ML20148H121
| ML20148H121 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 01/15/1988 |
| From: | PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC |
| To: | |
| Shared Package | |
| ML20148H115 | List: |
| References | |
| IEB-85-003, IEB-85-3, NUDOCS 8801270134 | |
| Download: ML20148H121 (24) | |
Text
I PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 RESPONSE TO I.E. BULLETIN 85-03 DOCKET NOS. 50-277 50-278 JANUARY 15, 1988 REV. 0 p8012701M 880121'-
R ADOCK 05000277 g
i PEACH BOTTOM ATOMIC POWER STATION RESPONSE TO I.E. BULLETIN 85-03 PURPOSE This report responds to I.E.Bulletin 85-03 which required licensees to develop and invloment a program' to hssure that motor-operated valve (MOV) switch settings in certain safety systems are selected, set and maintained correctly such that the MOVs will function during both normal and abnorTnal events within the plant design basis. This report is-Intended to partially satisfy the program conpletion reporting requirements of I.E.Bulletin 85-03 action item (f) for Peach Bottan Units 2 S 3.
Although the program described herein is applicable to both Peach Bottcm Units, the specific test and. Inspection results apply to Unit 2 only.- The Unit 3 workscope is in progress and will be addressed upon ccmpletion.
Reportability of any identified problem or defect will be reviewed in accordance with either 10CFR21 or 10CFR50.73 and addressed separately.
SU WARY DESCRIPTION OF THE PEACH BOTTOM I.E. BULLETIN 85-03 PROGRAM The Peach Bottom I.E.Bulletin 85-03 Program consists of the folloutng major. engineering and fleid activities:
EngineerIna ActIvltles 1)
Identification of the design basis operation requirements of MOVs within the scope of I.E.Bulletin 85-03.
2)
Verification of the design adequacy of the MOVs within the scope of the program by comparing valve / motor-operator design infonnation with the design basis requirements determined by
- 1) above.
Field Activities 1)
As-found stem thrust signature testing (Unit 2 Only).
i l
2)
Detailed motor-operator inspection including torque switch, limit switch and other electrical circuit evaluations.
l 3)
Motor-operator refurbishment and other maintenance based on inspection results.
l-L 1
_. 1 4)
Motor-Operator modifications:
hydraulic locking mitigation addition of open torque switch protection spring cartridge cap modifications o
stermut locknut staking 5)
As-left thrust signature testing to set torque switches and estabilsh an acceptable setting range.
6)
Instrunented differential pressure testing ~ on a representative sanple of MOVs (Unit 2 Only). This testing wl11 provide a correlation between MOV stem thrust and. valve operating differential pressure. These results will be used to validate MOVATS testing as a method for establishing proper torque switch settings.
The following discusses how these activities satisfy the required bulletin action items.
In addition, the "to-date" results of the program are discussed along with plans for future work.
. RESPONSE TO BULLETIN REOUIREMENTS The following provides PECo's responses to items (a) through (f) of I.E.Bulletin 85-03.
Each Bulletin item is restated followed by the PECo respcnse.
Item (a)
"Review and docunent thi design basis for the operation of each valve. This docunentatim should include the maximun differential pressure expected during both opening and closing the valve for both nonnal and abnonnal events to the-extent that these valve operations and events are included in the existing, approved design basis, (i.e.~,
the design basis docunented in pertinent Ilcensee sutmittals such as FSAR analyses and fully-approved operating and emergency procedures, etc.).
When detennining the maximun differential pressure, those single equipment failures and inadvertent equipment operations (such as inadvertent valve closures or openings) that are within the plant design basis should be assuned."
PECo Response Reference (3) provided PECo's preliminary I.E.Bulletin 85-03 submittal which addressed bulletin action item a).
The infonnation below provides a more complete discussion of PECo's ccmpIlance with this action item and describes how the Infonnation is related to the overall Peach Bottcxn progran.
L l
l t
F,
.. PECo was a participating member of _ the BWROG ccnmittee which established the scope of. systems and valves subject to the I.E.
iBu11etin 85-03 requirements.
This conmittee also developed the methodology by which the MOV design basis operational
-differential pressures were to be calculated.
Reference (2) is the BWROG topical report which describes these results and provides reccomendations regarding I.E.Bulletin 85-03 progran inplementation.
For Peach Bottom Units 2 and 3, the systems identified by the BWROG as being subject to I.E.Bulletin 85-03 are the High Pressure Coolant Injection (HPCI) and Reactor. Core Isolation Cooling-(RCIC)
Systems. The BWROG report further defined the Bulletin scope by stating that only those HPCI/RCIC MOVs designated as having an active safety function need comply.
PECo has adopted the BWROG Ccrrmittee's recenmended program but has expanded it to include all HPCI and RCIC safety-related motor-operated valves." Methodologies similar to those developed by the BWROG were used to calculate the maxinun operational differential pressures for the additional MOVs. These methodologies are considered conservative, since they include a conservatively rrodeled hydrodynamic pressure conponent
("waterhactmer") which as an Industry practice has not been considered when calculating valve closing differential pressure.
Table 1 presents a 'sunrary of the calculated differential pressure requirements and other pertinent Information appilcable to the MOVs'in the HPCI and RCIC systems.
For conservatism, the calculated differential pressures correspond to the higher of the "open" or "close" design basis differential pressures previously submitted via Reference (3). Please note that there are several changes to the calculated differential pressures frcm those submitted earlier.
The changes resulted from the application of a more conservative methodology in calculating the hydrodynamic pressure ccuponent of the valve closing differential pressures. The resulting increases In required operator capacity are within the capabillties of the affected MOV assemblies.
Since all HPCI and RCIC safety-related MOVs are included in the program and their respective design basis differential pressures were based on the higher of the "open" or "close" values, we believe we have satisfactorily addressed the NRC's concern with regard to operability of valves inadvertently out of position.
" - The RCIC Turbine Trip & Throttle Valve (M0-4487 (Unit 2) S MO-5487 (Unit 3)) Is not considered to have a safety-related motor-operator since the operator is used only to open the valve Creset function) under no differential pressure. The valve's safety function to close is acccmpiished by a spring rnechanIsm.
_4 Item (b)
"Using the results from item (a) above, establish the correct switch settings. This shall include a program to review and revise,.as necessary, the methods for selecting and setting all switches, (i.e., torque, torque bypass, position limit, overload) for each valve operation Copening and closing).
"If the llcensee determines that a valve is inoperable, the licensee shall also make an appropriate Justification for continued operation in accordance with the appilcable technical spec 1fIcatlon."
PECo Response Reference (3) provided a brlef sunnary of the Peach Bottcm MOV switch setting program in place at the time the bulletin was issued.
The. Information below provides details of the program aspects which were developed since then to denenstrate ccrrpliance with this action item.
