Proposed Tech Spec Table 4.3-2, ESF Actuation Sys Instrumentation Surveillance Requirements, Reflecting Replacement of Note 5 W/Note 4 Re Slave Relay Quarterly Test Exemptions for Accumulator Discharge Isolation ValvesML20148J444 |
Person / Time |
---|
Site: |
South Texas |
---|
Issue date: |
03/18/1988 |
---|
From: |
HOUSTON LIGHTING & POWER CO. |
---|
To: |
|
---|
Shared Package |
---|
ML20148J427 |
List: |
---|
References |
---|
NUDOCS 8803300274 |
Download: ML20148J444 (8) |
|
|
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML20217A2421999-09-30030 September 1999 Proposed Tech Specs Removing Parameters No Longer Applicable & Adding Tdf Value for Model 94 SGs in Place of Reactor Coolant Sys Flow ML20211Q2361999-09-0808 September 1999 Proposed Tech Specs 3/4.8.1,revised by Relocating 18-month Surveillance to Subject Sdg to Insps IAW Procedures Prepared in Conjunction with Mfg Recommendations to Section 3.8.1.1.4.8 of UFSAR ML20211Q8071999-09-0808 September 1999 Proposed Tech Specs & Associated Bases for Specification 3/4.8.1, AC Sources, to Eliminate Requirement for Accelerated Testing of Standby DGs & Associated NRC Reporting Requirements ML20211G2281999-08-24024 August 1999 Proposed Tech Specs Pages,Relocating Cycle Specific Operating Parameters from TSs to Colr,Including Moving Location of Insert 6 from Page 6-21 to Page 6-22 of Administrative Control Section & Renumbering Methods List ML20211C0371999-08-18018 August 1999 Proposed Tech Specs 3.4.9.3 Re Cold Overpressure Mitigation Curve Associated with Replacement SGs ML20209G9351999-07-15015 July 1999 Proposed Tech Specs 3.7.1.6 Re Atmospheric Steam Relief Valves ML20209G4461999-07-13013 July 1999 Proposed Tech Specs,Modifying 3.6.3 Action B,Clarifyin Use of Check Valve with Flow Through Valve Secured as Means to Isolated Affected Containment Penetrations ML20209C1511999-07-0101 July 1999 Proposed Tech Specs Pages Re Amend to License NPF-80, Changing TSs 3.3.2 & 3.7.8 Allowing All Fuel Handling Bldg Exhaust Air Sys Components to Be Inoperable for Period of 8 Hours to Facilitate Repair of Train B Exhaust Booster Fan ML20209B5341999-06-24024 June 1999 Proposed Tech Specs Section 6.9.1.6.a,adding Min Measured RCS Flow,Which Lists Parameters Included in COLR ML20195E4701999-06-0707 June 1999 Proposed Tech Specs Pages Re Proposed Amend to Licenses NPF-76 & NPF-80,deleting Total Allowance,Sensor Error & Z Terms from ESFAS & RTS Instrumentation Trip Setpoint Tables of TS 2.2.1 & 3.3.2 ML20195E4211999-06-0707 June 1999 Proposed Tech Specs,Relocating cycle-specific RCS-related TS Parameter Limits to COLR ML20205S3511999-04-19019 April 1999 Proposed Tech Specs Bases Page 3/4 8-3 Removing Reference to Fast Transfer Capability That Is Inconsistent with STP Design Bases as Described in UFSAR Chapters 8.2 & 8.3 ML20205G8081999-03-30030 March 1999 Proposed Tech Specs,Relocating Section 3/4.3.3.4, Meteorological Instrumentation & Associated Bases Description to STP Trm,Per NUREG-1431 ML20204J9681999-03-22022 March 1999 Proposed Tech Specs Incorporating New TS for Atmospheric Steam Relief Valve Instrumentation & Revising TS 3.7.1.6 Re Atmospheric Steam Relief Valves ML20204D1581999-03-15015 March 1999 Proposed Tech Specs 3/4.7.9 for Snubbers to TRM ML20207D9651999-03-0202 March 1999 Proposed Tech Specs Change Clarifies Use of Check Valve with Flow Through Valve Secured as Means to Isolate Containment Penetration in TS 3.6.3 Action B ML20207C4721999-02-24024 February 1999 Proposed Tech Specs