Text
__
May 7, 1985 MEMORANDUM FOR:
Harold R. Denton, Director Office of Nuclear Reactor Regulation FROM:
Hugh L. Thompson, Jr., Director Division of Licensing Office of Nuclear Reactor Regulation
SUBJECT:
"SH0LLY" STATISTICS Enclosed is the update of the Sholly statistics covering the period May 6, 1983 through April 23, 1985.
No additional comments nor reqrtsts for hearings were received.
The next monthly FRN is schedu.e' for publication on May 22,1985, after which the statistics w'll be updated.
Yrdnll E rnglh/for Hugh L. Thompson, Jr., Director Division of Licensing Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
NRR Division Directors NRR Deputy Directors DL Assistant Directors DL Branch Chiefs DL* Licensing Assistants OELD Lars Solander, PRAB CONTACT:
os) Pat Kreutzer X29516
///3
/
ORB #a:DL ORh3iDL A
R:DL p'
Pp/ hj /85
,eatzer;ef JRMiller 0 Lainas
/i om son
,}/,/85 g / [A85 4/f/85 f
~
WO5T702 7(o p 44
d "SH0LLY" STATISTICS May 6,1983 - April 23,1985 Monthly FRN Individual FRN Individual FRN Total Proposed NSHC Proposed NSHC SHC NUMBod 1739 285 28 2052 Period for public comment:
30 days 1739 267 28 2034 Less than 30 days:
Short FRN 18 18 Press release 9
2 Grand Gulf 8 TMI-1 1 Oyster Creek 1 Susquehanna 0
141/
Public comments received 1 LaSalle-2 1 WNP-2 2 TMI-1 2 Trojan 1 Pilgrim Requests for' hearing 1 Grand Gulf 1 Salem-1 2 Zion 1/2 152/
6 Turkey Pt. 3/4 Amendments issued - Total -----------------------------------------------------------------
1301 (1) with 30 days notice -----------------------------------------------------------------
1231
( 2 ) l es s tha n 3 0 days o r no no t i ce ------------------------------------------------------
59 (3) Hearing requested but final NSHC determination made (50.91(a)(4)) -------------------
105/
(4) Proposed NSHC; hearing requested.
Hearing completed and amendment issued.
No final NSHC determination was made because hearin 4/
amendment was needed ------------------------------g was completed before 3
Backlog:
(applications received which have not been noticed,,either in monthly FRN or individually through April 23, 1985
): NUMBER 295 (Includes items which have been prepared and approved for publication in May monthly, itens which are in concurrence, and items for which additional information is needed from the licensee.
FOOTNOTES: See pages 2 and 3.
FOOTNOTES FOR "SHOLLY" STATISTICS 1/ Comments Grand Gulf 2 comments, one from State, one from a member of the public.
TMI-1 7 comments received as result of initial noticing action, I additional comment received as a result of Notice of Additional Opportunity published on August 25, 1983.
Susquehanna I comment received from a member of the public.
Oyster Creek I coment received from State.
WNP-2 1 comment received from a member of the public.
LaSalle 2 I coment received from local government.
,2] Requests for hearing TMI Steam generator repair - 2 requests for hearing received.
Prehearing conference held. By a Memorandum and Order dated June 1,1984, Board dismissed 9 of 11 contentions.
Hearing concluded July 18, 1984.
Staff's proposed findings submitted August 20, 1984. Board issued Decision on October 31, 1984.
Salem Integrated leak rate - 1 request for hearing received from State of Delaware. On January 20, 1984, State filed a motion to withdraw which was granted by Board on January 25, 1984 Turkey Pt. 3/4 - (a) Proposed operational limits for current and future reloads - 2 requests for hearing (2 units).
Prehearing conference held
- February 28, 1984 Discovery in process.
(b) Spent Fuel Storage Expansion - 2 requests for hearing (2 units).
(c) Enriched fuel storage
- 2 requests for hearing (2 units). Nuclear Responsibility Inc. and Joette Lorf an petitioners in all three issues.
Pilgrim - Single loop operation - 1 request for hearing. Proceeding dismissed January 26, 1984 based'on settlement.
Grand Gulf - Amendment No.10 redefined HPCS operation and resulted in a calculated increase in peak clad : temperature. One hearing request received. Prehearing conference held February 29, 1984. ASLB issued decision on April 23, 1984 admitting two contentions for discovery. On September 24, 1984, ASLB issued Memorandum and Order Terminating Proceeding.
Trojan - Spent fuel pool expansion - 2 requests for hearing,1 from State and 1 from Coalition for Safe Power. Both admitted as parties to proceeding..
Prehearing conference held, two contentions accepted. Coalition withdrew from proceeding. Hearing held October 10, 1984 Initial Decision issued by Board on November 28, 1984.
Zion 1/2 - Containment leak testing - 2 requests for hearing (2 units) from Citizens Against Nuclear Power.
Licensee subsequently withdrew application.
m 2-3_/
Amendments Issued, Item (3)
TMI-1 hot testing, I amendment Salem I integrated leak testing, I amendment Turkey Pt. 3/4 operational limits for current / future reloads, 2 amendments TMI-1 hot functional testing of SG,1 amendment Trojan spent fuel pool, I amendment Turkey Pt. 3/4 SFP storage expansion 4 amendments 4/
Amendments Issued, Item (4)
TMI-1 steam generator tube repairs and return to operation, I amendment.
Pursuant to the initial Decision of the Atomic Safety and Licensing Board dated October 31, 1984, the Commission completed action on GPU's May 9,1983 application by the issuance of an amendment to the license permitting the return of the steam generators to operation. The hearing having been completed, the matter of a Final Determination of No Significant Hazards Consideration related to this amendnent was considered moot and no such determination was required or made.
W