General PECo has assessed the design adequacy of all those motor-operated valves which were identified in Reference (3). This assessment included the following steps for each MOV:
- 1) calculation of the minimum valve stem thrust and motor-operator torque necessary to operate the valve against maximun design basis differential pressure; 2) determination of the maximun allowable thrust and torque to which the MOV asserrbly could be subjected; 3) determination of the reconmended torque switch settings based on the minimun and maximun criteria established in steps 1) & 2) above; and 4) review of the valve and motor-operator design capacities relative to the design basis operation requirements.
Both the valve and trotor-operator manufacturers were consulted in making these determinations for all affected valves. A sunnary of this information is shcwn in Table 1.
Conclusion Through the MOV design adequacy review described above, it has been detennined that all of the HPCI and RCIC System notor-operated valves which are in-service at Peach Bottom were adequately l
sized and have the capabilltles to function as required under design basis conditions.
l l
l l
. Torque Swltches The program developed at Peach Bottom in response to I.E.
. Bulletin 85-03_ requires that motor-operator torque switches be set in accordance with the following criteria:
1)
The minimtm acceptable setting shall be such that the developed stem thrust at torque switch trip-Is sufficient to fully close the valve against the design basis differential pressure. Once the notor is de-energized, motor-operator inertia provides thrust margin over the minimtm requirement.
PECo's program does not take credit for this additional thrust corponent.
2)
The maximtm acceptable setting is constrained by the lowest of the following four limits; a)
The maximtm allowable thrust for the valve as specified by the valve manufacturer.
b)
The maximtm allowable thrust for the motor-operator as specified by the operator manufacturer.
c)
The maximtm torque capability of the notor at -degraded
- voltage, d)
Spring pack specific maximtm allowable settings.
The Peach Bottan Program requires that a MOV torque switch first be balanced and then adjusted to equal open and close settings.
Balancing adjusts the torque switch such that It operates at equal spring pack compression in both directions. Because spring pack compression is proportional to stem force, this assures that a stem force at least equal to that required to fully close the valve against maximtm differential pressure is available to fully open the valve when actuated. This is a program conservatism which further assures recovery fran inadvertent valve operatlon.
Since SMB-000 torque switches maynot be acceptably balanced the open and closure setpoints are individually verified.
The Peach Bottom Progrrm also requires that torque switch setting adjustments be made in discrete increments. The minimtm setpoint is at the next higher acceptable incremental dial setting determined by criteria 1) above to assure the minimtm closing thrust is exceeded.
In a similar fashion, the maximtm setpoint is at the next lower acceptable incremontal dial setting determined by criteria 2) to assure the maximtm thrust ilmit is not exceeded.
Therefore, this methodology provides inherent margin at both ends of the torque switch setting range. For SMB-000 type operators, the torque switch minimtm increment is 1/2; whereas, on SMB-00 and larger types the minimtm increment is 1/4.
[
Where permitted by the acceptance criteria, a torque switch setting: range.Is established during the "as-left" testing.
This information is entered onto a controlled drawing for future reference. Torque switch limiter block plates are being installed to prevent Inadvertent swltch oversetting.
Limit Switches As part of the PBAPS I.E.Bulletin 85-03 program, a special procedure (Reference 6) was developed to verify and, if necessary, reset motor-operator Ilmit switch settings.
In sunnary, this procedure requires that:
(1) the open torque switch bypass switch (i.e. on the same rotor as the close Ilmit-Indication) is to remain closed until the valve disk has unseated as evidenced by visually observing torque switch operation, noting change. In motor loading, etc.; and (2) the open Ilmit switch is set such that the stem or disk does not coast into the backseat after electrical operation is terminated.
Normal practice for SMB-000 operators ls to set.
~
the valves to stop 1/2 to I handwheel turn frcm the backseat.
For all other rising stem operators, normal practice is 1/4" to 1/2" of stem travel off the backseat.
This special procedure is in conformance with existing maintenance procedure M-9.1.
Thermal Overloads At Peach Bottom, safety-related notor-operator thermal overload (TOL) protection has the following features:
(1) Motor-operator thermal overload (TOL) device trips are annunciated in the control rocm.
(2) Auto-actuation signals bypass the overload trip circuitry, preventing the TOL frcm de-energizing the operator motor.
This increases the probability that the valve will perform its safety functlon.
(3) Thermal overload protection can be overridden in an emergency by the ccntrol room operator by holding the control switch in the open or close position.
(4) The overload heaters are sized in accordance with the special service requirements of Intermittent duty motors.
The sizing criterla is such that the motor will rapidly trip If a locked rotor condition occurs, provides sufficient margin for operational loadings, and provides prcrmt Indication.
Item (c)
"Individual valve settings shall be changed, as appropriate, to those estabitsbed in item b, above. Whether the valve setting is changed or not, the valve will be demonstrated to be operable by testing the valve at the maximtm differential pressure determined in item (a) above with the exception that testing motor-operated valves under conditions simulating a break in the line containing the valve is not required. Otherwise, Justification should be provided for any cases where testing with the maximtm differential pressure cannot practicably be performed. This justification should include the alternative to maximtm differential pressure testing which will be used to verify the correct settings.
PECo Response The adequacy of the actual torque switch settings is confinned through stem thrust measurements made utilizing the Motor-Operated Valve Analysis and Test System (MOVATS) and comparing the results with the calculated valve actuator forces required to overcome the maximtm design basis differential pressures. By directly measuring stem thrust, the uncertalnty in the MOV's torque to thrust conversion can be resolved and the required torque switch setting nere accurately determined. This testing forms an integral ccmponent of PECo's I.E.
Bulletin 85-03 program.
All Unit 2 HPCI and RCIC with the exception of M0-2-23-19 (HPCI Inboard injection valve) have undergone MOVATS testing. The physical location of M0-2-23-19 prohibits the Installation of the MOVATS test equipment. The switch setting data for M0-2-23-19 will be derived from the testing of M0-2-23-20 which is identical both physically and fur.ctionally. Differential pressure testing will be performed to confirm the adequacy of the M0-2-23-19 torque switch settings.
Inspection and Refurbishment The "as-found" torque switch settings on trost tested MOVs were found to be within the limits established by a torque switch setting review program conducted in 1975. This derronstrates that torque switch configuration control has been maintained.
During Unit 2 testing, two (2) "open" Ilmit switches and six (6)
"close" limit switches were found to be set improperly. The improper "open" 1Imit swltch settings resulted in MOVs coasting into the backseat and did not affect MOV operation.
The Improper "close" Ilmit switch settings had no detrimental affect.
These swltches provided only pcsItIon Indication and were not functional during valve opening because the "open" torque switch was Jttrpered out. As indicated in the earlier discussion on limit switches, the "open" torque switch bypass switch is on the same rotor as the "close" 1Imit swltch.