Bases 3/4.2.5,clarifying That Averaging of Only Three Channels Is Min Expected When Verifying DNB Parameter Compliance ML20202G6871999-01-26026 January 1999 Proposed Tech Spec Page 3/4 4-39,revising TS 4.4.10 for Alternate ISI of RCP Flywheels ML20199K5681999-01-20020 January 1999 Proposed Tech Specs Surveillance Requirement 4.7.1.2.1.a Re AFW Pump Performance Testing ML20198A2181998-12-10010 December 1998 Revised TS Pages,Adding Ref to TS Figure 2.1-2 to Bases Section 2.1.1 as Figure Provides DNBR Curves Appropriate to Alternate DNB Operating Criteria ML20198A1951998-12-0909 December 1998 Corrected TS Bases Pages B 3/4 8-15,-16 & -17,as Discussed During 981103 Telcon ML20196B8121998-11-23023 November 1998 Proposed Tech Specs Pages for Proposed Amends to Licenses NPF-76 & NPF-80,relocating Descriptive Design Info from TS 3/4.7.1.1 (Table 3.7-2) Re Orifice Sizes for Main Steam Line Code Safety Valves,To Bases Section ML20155J9031998-11-0303 November 1998 Proposed Corrected Tech Specs Bases 3/4 9-3 Re Water level- Refueling Cavity & Storage Pools ML20155D5561998-10-29029 October 1998 Proposed Tech Specs Pages for Proposed Amends to Relocate Snubber TS 3/4.7.9 to TRM ML20155D5801998-10-29029 October 1998 Proposed Tech Specs Pages for Amends to Relocate Portion of TS Surveillance Requirement for DG Fuel Oil Storage Tank to TRM ML20155D5441998-10-29029 October 1998 Proposed Tech Specs Pages for Proposed Amend to Relocate Turbine Overspeed Protection TS 3/4.3.4 to TRM ML20154M1621998-10-12012 October 1998 Revised Tech Specs Bases Pages B3/4 8-14 Through -17 ML20154C5071998-09-30030 September 1998 Proposed Tech Specs Bases Page B 3/4 9-2,removing Wording Re 10% Value for Clad Gap Iodine Isotopics ML20154C0051998-09-30030 September 1998 Proposed Tech Specs Reflecting Replacement SG Tube Insp Surveillance Differences & Deleting Provision Allowing Use of F* Alternate Repair Criteria ML20154A4281998-09-28028 September 1998 Proposed Tech Specs Re Requirements Associated with Control Room & Fuel Handling Bldg Ventilation Sys ML20151T1621998-08-31031 August 1998 Proposed Tech Specs 3.4.9.3 Re Cold Overpressure Mitigation Curve Associated W/Replacement SGs ML20238F0841998-08-28028 August 1998 Proposed Tech Specs Section 4.0.5,excluding Specified Containment Isolation Valves from ISI & Testing Requirements as Stated in Section XI of ASME Boiler & Pressure Vessel Code ML20236T5141998-07-22022 July 1998 Proposed Tech Specs Re Replacement SG Water Level Setpoint Differences ML20236R1461998-07-15015 July 1998 Proposed Changes to Current Tech Specs Bases ML20236L6311998-07-0707 July 1998 Proposed Tech Specs,Reflecting Rev of Criticality Analyses & Rack Utilization Schemes for Regions 1 & 2 of Spent Fuel Racks as Described in STP UFSAR & TSs ML20236N0001998-07-0606 July 1998 Proposed Tech Specs,Relocating RCS Design Features from TS Section 5.4 to UFSAR ML20236M6381998-07-0606 July 1998 Proposed Tech Specs,Relocating 3/4.3.3.3 Requirements for Seismic Instrumentation to Technical Requirements Manual ML20236K3481998-07-0606 July 1998 Proposed Tech Specs,Relocating 3/4.7.13 Requirements for Area Temp Monitoring Sys to Technical Requirements Manual ML20247F3321998-05-0707 May 1998 Proposed Tech Specs Pages,Reflecting Replacement SG Reactor Coolant Flow Differences ML20217P1441998-04-0202 April 1998 Proposed Tech Specs 3.4.5 Re voltage-based Repair Criteria ML20202H9771998-02-16016 February 1998 Proposed Tech Specs Pages,Implementing 1-volt voltage-based Repair