shall be established to assure that condi-

tions adverse to quality such as failures, malfunctions, deficiencies,

deviations, defective material and equipment, and nonconformances are

i

promptly corrected.

In the case of significant conditions adverse to

i

quality, the measures shall assure that the cause of the condition is

>

determined and corrective action taken to preclude repetition.

<

B-3

l

.

- -

-

.

-

- -

.

- -

- _ _ - - - _ - _ _ _

i

Contrary to these requirements, at the time of the inspection the licen--

see's corrective actions were found to be inadequate in that the balance

- of plant suppliers of NDE film and documentation were not included in the

corrective actions taken after the radiographs for the reactor vessel head

were discovered to be missing in May 1985.

,

!

i

l

?

l

!

l

l

l

l

!

!

!

B-4

l --

_ _ __ _ -- _ _- - .--- _ ---- - - - - - - - - - - - - - _ - - - - - - - -

- - - - - - -

- - - . - - - - - - - -

--

-

-

-