._. In cormliance with the Reference 6 procedure on the Unit 2 MOVs, the thermal overload coll sizes and orientations were recorded.
They were then ccrnpared to the size and orientation specifIed on the associated controlled drawing. Two (2) were fomd to be oriented Incorrectly, one (1) was the wrong size, and one was-the wrong size and oriented incorrectly.
In all cases the overload size and/or orientation were such that a higher current was required to trip the valve.. The safety function of the valve was never impaired since the overload will not trip the valve during an auto-actuation.
In addition to notor-operator switch inspections, the Peach Bottcm Program includes a mechanical and electrical Inspection to evaluate the overall condition of the valve notor-operator assently.
Based on the results of these Inspections, worn or degraded parts were replaced, operators were cleaned and relubricated, and other refurbistynent activities were performed as necessary.
Torque Switch Testina A special procedure (Reference 5) has been developed to perforTn the torque switch testing.
This same procedure also provides for torque switch balancing, spring pack preload rework / repair and spring pack shoulder verification.
"As-Found" Testing Results "As-found" MOVATS testing has been performed on all Unit 2 HPCI and RCIC MOVs except M0-2-23-19.
Through this testing, stem thrust signatures were obtained for each MOV before the necessary modifications a.id refurbishments were performed. Tables 2 and 3 contain the results of the "as-found" testing.
Underthrust Conditions: Five (5) of the twenty-four MOVs which underwent "as-found" MOVATS testing were found to generate less than the calculated minimtm thrust at torque switch trip than that required for design basis operation.
The cause of the MOV underthrusting was attributed to one or more of the following conditions:
Torque switch inhalance.
Insufficient spring pack preload, Excessive gap between the spring pack and spring cartridge o
cap which results In rotation of the torque switch without a corresponding increase in stem thrust.
It was agreed between the NRC Resident Site inspector and the PBAPS Compilance Group that the reportability evaluation of the MOVATS diagnosed valve underthrust conditions is to be deferred untti after confirmatory differential pressure / thrust testing is performed folicwing Unit 2 startup.
I
_9._
Overthrust Conditions: Ten (10) of the 24 MOVs which underwent "as-found" M0 VATS testing were found to generate more than the maximtm vendor reconmended thrust at torque switch trip..In eight (8) cases, the valve reconmended maximtm was exceeded; in four (4) cases,. the trotor operator reccomended maximtm had been uxceeded.. The maxinun thrust reconmendations supplied by the valve vendor correspond to those required to operate the valve against maximtm rated cold working pressure rather than being based on detailed stress analyses.
Examinations of the thrust affected operator components yielded no detrimental condition which would have affected valve operability.
Howevor, scme parts were observed to have experienced greater than normal wear. A Ilmiting load for each thrust affected valve comonent was determined and found to significantly exceed the as-found measured thrust in all cases. On this basis, the vendor reccmnended maximtm thrust values are considered to be conservative and the valves which exhibited the overthrusting condition were determined to be suitable for continued service following motor-operator refurbi strnent.
"As-Left" Testing Upon completion of "as-found" testing, the motor-operators were reconditioned as necessary and made ready for "as-left" MOVATS testing.
The Unit 2 "as-left" torque switch settings and corresponding thrust data are contained in Tables 2 & 3.
The data Indicates that all MOVs within the scope of this program meet the. switch setting criteria established and discussed in the Item (b) response.
Instrtmented Differential Pressure Testing l
PECo plans to perform Instrtmented differential pressure testing on 19 of the 24 Unit 2 HPCI and RCIC MOVs.
Instrunented differential pressure testing will entall the monitoring of valve stem thrust, torque switch operation and flow shutoff (verified acoustically) while the valve is operated against differential pressure. Most of this testing must be deferred until after Unit 2 restart since nuclear steam is required. No differential pressure tests have been camleted to date.
An assessment of design basis operating margin for the MOVs at both Units 2 6 3 will be made by ccmparing this data with the "as-left" MOVATS test data.
Table 4 provides an overall stmnary of the testing program.
Item (d)
"Prepare or revise procedures to ensure that correct switch settings are determined and maintained throughout the life of the plant. Ensure that applicable Industry reccmnendations are considered in the preparation of these procedures."
_ _. - _ _ PECo Response As mentioned in earlier discussions, PEco has developed several special procedures to address MOV operability testing and switch verification. These procedures provide the means by which PECo is irrplementing I. E.Bulletin 85-03 at PBAPS.
Infonnation In these procedures which is directly related to the maintenance of MOV switch settings.ls being incorporated into station or Fleid Engineering approved procedures. An extensive revision to maintenance Procedure M-9.1 (Reference 7) is in progress and will reflect this Information. Procedure M-9.1 will also reference the ccatrolled MOV data Index (Reference 8) for making any torque switch adjustments. These procedure revisions will be carpleted prior to Unit 2 restart.
As part of the procedures review, PECo developed a specific list of fdOV maintenarn:e activities which may effect base 1Ine MOVATS results (Reference 9).
Under the PECo progran, all future MOV maintenance will be reviewed against this list to determine what testing must be performed prior to returning any safety-related MOV to service.
Stroke time and motor-current data collected during future surveillance and modification acceptance testing will be canpared to the "as-left" test results in order to monitor valve operability on an ongoing basis.
Item (e)
"Within 180 days of the date of this bulletin, submit a written report to the NRC that:
(1) reports the results of item (a) and (2) contains the program to accanpilsh items (b) through (d) above including a schedule for cenpletion of these items."
PECo Response (Cortplete)
Reference (3) dated Noverrber 3,1986 provided PECo's response to this action item.
Item (f)
"Provide a written report on corrpletion of the above program. This report should provide (1) a verification of camletion of the requested program, (2) a stmnary of the findings as to valve operability prior to any adjustrrents as a result of this bulletin, and (3) a simnary of data in accordance with Table 2, Suggested Data Stmnary Format.
The NRC staff Intends to use this data to assist in the resolution of Generic issue II.E.6.1.
This report shall be submitted to the NRC within 60 days of carpletion of the program.
Table 2 should be expanded, if appropriate, to include a stnmary of all data required to evaluate the response to this bulletin."
.-__ ___ ____ __________ ' Q:
PECo Response This docunent partially cormletes the reporting requirements of I.E.Bulletin 85-03 action item (f) for Peach Bottom. Our plans are to comolete the IEB 85-03 differential pressure testing during PBAPS-2 restart and submit a report ccntaining the evaluated results within three (3) months of its completion. The Unit 3 response will be submitted prior to ullt restart.
. lNIT 3 PROGRAM DIFFERENCES The test program planned for Unit 3 consists of the inspection, refurbishment and "as-left" MOVATS testing of all HPCI and RCIC MOVs.