Criteria for SG Tube Support plate-to-tube Intersections ML20198C3741997-12-31031 December 1997 Proposed Tech Specs 2.1,2.2 & 3/4.2.5 for Alternate Operation W/Reduced Measured RCS Flow ML20197A7211997-12-17017 December 1997 Proposed Tech Specs Pages,Revising TS 4.6.2.1 to Extend Surveillance Interval of Containment Spray Sys Nozzle Air Flow Test from Five Years to Ten Years ML20199H2081997-11-20020 November 1997 Revised TS Bases Page B 3/4 4-15 ML20199A6101997-11-0505 November 1997 Proposed Tech Specs Pages,Updating TS Bases Section 3/4.4.9, to Reflect Results of Revised Analysis That Was Reviewed & Accepted by NRC as Part of License Amends 55 & 44.Analysis Results Not Incorporated Into TS Bases Due to Oversight ML20210T7401997-09-0404 September 1997 Proposed Tech Specs,Revising TS to Allow Use of Elbow Tap Differential Pressure Measurements Instead of Precision Heat Balance Measurements to Determine RCS Total Flow Rate ML20217M8351997-08-18018 August 1997 Proposed Tech Specs Incorporating Revs to TS 3.7.1.6, Atomospheric Steam Relief Valves, to Ensure Automatic Feature of SG Power Operated Relief Valve Remains Operable During Mode 1 & 2 ML20210L5801997-08-14014 August 1997 Proposed Tech Specs Allowing Tolerance of RCS Volume Provided in Specification 5.4.2 to Account for SG Tube Plugging ML20198F2211997-08-0505 August 1997 Proposed Tech Specs,Providing Suppl Info Re Amends to Licenses to Convert STP TS to Improved STS Format ML20148G1531997-05-29029 May 1997 Proposed Tech Specs Providing Administrative Changes to Affected Page Re Removal of Surveillance Requirement 4.7.7.e.5 1999-09-08
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARNOC-AE-000661, Rev 4 to Severe Weather Plan, Including Summary of Changes.With1999-10-0404 October 1999 Rev 4 to Severe Weather Plan, Including Summary of Changes.With ML20217A2421999-09-30030 September 1999 Proposed Tech Specs Removing Parameters No Longer Applicable & Adding Tdf Value for Model 94 SGs in Place of Reactor Coolant Sys Flow ML20211Q8071999-09-0808 September 1999 Proposed Tech Specs & Associated Bases for Specification 3/4.8.1, AC Sources, to Eliminate Requirement for Accelerated Testing of Standby DGs & Associated NRC Reporting Requirements ML20211Q2361999-09-0808 September 1999 Proposed Tech Specs 3/4.8.1,revised by Relocating 18-month Surveillance to Subject Sdg to Insps IAW Procedures Prepared in Conjunction with Mfg Recommendations to Section 3.8.1.1.4.8 of UFSAR ML20211G2281999-08-24024 August 1999 Proposed Tech Specs Pages,Relocating Cycle Specific Operating Parameters from TSs to Colr,Including Moving Location of Insert 6 from Page 6-21 to Page 6-22 of Administrative Control Section & Renumbering Methods List ML20211C0371999-08-18018 August 1999 Proposed Tech Specs 3.4.9.3 Re Cold Overpressure Mitigation Curve Associated with Replacement SGs ML20210J0481999-07-28028 July 1999 STP Unit 1,Cycle 9 Startup Testing Summary Rept ML20209G9351999-07-15015 July 1999 Proposed Tech Specs 3.7.1.6 Re Atmospheric Steam Relief Valves ML20209H2131999-07-13013 July 1999 Rev 4,revised Pages 29 & 30 of 102 to Procedure 0ERP01-ZV-IN01, Emergency Classification ML20209H3371999-07-13013 July 1999 Rev 0 to 0PGP02-ZA-0004, Station Performance Data Collection,Categorization & Reporting ML20209G4461999-07-13013 July 1999 Proposed Tech Specs,Modifying 3.6.3 Action B,Clarifyin Use of Check Valve with Flow Through Valve Secured as Means to Isolated Affected Containment Penetrations ML20209C1511999-07-0101 July 