"As-found" testing is not included in the planned Unit 3 scope of work, since the valve operators will Le completely refurbished and verified operable prior to return to service.
The Unit 3 valves will not be differential pressure tested. The adequacy of MOVATS testing as the basis for determining proper torque switch settings will be confirmed via the results of the Unit 2 instrunented differential pressure test assessment. The Unit 2 differential pressure test results are directly applicable to Unit 3 on the basis of Identical design and operation of the systems and system ccrmonents.
MOTOR OPERATOR MODIFICATI(NS Four modifications concerning MOV operability are being limicmented as part of the PBAPS I.E.Bulletin 85-03 Progran. A description of each modification folicws:
1)
Slots will be machined in the spring pack torque limiting sleeves to alleviate hydraulic locking concerns identified in INPO SER 86-03. Limitorque has approved this slotting scheme.
2)
The electrical Jumer bypassing the open torque switch on all but the HPCI/RCIC Injection and pum discharge valves will be retroved. Since proper torque switch protection will be verified by this test program, there is no need to ccrnpletely override the open torque switch protective feature. Conventional torque switch bypassing, where the open torque switch is bypassed until the disc Ilfts off its seat, will then be put into effect. This rmdification will increase MOV reliability by reducing the Ilkelihood of rmtor burncut and Internal valve damage.
3)
Old style spring cartridge caps on size SMB-000 through SMB-2 operators will be replaced with the newer adjustable type allowing Inservice installation of MOVATS diagnostic equipment.
In addition, this replacement provides the means to reduce the gap between the spring pack and spring cartridge cap which in turn will reduce lost rotaticnal motion of the torque switch. On SMB-3 and SMB-4 size operators, the original spring cartridge cap is being rmdified to allow the Inservice Installation of MOVATS diagnostic equipment.
4).
As a nore positive means of securing the sterrnut locknut, a setscrew is being installed at the locknut /drivesleeve interface.- A setscrew provides easier maintenance disassembly than'the previously used staking method.
PBAPS MOV PROGR#4 BEYOto 1. E. BULLETIN 85-03 PECo is in the process of inplementing a ccmprehensive inspection, refurbishment and test program for all active safety-related MOVs at Peach Bottom. This-program is a direct expansion of our I.E.
Bulletin 85-03 program which was limited specifically to the HPCI and RCIC Systems. The expanded program includes the same engineering and fleid activities described earlier with the exception of "as-found" and instnmented differential pressure testing.
The scope of work will include over 160 MOVs.
SUMMARY
S CONCLUSION This report has described the Peach Bottom I.E.Bulletin 85-03 Program, provided a ccmplete response to bulletin action items a), b),
& d) and provided a partial response to action item c).
The Peach Bottom I.E.Bulletin 85-03 Program will assure the capability of the subject valves to perform their design basis safety functlon.
Future valve-operabi11ty will be maintained through the implementation of revised maintenance procedures.
REFERENCES (1)
I.E.Bulletin 85-03, "Motor-operated Valve Cmmon Mode Failure During Plant Transients Due to Invroper Switch Settings, Novenber 15, 1985 (2) BWROG Report on the Operational Design Basis of Selected Safety-Related Motor-Operated Valves, NEDC-21322, September 1986 (3)
- d. S. Kemper (PECo) letter to Dr. T. E. Murley (NRC), dated Noventer 3,1986 (4)
E. L. Gordon (NRC) letter to T. A. Pickens (BWROG), dated January 30, 1987 (5) Mod 1915 Torque Switch Test Procedure, Rev. 1, dated 8/31/87 (6) Mod 1915 Limit Switch Test and overload Verification Precedure, Rev. O, dated 3/26/87 (7) Procedure M-9.1, Limitorque Switches Inspection, Maintenance, Adjustment, Lubrication, Rev. 11, dated 5-24-84 (8) DWG E-3123 CDraft), Limitorque M.O.V. Operators Data Report (9)
C. B. Patton letter to G. F. Dawson, dated 9/10/87 TSN/pd11128707 Attachrents
TABLE 1 PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 VALVE AND MOTOR-OPERATOR MATRIX FOR I.
E.
BULLETIN 85-03 11NSTRUMENT NO.
I DELTA P I VENDOR I
VALVE THRUST IOPERATOR-lMAX OPER. I MAX OPERATOR I
I SERVICE LPSCRIPTION I SPEC / I PEco PRINT NO.
IMIN OPEN MIN CLOSEI NUMBER 1 THRUST I TOROUE I
I FUNCTION (NOTE 1) I CALC I
VENDCR IMAX OPEN MAX CLOSE1 NOTE 3 i CAPACITY l@80% VOLTS 9100%VOLTSI I
I (PSID)
I DRAWINO NO.
I NOTES 4,5 (LBS)
ISERIAL NOl' (LBS) 1 SWITCH SETTINGS I i
I i
I I
P. O.
NO I I
(LB-FT) i IMO-2-13-15 I
1150 IWALWORTH I
3220 3892 1000-5 1
8000 13.5/55 3.5/55 I I RCIC INDOARD STEAM ISO VALVE I 1116 IM102B38 1
3923 4789 IL-377306 I I
I I
ACE I I A-9777-M-131-E I I 3M6189A I I
I 1
i IMO-2-13-16 1
1150 IWALWORTH I
3220 3892 1000-5 1
8000 14/68 4/68 I I RCIC OUTBOARD STEAM ISO VALVE I 1116 IM102B38 4
3923 4789 1107763 I
I I
I ACE I I A-9777-M-131-E I 1334298-U 1 l
i I
I IMO-2-13-18 I
31 IWALWORTH I
1552 1589 8000-2 l
8000 12.5/47 3/55 I I RCIC CST SUCTION BLCCK VALVE I 37 IM102B46 1
3817 4090 191740-A I
I I
I A I I A-1060003-M-4B i 1334297-0 I I
I I
I IMO-2-13-20 1
1700 IWALWORTH I
9716 11831 10-25 1 24000 12.75/282 3/324 I I
RCIC EUMP DIS BLOCK VALVE I 1123 IM102B15 i
16244 20061 192133-A I
I I
I BE I I
A9509-M-169-A i 1334297-AGI I
I I
I IMO-2-13-21 1
1700 IWALWORTH I
9716 11831 10-25 1 24000 12.75/282 3/324 I I
RCIC INJTCTION VALVE I 1123 IM102B15 1
16244 20061 192034-A I
I I
I ACE I I
A9509-M-169-A l 1334297-AGI I
I I
I IMO-2-13-27 1
1500 IWALWORTH I
(2) 5704 1000-5 I
8000 14/68 4/68 I I
RCIC PUMP MIN FLOW VALVE I 1326 IM1-G-50 1
13600 194407-A I
I I
I ACE I I
A-12399-M-1B I 1335313-F I I
I I
I IMO-2-13-30 1
1700 IWALWORTH I
(2) 17090 10-15 1 24000 13/324 3.75/425 I I
RCIC PUMP DIS TEST VALVE I 1300 IM102B47 1
27528 192136-A I I
l 1
BE I I
A-9533-M-57-C I 1334297-AII I
I 1
I IMO-2-13-39 I
65 IWALWORTH I
2085 2177 1000-2 1
8000 12.5/47 3/55 1 1RCIC TORUS SUCTION BLOCK VALVE I 93 IM102B46 1
3817 4090 191741-A I
I I
I AC 1 i A-1060003-M-4B I 1334297-0 I I
I I
I IMO-2-13-41 1
65 IWALWORTH I
2085 2177 1000-2 I
8000 12.5/47 3/55 1 1RCIC TORUS SUCTION BLOCK VALVE I 93 IM102B46 1
3817 4090 191742-A i
1 1
1 AC I I A-1060003-M-4B i 1334297-0 1 1
I l
a l
PAGE 1
TABLE 1 PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 VALVE AND MOTOR-OPERATOR MATRIX FOR I.
E. BULLETIN 85-03 IINSTRUMENT NO.
I DELTA P I VENDOR I
VALVE THRUST IOPERATOR-lMAX OPER. I MAX OPERATOR R
I SERVICE DESCRIPTION I SPEC / I PECo PRINT NO.
IMIN OPEN MIN CLOSEl NUMBER 1 THRUST 1 TORQUE I
I FUNCTION (NOTE 1) I CALC 1
VENDOR IMAX OPEN MAX CLOSE1 NOTE 3 i CAPACITY 1980% VOLTS 9100%VOLTSI I
I (PSID)
I DRAWINO NO.
I NOTES 4,5 (LBS)
ISERIAL NOI (LBS) i SWITCH SETTINGS I I
I I
I I
P. O.
NO 1 I
(LB-FT) 1 IMO-2-13-131 1
1150 IWALWORTH I
(2) 15869 10-10 1 24000 12.5/252 3/324 I IRC1C TURBINE ST ADMISION VALVE I 1116 IM102844 I
20128 196358-A I I
I I
AE I I
A-12326-M-4-B I 1334297-AFI I
I I
I IMO-2-13-132 1
1450 1ROCKWELL I
(2) 3270 100-7.5 l 14000 11.625/60 2/75 1 1RCIC TURB COOL WATER BLOCK VAL i 1308 IM102A26 I
6405 1109297-A I I
I I
DE I I
D-472450 1 1343227-A 1 1
I I
I BMO-0244 5
62 IANCHOR/DARLINO I (2) 2461 1000-5 I
8000 13.75/64 4/68 1 IRCIC TURB EXH VAC BREAKER VALVEl 41 IM-147-20 1
22635 1175492 I
I I
I C 1 1
2321-3A i 1371819-A I I
I I
I IMO-a-23-14 8
1150 IWALWORTH I
16586 18558 11-40 1 45000 12.25/437 2.5/525 I IHPCK TURBINE ST ADMISION VALVE I 1116 IM102B42 1
20937 23482 191748-A I
I I
I AE I I
A-9782-M-100C 1 1334297-AJ1 I
I I
I IMO-2-23-15 I
1150 IWALWORTH I
16586 18558 10-40 1 24000 13/322 4.25/500 I I HPCI INBOARD STEAM ISO VALVE I 1116 IM102835 1
20937 234*? 199821-A I
I I
I ACE I I
A-9782-M-99-B l 1334297-ADI I
I I
i I
IMO-2-23-16 1
1150 IWALWORTH I
16586 18558 11-40 I 45000 12.25/437 2.5/525 I HPCI OUTBOARD STEAM ISO VALVE I 1116 IM102B42 1
20937 23482 191749-A I
I I
I ACE I I
A-9782-M-100C i 1334297-AJI I
I I
I IMO-2-23-17 1
65 IWALWORTH I
4766 4892 10-10 1 24000 12.25/227 2.75/284 I I HPCI CST SUCTION BLOCK VALVE I 40 BM102833 1
18078 18942 192272-A I
I I
I A I I
A-7519-M-46A i 1334297-ACI I
I I
I IMO-2-23-19 1
1760 IWALWORTH I
30692 34749 14-130 1 250000 12.5/1700 3.25/2325 I I
HPCI INJECTION VALVE I 1123 IM102B29 I
55552 63212 193813-A I
I I
I ACE I I
A-95522-M-37C i 1334297-AUI I
I I
I BMO-2-23-20 1
1700 IWALWORTH I
30692 34749 14-150 1 250000 12.5/1700 3.25/2325 I I
HPCI PUMP DIS BLOCK VALVE I 1123 IM102B29 I
55552 63212 1111122 I
I I
I AE I I
A-95522-M-37C 1 1334298-A01 I
I PAGE 2
TABLE 1 PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 VALVE AND MOTOR-OPERATOR MATRIX FOR I.
E.
BULLETIN 85-03 IINSTRUMENT NO.
I DELTA P 1 VENDOR I
VALVE THRUST IOFERATOR-IMAX OPER. I MAX OPERATOR I
I SERVICE DESCRIPTION I SPEC / I PECo PRINT NO. IMIN OPEN MIN CLOSEl NUMBER I THRUST I TOROUE I
I FUNCTION (NOTE 1) I CALC i
VENDOR IMAX OPEN MAX CLOSE1 NOTE 3 i CAPACITY 1980% VOLTS 0100%VOLTSI i
1 (PSID)
I DRAWING NO.
I NOTES 4,5 (LBS)
ISERIAL NOI (LDS)
I SWITCH SETTINGS I I
I I
I I
P. O.
NO I I
(LB-FT)
I iMO-2-23-21 1
1700 1WALWORTH I
(2) 87027 13-100 1
140000 13/2551 3.75/3188 I I
HPCI PUMP DIS TEST VALVE I 1350 IM102B37 1
137444 1107629 I
i
'l I
BE I I
A-9537-M-4-C 1 1334298-ASI I
I I
I IMO-2-23-24 1
1700 1WALWORTH I
16851 19651 80-25 1 24000 13.5/396.