1999 Proposed Tech Specs Pages Re Amend to License NPF-80, Changing TSs 3.3.2 & 3.7.8 Allowing All Fuel Handling Bldg Exhaust Air Sys Components to Be Inoperable for Period of 8 Hours to Facilitate Repair of Train B Exhaust Booster Fan ML20209B5341999-06-24024 June 1999 Proposed Tech Specs Section 6.9.1.6.a,adding Min Measured RCS Flow,Which Lists Parameters Included in COLR ML20209H3151999-06-23023 June 1999 Rev 4 to 0PGP02-ZA-0003, Comprehensive Risk Management ML20195E4211999-06-0707 June 1999 Proposed Tech Specs,Relocating cycle-specific RCS-related TS Parameter Limits to COLR ML20195E4701999-06-0707 June 1999 Proposed Tech Specs Pages Re Proposed Amend to Licenses NPF-76 & NPF-80,deleting Total Allowance,Sensor Error & Z Terms from ESFAS & RTS Instrumentation Trip Setpoint Tables of TS 2.2.1 & 3.3.2 ML20209H3081999-06-0101 June 1999 Rev 3 to 0PGP04-ZA-0604, Probabilistic Risk Assessment Program ML20205S3511999-04-19019 April 1999 Proposed Tech Specs Bases Page 3/4 8-3 Removing Reference to Fast Transfer Capability That Is Inconsistent with STP Design Bases as Described in UFSAR Chapters 8.2 & 8.3 ML20205G8081999-03-30030 March 1999 Proposed Tech Specs,Relocating Section 3/4.3.3.4, Meteorological Instrumentation & Associated Bases Description to STP Trm,Per NUREG-1431 ML20204J9681999-03-22022 March 1999 Proposed Tech Specs Incorporating New TS for Atmospheric Steam Relief Valve Instrumentation & Revising TS 3.7.1.6 Re Atmospheric Steam Relief Valves ML20204D1581999-03-15015 March 1999 Proposed Tech Specs 3/4.7.9 for Snubbers to TRM ML20207D9651999-03-0202 March 1999 Proposed Tech Specs Change Clarifies Use of Check Valve with Flow Through Valve Secured as Means to Isolate Containment Penetration in TS 3.6.3 Action B ML20207C4721999-02-24024 February 1999 Proposed Tech Specs Bases 3/4.2.5,clarifying That Averaging of Only Three Channels Is Min Expected When Verifying DNB Parameter Compliance ML20202G6871999-01-26026 January 1999 Proposed Tech Spec Page 3/4 4-39,revising TS 4.4.10 for Alternate ISI of RCP Flywheels ML20199K5681999-01-20020 January 1999 Proposed Tech Specs Surveillance Requirement 4.7.1.2.1.a Re AFW Pump Performance Testing ML20198A2181998-12-10010 December 1998 Revised TS Pages,Adding Ref to TS Figure 2.1-2 to Bases Section 2.1.1 as Figure Provides DNBR Curves Appropriate to Alternate DNB Operating Criteria ML20198A1951998-12-0909 December 1998 Corrected TS Bases Pages B 3/4 8-15,-16 & -17,as Discussed During 981103 Telcon ML20196B8121998-11-23023 November 1998 Proposed Tech Specs Pages for Proposed Amends to Licenses NPF-76 & NPF-80,relocating Descriptive Design Info from TS 3/4.7.1.1 (Table 3.7-2) Re Orifice Sizes for Main Steam Line Code Safety Valves,To Bases Section ML20155J9031998-11-0303 November 1998 Proposed Corrected Tech Specs Bases 3/4 9-3 Re Water level- Refueling Cavity & Storage Pools ML20155D5441998-10-29029 October 1998 Proposed Tech Specs Pages for Proposed Amend to Relocate Turbine Overspeed Protection TS 3/4.3.4 to TRM ML20155D5561998-10-29029 October 1998 Proposed Tech Specs Pages for Proposed Amends to Relocate Snubber TS 3/4.7.9 to TRM ML20155D5801998-10-29029 October 1998 Proposed Tech Specs Pages for Amends to Relocate Portion of TS Surveillance Requirement for DG Fuel Oil Storage Tank to TRM ML20154M1621998-10-12012 October 1998 Revised Tech Specs Bases Pages B3/4 8-14 Through -17 ML20154C0051998-09-30030 September 1998 Proposed Tech Specs Reflecting Replacement SG Tube Insp Surveillance Differences & Deleting Provision Allowing Use of F* Alternate Repair Criteria ML20154C5071998-09-30030 September 1998 Proposed Tech Specs Bases Page B 3/4 9-2,removing Wording Re 10% Value for Clad Gap Iodine Isotopics ML20154A4281998-09-28028 September 1998 Proposed Tech Specs Re Requirements Associated with Control Room & Fuel Handling Bldg Ventilation Sys ML20151T1621998-08-31031 August 1998 Proposed Tech Specs 3.4.9.3 Re Cold Overpressure Mitigation Curve Associated W/Replacement SGs ML20238F0841998-08-28028 August 1998 Proposed Tech Specs Section 4.0.5,excluding Specified Containment Isolation Valves from ISI & Testing Requirements as Stated in Section XI of ASME Boiler & Pressure Vessel Code ML20236T5141998-07-22022 July 1998 Proposed Tech Specs Re Replacement SG Water Level Setpoint Differences ML20236R1461998-07-15015 July 1998 Proposed Changes to Current Tech Specs Bases ML20236L6311998-07-0707 July 1998 Proposed Tech Specs,Reflecting Rev of Criticality Analyses & Rack Utilization Schemes for Regions 1 & 2 of Spent Fuel Racks as Described in STP UFSAR & TSs ML20236K3481998-07-0606 July 1998 Proposed Tech Specs,Relocating 3/4.7.13 Requirements for Area Temp Monitoring Sys to Technical Requirements Manual ML20236M6381998-07-0606 July 1998 Proposed Tech Specs,Relocating 3/4.3.3.3 Requirements for Seismic Instrumentation to Technical Requirements Manual ML20236N0001998-07-0606 July 1998 Proposed Tech Specs,Relocating RCS Design Features from TS Section 5.4 to UFSAR ML20247F3321998-05-0707 May 1998 Proposed Tech Specs Pages,Reflecting Replacement SG Reactor Coolant Flow Differences ML20217P1441998-04-0202 April 1998 Proposed Tech Specs 3.4.5 Re voltage-based Repair Criteria ML20202H9771998-02-16016 February 1998 Proposed Tech Specs Pages,Implementing 1-volt voltage-based Repair Criteria for SG Tube Support plate-to-tube Intersections ML20198C3741997-12-31031 December 1997 Proposed Tech Specs 2.1,2.2 & 3/4.2.5 for Alternate Operation W/Reduced Measured RCS Flow ML20197A7211997-12-17017 December 1997 Proposed Tech Specs Pages,Revising TS 4.6.2.1 to Extend Surveillance Interval of Containment Spray Sys Nozzle Air Flow Test from Five Years to Ten Years ML20199H2081997-11-20020 November 1997 Revised TS Bases Page B 3/4 4-15 1999-09-08
[Table view] |
Text
~
f
$ y, TABLE 4.3-2 "8 8 ..
38 g ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION co y SURVEILLANCE REQUIREMENTS
~
DIGITAL OR TRIP o c) ,
ANALOG ACTUATING MODES
$$ c CHANNEL DEVICE MASTER SLAVE FOR WHICH a83 O 2.a) 5 CHANNEL CHANNEL CHANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RFLAY SURVEILLANCE
- FUNCTIONAL UNIT CHECK CALIBRATION TEST TEST LOGIC TEST TEST TEST IS REQUIRED
- 1. Safety Injection (Reactor Trip, Feedwater Isolation, Control Room Emergency Ventilation, Start Standby Diesel Generators, Reactor Containment Fan Coolers, and Essential Cooling Water)
- a. Manual Initiation N.A. N.A. N. A. R N. A. N.A. N.A. 1,2,3,4 Y
g b. Automatic Actuation N.A. N.A. N.A. N.A. N(1) N.A. N.A. 1,2,3,4 Logic ,
- c. Actuation Relays N.A. N.A.
N.A. N.A. N.A.
M% Q(4,% 1, 2, 3, 4 %
- d. Containment Pressure- S R M N.A. N.A. N.A. N.A. 1,2,3,4 High-1
- e. Pressurizer Pressure- S R M N.A. N.A. N.A. N.A. 1,2,3 Low '_
- f. Compensated Steam Line S R M N.A. N.A. N.A. N.A. 1,2,3 Pressure-Low
- g. Compensated T -
S R H N.A. N.A. N.A. N.A. 1,2,3 COLD Low-Low (interlocked with P-15)
g TABLE 4.3-2 (Continued)
C E2 ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION y SURVEILLANCE REQUIREMENTS R .