4.25/500 t i
HPCI PUMP DIS TEST VALVE I 1350 IM102830 1
25971 30451 192135-A I
I I
I BE I I A-9519-M-131-D I 1334297-AH1 1
I 1
i IMO-2-23-25 1
1500 IWALWORTH I
(2) 17896 10-25 1 24000 13.5/395' 4/468 1 i
HPCI PUMP MIN FLOW VALVE I 1375 IM1-J-44 I
27528 194881-A I
I I
I ACE I I
A-12326-M-2-C i 1335313-E I I
I I
I IMO-2-23-31 1
1700 IWALWORTH I
5627 7283 100-10 1
14000 12/171 2.5/214 I i HPCI TORUS RETURN BLOCK VALVE I 1350 IM102B59 1
8223 10847 1113579 I
I I
I CE I I
A-12367-M-4-6 1 1334297-DIl i
I I
I IMO-2-23-57 1
65 IWALWORTH I
7768 8060 10-10 1 24000 12.25/216 2.75/284 I IHPCI TORUS SUCTION BLOCK VALVE I 93 IM192833 1
18078 18942 192273-A I I
I I
AC i i
A-7519-M-46A i 1334297-ACI I
I I
I BMO-2-23-58 1
65 IWALWORTH I
7768 8060 10-10 1 24000 12.25/216 2.75/284 I IH9C1 TORUS SUCTION DLOCK VALVE I 93 IM102B33 1
18078 18942 192274-A 1
I I
I AC I I
A-7519-N-46A i 1334297-AEl I
I i
I IMO-4244A I
62 IANCHOR/ DARLING I (2) 2461 1000-5 1'
8000 13.75/64 4/68 I IHPCI TURB EXH VAC BREAKER VALVEl 41 IM-147-20 1
22635 1185604 I
I I
I C i 1
2321-3A I I 376737A I I
I P't3E 3 t
TABLE 1 PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 VALVE AND MOTOR-OPERATOR P. ATRIX FOR I.
E.
BULLETIN 85-03 IINSTRUMENT NO.
I DELTA P I VENDOR I
VALVE THRUST IOPERATOR-BMAX OPER. I MAX OPERATOR i
i SERVICE DESCRIPTION I SPEC / 1 PECo PRINT NO.
IMIN OPEN MIN CLOSEE NUMBER I THRUST I TORQUE I
I FUNCTION (NOTE 1) I CALC I
VENDOR IMAX OPEN MAX CLOSEI NOTE 3 I CAPACITY le80% VOLTS 9100%VOLTSI I
I (PSID) 1 DRAWING NO.
I NOTES 4,5 (LBS)
ISERIAL NOI (LBS) i SWITCH SETTINGS l
I I
I t
i P. O.
NO I I
(LB-FT) 1 IMO-3-13-15 5
1150 IWALWORTH I
3220 3892 1000-5 I
8000 13/55 4/68 8 I
RCIC INBOARD STEAM ISO VALVE I 1116 IM102B38 1
3923 4789 1121874 I
I I
I ACE I I A-9777-M-131-E I 1334297-0 1 1
l I
I IMO-3-13-16 1
1150 IWALWORTH I
3220 3892 1000-5 1
8000 14/68 4/68 8 i RCIC OUTBOARD STEAM ISO VALVE I 1116 IM102B38 1
3923 4789 1188267 I
I I
I ACE I I A-9777-M-131-E I 1381459-B I 1
1 I
I IMO-3-13-18 1
31 IWALWORTH I
1552 1589 1000-2 3
8000 12.5/47 3.25/58 I I
RCIC CST SUCTION BLOCK VALVE I 37 IM102B46 1
3817 4090 1107759 1
I I
I A I l A-1060003-M-4B l 1334298-0 I I
I I
I IMO-3-13-20 I
1700 IWRLWORTH I
9716 11831 10-25 1 24000 12.75/282 3.25/352 e i
RCIC PUMP DIS BLOCK VALVE I 1123 IM102B15 1
16244 20061 1107931 1
I I
I BE I I
A9509-N-169-A i 1334298-AOI I
I I
I IMO-3-13-21 1
1700 IWALWORTH I
9716 11831 10-25 1 24000 12.75/282 3.25/352 I I
RCIC INJECTION VALVE I 1123 IM102B15 l
16244 20061 1107932 I
I I
I ACE I I
A9509-M-169-A i 1334298-A01 1
I I
I IMO-3-13-27 1
1500 IWALWORTH I
(2) 5704 1000-5 I
8000 14/68 4/68 I I
RCIC PUMP MIN FLOW VALVE I 1326 IM1-0-50 1
13600 194406-A I
I l
i ACE I 1
A-12399-M-1B 1 1335313-F I I
I I
I IMO-3-13-30 1
1700 IWALWORTH I
(2) 17090 10-15 1 24000 13/324 3.75/425 I I
RCIC PUMP DIS TEST VALVE I 1300 IM102B47 1
2752a 1105891 I
I I
I BE I I
A-9533-M-57-C i 1334298-AII I
I I
I IMO-3-13-39 I
65 IWALWORTH I
2085 2177 1000-2 1
8000 12.5/47 3.25/58 I IRCIC TORUS SUCTION BLOCK VALVE I 93 IM102B46 1
3817 4090 1107760 t
i I
I AC i 1 A-1960003-M-4B i 1334298-0 1 I
I l
1 IMO-3-13-41 1
65 IWALWORTH I
2085 2177 1800-2 1
8000 12.5/47 3.25/58 1 1RCIC TORUS SUCTION BLOCK VALVE I 93 IM102B46 1
3817 4090 1107761 1
I 1
i AC i 1 A-1960003-M-4B I 1334298-0 1 I
I PRSE 4
TABLE 1 PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 VALVE AND MOTOR-OPERATOR MATRIX FOR I.
E.
BULLETIN 85-03 IINSTRUMENT NO.
I DELTA P I VENDOR I
VALVE THRUST IOPERATOR-lMAX OPER. I MAX OPERATOR I
I SERVICE DESCRIPTION I SPEC / I PECo PRINT NO.
IMIN OPEN MIN CLOSEE NUMBER I THRUST I TOROUE I
I FUNCTION (NOTE 1) I CALC I
VENDOR IMAX OPEN MAX CLOSEl NOTE 3 i CAPACITY 1980% VOLTS #100%VOLTSI I
I (PSID)
I DRAWING NO.
I NOTES 4,5 (LBS)
ISERIAL NOI (LBS) i SWITCH SETTINGS I I
1 I
i 1
P. O.
NO I I
(LB-FT)
I IMO-3-13-131 1
1150 IWALWORTH I
(2) 15869 10-10 1 24000 12.5/252 3/324 1 IRCIC TURBINE ST ADMISION VALVE I 1116 IM102B44 1
20128 1107930 I
I I
I AE I I
A-12326-M-4-B I 1334298-AFI 1
I 1
1 IMO-3-13-132 1
1450 IROCKWELL I
(2) 3270 100-7.5 1
14000 11.625,o0 2/75 1 1RCIC TURB COOL WATER BLOCK VAL i 1308 IM102A26 8
6405 1109296 l-e a
i BE I I
D-472450 1 1343227-A I I
I I
I BMO-5244 5
62 1 ANCHOR / DARLING I (2) 2461 1900-5 I
8000 13.75/64 4/68 8 1RCIC TURB EXH VAC BREAKER VALVEl 41 IM-147-20 4
22635 1185603 I
I I
I C 1 1
2321-3A i 1376737-A 1 I
i 8
i IMO-3-23-14 1
1150 IWALWORTH I
16586 18558 11-40 1 45000 12.25/437 2.5/525 I IHPCI TURBINE ST ADMISION VALVE I 1116 IM102B42 1
20937 23482 1105096 I
I I
I AE I I
A-9782-M-100C I 1334298-AJ1 8
1 e
i IMO-3-23-15 1
1150 IWALWORTH I
16586 18558 10-40 1 24000 13/322 4.25/500 I I
H PCI INBOARD STEAM ISO VALVE I 1116 IM102B35 1
20937 23482 1107926 I
I I
I ACE I I
A-9782-M-99-B B 1334298-ADI I
I I
I IMO-3-23-16 1
1150 1WALWORTH I
16586 18558 11-40 I 45000 12.25/437 2.5/525 i 1 HPCI OUTBOARD STEAM ISO VALVE I 1116 IM102B42 1
20937 23482 1105897 I
I I
I ACE I I
A-9782-M-100C I
!334298-AJ1 I
I I
I IMO-3-23-17 1
65 IWALWORTH I
4766 4892 50-10 1 24000 12.25/216 2.75/284 I
18078 18942 1107927 I
I I
I A i I
A-7519-M-46A I 1334298-AE1 1
I I
I IMO-3-23-19 1
1760 IWALWORTH I
30692 34749 14-150 1 250000 12.5/1700' 3.25/2325 8 I
HPCI INJECTION VALVE I 1123 IM102B29 I
55552 63212 1111121 1
I 4
1 ACE I I
A-95522-M-37C I 1334298-AUI I
I 8
1 IMO-3-23-20 1
1700 IWALWORTH I
30692 34749 14-150 I 250000 12.5/1700 3.25/2325 I I
HPCI PUMP DIS BLOCK VALVE I 1123 IM102B29 I
55552 63212 193814-A I
I I
I AE I I
A-95522-M-37C I 1334297-Auf I
I PAGE 5
TABLE 1 PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 VALVE AND MOTOR-OPERATOR MATRIX FOR I.
E.
BULLETIN 85-03 IINSTRUMENT NO.
I DELTA P 1 VENDOR I
VALVE THRUST IOPERATOR-lMAX OPER. I MAX OPERATOR I
I SERVICE DESCRIPTION I SPEC / I PECo PRINT NO.
IMIN OPEN MIN CLOSEI NUMBER I
THRUST I TORQUE I
i FUNCTION (NOTE 1) 1 CALC I
VENDOR IMAX OPEN MAX CLOSEI NOTE 3 i CAPACITY 1080% VOLTS 0100%VOLTSI I
I (PSID)
I DRAWING NO.
I NOTES 4,5 (LBS)
ISERIAL NOl (LBS) i SWITCH SETTINGS I I
I i
1 1
P. O.
NO I I
(LB-FT) i IMO-3-23-21 1
1700 IWALWORTH I
(2) 87027 13-100 1
140000 13/2551 3.75/3188 I I
HPCI PUMP DIS TEST VALVE I 1350 IM102B37 1
137444 192275-A I I
I I
BE I I
A-9537-M-4-C I 1334297-ASI I
I i
I IMO-3-23-24 1
1700 IWALWORTH I
16851 19651 10-25 l 24000 13.5/396 4.25/500 I I
HPCI PUMP DIS TEST VALVE I 1350 IM102B30 1
25971 30451 1107933 I
I I
I BE I I A-9519-M-131-D 1 1334298-Allt i
I I
I IMO-3-23-25 1
1500 IWALWORTH I
(2) 17896 10-25 1 24000 13.5/395 4/468 I I
HPCI PUMP MIN FLOW VALVE I 1375 IM1-J-44 1
27528 194880-A I
I I
I ACE I I
A-12326-M-2-C i 1335313-E I I
I I
I IMO-3-23-31 1
1700 IWALWORTH I
5627 7283 100-10 1
14060 12/171 2.5/214 I I HPCI TORUS RETURN BLOCK VALVE I 1350 IM102B59 I
8223 10847 1113580 1
I I
I CE I I
A-12367-M-4-6 1 1334298-Dill i
I I
I IMO-3-23-57 1
65 IWALWORTH I
7768 8060 10-10 1 24000 12.25/216 2.75/284 1 IHPCI TORUS SUCTION BLOCK VALVE I 93 IM102B33 1
18078 18942 1107928 I
I I
I AC i 1
A-7519-M-46A I 1334298-ACI i
i I
i IMO-3-23-58 I
65 IWALWORTH I
7768 8060 10-10 1 24000 12.25/216 2.75/284 I IHPCI TORUS SUCTION BLOCK VALVE I 93 IM192833 1
18078 18942 1107929 I
I I
I AC 1 1
A-7519-M-46A i 1334298-AEl i
I I
I IMO-5244A B
62 IANCHOR/DARLINO I (2) 2401 1000-5 I
8000 13.75/64 4/68 I IHPCI TURB EXH VAC BREAKER VALVEl 41 IM-147-20 1
22635 1175491 I
I I
I C I I
2321-3A I I 371819A I I
I PRGE6
TAGLC I NOTES PCACH LOTTOM ATOMIC POWER STATION UNITS 2 f. 3 vat.VE AND MOTOR-OPERATOR MATRIX FOR I. E. DULLETIN 85-03 (1)
FUNCTION KEY A=ECCS VALVC AUTOMATIC ACTION OR SUPPORT OF ECCS AUTOMATIC ACTION B*ECCS VALVE MANUAL It4ITATIOra OR SUPPORT OF ECCS MANUAL ACT70t3 C=COf4 T AINMEt1T ISOLATION VALVE AUTOMATIC ACTION D = cot 4TAINMEt4 T ISOLATIOta VALVE mat 4UAL It41 TATION C=HIGH PRESSURE VALVC 2900psig F=OfitER VALVES MANUAL INITIATION (2) Tills VALVE IS A GLOBE VALVE.
IF THE PRESSURE IS UtJDER THE SEAT IT ACTS TO OPEtt THC VALVE, itCNCE TitC REQUIRCD TliRUST IS MIN!ttAL.
IF TitC PRESSURE IS OvCR TitC SEAT Tile OPEt4ING TitRUST EQUALS THE CLOSING TitRUST 14HICH IS GIVEta.
(3) (LL VALVE OPERATORS ARE LIritTOROUE MODEL NO. SMD-UtJLESS OTHERWISE NOTED.