R DIGITAL OR TRIP
, ANALOG ACTUATING MODES .
c CHANNEL DEVICE MASTER SLAVE FOR WHICH 5 CHANNEL CHANNEL CHANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE FUNCTIONAL UNIT CHECK CALIBRATION TEST TEST LOGIC TEST TEST TEST IS REQUIRED
]
- 2. Containment Spray
- a. Manual Initiation N.A. N.A. N.A. R N.A. N.A. N.A. 1,2,3,4
- b. Automatic Actuation N.A. N.A. N.A. N.A. M(1) N.A. N.A. 1,2,3,4 Logic
- c. Actuation Relays N.A. N.A. N.A. N.A. N.A.
$ 1,2,3,4 4 t'
a M(O Q Y d. Containment Pressure- S R M N.A. N.A. N.A. N.A. 1,2,3 '
- 3. Containment Isolation
- a. Phase "A" Isolation
- 1) Manual Initiation N.A. N.A. N.A. R N.A. N.A. N.A 1,2,3,4
- 2) Automatic Actuation N.A. N.A. N.A. N.A. M(1) N.A. N.A. 1,2,3,4 Logic
- 3) Actuation Relays N.A. N.A. N.A. N.A. N.A.
M(fry 1, 2, 3', 4 @
Q(4)
- 4) Safety Injection See Item 1. above for all Safety Injection Surveillance Requirements.
- b. Containment Ventilation Isolation
- 1) Automatic Actuation N.A. N.A. N.A. N.A. M(1) N.A. N.A. 1,2,3,4 Logic W.
- 2) Actuation Relays N.A. N.A. N.A. N.A. N.A. M(fd - Q(4) 1, 2, 3, 4 C
g TABLE 4.3-2 (Continued) ,'
S ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION SURVEILLANCE REQUIREMENTS R - DIGITAL OR TRIP
$; ANALOG ACTUATING MODES
, CHANNEL DEVICE MASTER SLAVE FOR WHICH c- CHANNEL CHANNEL CHANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE
- FUNCfl0NAL UNIT CHECK CALIBRATION TEST TEST LOGIC TEST TEST TEST IS REQUIRED
~ 3. Containment Isolation (Continued)
- 3) Safety Injection See Item 1. above for all Safety Injection Surveillance Requirements. ,
- 4) RCB Purge Radioactivity-High S R M N.A. N.A. N.A. N.A. 1,2,3,4,5*,6*
- 5) Containment Spray - See Item 2. above for Containment Spray manual initiation Surveillance Manual Initiation Requirements.
w 6) Phase "A" Isolation- See Item 3.a. above for Phase "A" Isolation manual initiation 1 Manual Initiation Surveillance Requirements.
Y c. Phase "B" Isolation
$ N.A. N.A. 1,2,3,4
- 1) Automatic Actuation N.A. N.A. N.A. N.A. M(1)
Logic g
- 2) Actuation Relays N.A. N.A. 'N.A. N.A. N.A. M(Ed Q 1,2,3,4 h
- 3) Containment S R M N.A. N.A. N.A. N.A. 1,2,3 Pressure--High-3
- 4) Containment Spray- See Item 2. above for Containment Spray manual initiation Surveillance Requirements.
Manual Initiation
- 4. Steam Line Isolation
- a. Manual Initiation N.A. N.A. N.A. R N.A. N.A N.A. 1,2,3
- b. Automatic Actuation N.A. N.A N.A N.A. M(1) M Q 1, 2, 3 @
Logic and Actuation Relays
- c. Steam Line Pressure- S R M N.A. N.A. N.A. N.A. 3 Negative Rate-High
- d. Containment Pressure - S R H N.A. N.A. N.A. N.A. 1,2,3 High-2
v, o TABLE 4.3-2 (Continued) 5 I
ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION SURVEILLANCE REQUIREMENTS Q _ DIGITAL OR TRIP R ANALOG ACTUATING MODES
, CilANNEL DEVICE MASTER SLAVE FOR WHICH c_ CHANNEL CilANNEL CHANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE 2
FUNCTIONAL UNIT CiiECK CALIBRATION TEST TEST LOGIC TEST TEST TEST IS REQUIRED
,, 4. Steam Line Isolation .
- e. Compensated Steam Line S R M N.A. "
..A. N.A. N.A. 1,2,3 Pressure-Low-
- f. Compensated T -
S R M N.A. N.A. N.A. N.A. 1,2,3 COLD Low-Low (interlocked with P-15) m 5. Turbine Trip and Feedwater 1 Isolation Y
g
- a. Automatic Actuation Logic and Actuation N.A. N.A. N.A. N.A. M(1) M(d[ Q(4) 1, 2, 3
(
Relays -
- b. Steam Generator Water 5 R M N.A. N.A. N.A. N.A. 1, 2, 3 Level-High-High (P-14) '
- c. Compensated T -Low 5 R H N.A. N.A. N.A. N.A. 1,2,3 COLD (interlocked with P-15)
- d. Feedwater Flow-High 5 R H N.A. I;. A. N.A. N.A. 1, 2, 3 (interlocked with P-15)
Coincident with either of the following in 2 of 4 loops: Reactor Coolant Flow-Low or T,yg-Low
- e. Safety Injection See Item 1. above for all Safety Injection Surveillance Requirements.
- f. T,yg-Low Coincident S R H N.A. N.A. N.A. N.A. 1,2,3 with Reactor Trip (P-4)
(Feedwater Isolation Only)
y, TABLE 4.3-2 (Continued) .
E M ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION
~ SURVEILLANCE REQUIREMENTS x
$ DIGITAL OR TRIP ACTUATING MODES ANALOG c-CHANNEL DEVICE MASTER SLAVE FOR WHICH 5 CHANNEL CHANNEL CHANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE FUNCTIONAL UNIT CHECK CALIBRATION TEST TEST LOGIC lEST TEST, TEST IS REQUIRED
- 6. Auxiliary feedwater
- a. Manual Initiation N.A. N.A. N.A. R N.A. N.A. N.A. 1,2,3
- b. Automatic Actuation N.A. N.A. N.A. N.A. M(1) N.A. N.A. 1,2,3 Logic g
- c. Actuation Relays N.A. N.A. N.A. N.A. N.A. M(FJ Q 1,2,3 @
$ d. Steam Generator Water S R H N.A. N.A. N.A N.A 1,2,3 y Level--Low-Low
$; e. Safety Injection See Item 1. above for all Safety Injection Surveillance Requirements. ,
- f. Loss of Power See Item 8. below for all Loss of Power Surveillance Requirements.
- 7. Automatic Switchover to Containment Sump
- a. Automatic Actuation N.A. N.A. N.A. N.A. M M(Ed -Q 1,2,3,4k Logic and Actuation Relays
- b. RWST Level--Low-Low S R M N.A. N.A. N.A. N.A 1,2,3,4 Coincident With:
Safety Injection See Item 1. above for all Safety Injection Surveillance Requirements.
- 8. Loss of Power
- a. 4.16 kV ESF Bus N.A. R N.A M N.A. N.A. N.A. 1,2,3,4 Undervoltage (Loss of Voltage)
g TABLE 4.3-2 (Continued) , ,
ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION a SURVEILLANCE REQUIREMENTS O -
F. DIGITAL OR TRIP
. ANALOG ACTUATING MODES c CHANNEL DEVICE MASTER SLAVE FOR WHICH 5 CHANNEL CHANNEL CHANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE FUNCTIONAL UNIT CHECK CALIBRATION TEST TEST LOGIC TEST TEST TEST IS REQUIRED
]
- 8. Loss of Power,,(Continued)
- b. 4.16 kV ESF Bus N.A. R N.A. M N.A. N.A. N.A. 1,2,3,4 Undervoltage (Tolerable Degraded Voltage Coincident with SI)
R
- c. 4.16 kV ESF Bus N.A. R N.A. M N.A. N.A. N.A. 1,2,3,4 Undervoltage (Sustained
{
w Degraded Voltage)
- 9. Engineered Safety -
Features Actuation -
System Interlocks -
- a. Pressurizer N.A. R M N.A. N.A. N.A. N.A. 1,2,3 Pressure, P-11 N.A. R M N.A. N.A. N.A. N.A. 1,2,3
- b. Low-Low T,y9, P-12
- c. Reactor Trip, P-4 N.A. N.A N.A. R N.A. N.A. N.A. 1,2,3
- d. Power Range Neutron N.A. R(2) M(3) N.A. N.A. N.A. N.A. 1,2,3 .
Flux Input to Excessive Cooldown Protection, P-15
- 10. Control Room Ventilation
- a. Manual Initiation N.A. N.A. N.A. R N.A. N.A. N.A. All
y y, TABLE 4.3-2 (Continued) .
o .
h ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION SURVEILLANCE RE@IREHENTS y
C 2- DIGITAL TRIP
" MODES ANALOG ACTUATING CHANNEL DEVICE MASTER SLAVE FOR WHICH
$ CilANNEL CilANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE 5 CHANNEL TEST LOGIC TEST TEST TEST IS REQUIRED
- FUNCTIONAL UNIT CllECK CALIBRATION TEST w .
- 10. Control Room Ventilation (Continued)
- b. Safety Injection SeeItem1.aboveforallSafetyInjectionSurveillgnceRequirements.
- c. Automatic Actuation N.A. N.A. N.A. N.A. M N.A. N.A. All <
Logic and Actuation e,
Relays K N.A. N.A. N.A. N.A. All
- d. Control Room Intake Air S R M y Radioactivity-High
- e. Loss of Power See Items 8. above for all Loss of Power Surveillance Requirements. , ,
1 -
- 11. FHB HVAC ,
- a. Manual Initiation N.A. N.A. N.A. R N.A. N.A. N.A. 1,2,3,4, !
or with irradiated fuel in the l spent fuel l pool r 8 i
- b. Automatic Actuation N.A. N.A. N.A. N.A. M(d N.A. N.A. 1,2,3,4,(C Logic and Actuation or with Relays irradiated .
fuel in the spent fuel pool
a '
g TABLE 4.3-2 (Continued) ,,
5 ENGINEERED SAFETY FEATURES ACTUATION SYSTEM INSTRUMENTATION
[ SURVEILLANCE REQUIREFiERIS 0 -
DIGITAL OR TRIP
$; ANALOG ACTUATING MODES
. CHANNEL DEVICE MASTER SLAVE FOR WHICH c- CHANNEL CHANNEL CilANNEL OPERATIONAL OPERATIONAL ACTUATION RELAY RELAY SURVEILLANCE FUNCTIONAL UNIT CllECK CALIBRATION TEST TEST LOGIC TEST TEST TEST IS REQUIRED
{
~ 11. FilB HVAC (Continued)
- c. Safety Injection See Item 1. above for all Safety Injection Surveillance Requirements.
- d. Spent Fuel Pool S R H N.A. N.A. N.A. N.A. With Exhaust Radio- irradiated activity-High fuel in spent fuel pool.
k
{
so TABLE NOTATION (1) Each train shall be tested at least every 62 days on a STAGGERED TEST BASIS. -
(2) Neutron detectors may be excluded from CHANNEL CALIBRATION. 7 (3) With Rated Thermal Power greater than or equal to the P-15 interlock setpoint, the ANALOG CHANNEL OPERATIONAL TEST shall consist of verifying that the P-15 interlock is in the required state by (4) observing the permissive annunicator window.
Except relays K807, K814, K829 (Train 8 only), K831, Sif K2
%y K845, 49 ickv4 m o
- b. A K852 and Candonl K8 4 (Trains 3mo
(-
which shall be tested at least once per 18 months during refueling and during each COLD SHUIDOWN exceeding 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> unless they have been tested within the previous 92 days.
(5) ExceptrelayK815whichshallbetestedatindicatedintervalonlywhenreactorcoolantpressure]
is above 700 psig. f f f&f Each actuation train shall be tested at least every 92 days on a STAGGERED TEST 3 ASIS. Testing of each actuation train shall include master relay testing of both logic trains. If an ESFAS instru-mentation channel is inoperable due to failure of the Actuation Logic Test and/or Master Relay Test, increase the surveillance frequency such that each train is tested at least every 62 days on a STAGGERED TEST BASIS unless the failure can be determined by performance of an engineering evaluation -
to be a single random failure.
- During CORE ALTERATIONS or movement of irradiated fuel within containm nt.
_