(4)
THE HIGliCR OF THE TL40 MINIMUM VALVE THRUSTS WILL DE APPLIED F OR DOTil THE OPEtJ At3D CLOSE TOROUE SWITCHCS.
(5)
DECAtr3E THESC VALVES ARE IJOr DACKSEATED, Tile CLOSE THRttST WILL DE USED AS THC GOVERNING W1VC MAXIMUM.
UP TO 110% OF THIS VALUE MAY BE USED FOR THE MAXIt1UM THRUST LIMIT AS lot 4G AS IT DOES NOT EXCEED THE MAXIMUM OPERATOR THRUST OR 90% OF THC LIMITING COMPONEt4T THRUST.
PAGE 'I
TABLE 2 HPCI SYSTEM MOTOR OPERATED VALVE TORQUE SWITCH AbD OPERATING THRUST DATA TORCUE SETTING OPERATING THRUST VALVE DESIGN AS TEST AS DESIGN (1)
AS TEST AS AS-FOUr0 MJMBER MIN.
MAX.
FOUND MIN.
MAX.
LEFT MIN.
MAX.
.FOUND MIN.
MAX.
'LEFT-REMARKS 2-23-14 1.5 3.75 1.5 1.0 1.25 1.25 18558' 23482 24240 20800 21760 21760 Overthrust 2-23-15 2.75 4.0 2.75 1.5 1.75 1.5 18558 23482 13840 18800 22280 19000 ~ Underthrust.
2-23-16 1.5 3.75 1.5 1.25 1.25 1.25 18558 23482 43310 22400 22400 22400 Overthrust-2-23-17 1.5 2.5 1.5 1.0 2.25 1.25 4892 18942 19560 4520 17760 7880-Overthrust 2-23-20 1.5 2.0 1.0 1.0 1.25 1.0 34749 63212 53800 42800 58000 42800 2-23-21 2.75 3.5 2.75 2.25 3.0 2.25 87027 137444 102800 93000 -
121500 93000 2-23-24 3.5 4.25 2.5 2.25 2.5 2.25 19650 24000: 33180 21020 23340 19700 Overthrust 2-23-25 2.0 3.5 2.0 1.25 1.25 1.25 17896 24000* 25180 21940 21940 21940 ' Overthrust 2-23-31 1.0 2.75 1.0 1.0 1.0 1.0 7283 10847 10520 10560 10560 10560 2-23-57 1.5 2.5 1.5 1.5 1.75 1.5 8060 18942 24240 12600 14750 12600. Overthrust 2-23-58 1.5 2.5 1.5 1.75 2.25 1.75 8060 18942 18360 9700 17350
-9700 23-4244A 1.0 4.0 2.0 1.0 3.5 1.0 2461 8000 5100 3020-7960 3020 NOTES:
(1)
Maxinun values are valve Ilmited unless identified with a "x" indicating motor operator limited.
TSN/pd11048706
TABLE 3 RCIC SYSTEM MOTOR OPERATED VALVE TORQUE SWITCH Ato OPERATING THRUST DATA TORQUE SETTING OPERATING THRUST VALVE DESIGN AS TEST AS DESIGN (1)
AS TEST AS AS-FOUND NtJ4BER MIN.
MAX.
FOUND MIN.
MAX.
LEFT MIN.
MAX.
FOUND MIN.
MAX.
LEFT REMARKS 2-13-15 1.0 4.0 3.0 2.0 2.0 2.0 3892 4789 4960 3960 4640 4640 Overthrust 2-13-16 1.0 4.0 2.0 Unavailable 3892 4789 5320 Unavailable Overthrust 2-13-18 1.0 3.0 1.0 1.0 2.5 1.0 1589 4090 1540 1960 3320 2040 Underthrust 2-13-20 2.25 3.0 2.5 1.25 1.5 1.25 11831 20061 24400 13160 16340 13160 Overthrust 2-13-21 1.0 2.5 2.0 2.0 2.75 2.0 11831 20061 14980 12000 18440 12400 2-13-27 2.25 4.0 3.0 2.5 4.0 2.5 5704 8000 3600 6480 7960 6480 Underthrust 2-13-30 2.25 3.5 2.25 2.5 2.75 2.5 17090 24000 13460 18880 22180 18880 Underthrust 2-13-39 1.0 3.0 1.0 1.0 2.5 1.0 2177 4090 3080 2720 3660 3260 2-13-41 1.0 3.0 1.0 2.0 2.5 2.0 2177 4090 1530 2660 3470 2660 Underthrust 2-13-131 2.0 3.0 1.75 1.75 1.75 1.75 15869 20128 12550 18150 18150 18150 Underthrust 2-13-132 1.0 1.5 1.0 1.0 1.0 1.0 3270 6405 8248 6240 6240 6240 Overthrust 13-4244 1.0 4.0 1.0 1.0 3.5 1.0 2461 8000:
2980 3940 8080 3940 NOTES:
(1)
Maximum values are valve limited unless identified with a "X"
Indicating motor-operator 1imited.
TSN/aud/11048708
i l
TABLE 4 PBAPS l.E. BULLETIN 85-03 TESTING PROGRAM
SUMMARY
Yelve No.
Deceriotion Test Method (*)
BWROG ID#
System #13 N0-2(3)-21 RCIC Injection Yalve A) 1 M0-2(3)-27 RCIC Minimum Flow Bypass Yalve A) B) 2 MO-2(3)- 18 RCICCondensate Storage A) B) 3 Tank Suction Yalve M0-2(3)-41 RCIC Torus Suction Isolation Yalve A) 4 M0-2(3)-39 RCIC Torus Suction Isolation Yalve A) B) 4a M0-2(3)-30 RCIC CST Test Return Yalve A) B) 5 M0-2(3)-20 RCIC Injection Yelve Test Yalve A) B) 8 M0-2(3)- 132 RCIC Turbine Accessory A) B) 9 Cooling Water Yalve M0-2(3)- 131 RCIC Steam Admission Yalve A) B) l M0-2(3)- 15 RCIC Steam Line inboard A)
Il r;
Isolation Yalve 6
M0-2( 3)- 16 RCIC Steam Line Outboard A) B) til Isolation Yalve M0-4244 RCIC Yacuum Breaker Line A) B)(1)
Vil M0-5244 Isolation Yalves System *23 M0-2( 3)- 19 HPCI Injection Yalve C) 1 (Identical to M0-2(3)-20)
M0-2(3)-25 HPCI Min. Flow Bypass Yelve A) B) 2 M0-2(3)- 17 HPCI CST Suction Yelve A) B) 3 M0-2(3)-58 HPCI Torus Suction isolation Yalve A) 4 M0-2(3)-57 HPCI Torus Suctfon Isolation Yalve A) B) 4a M0-2(3)-21 HPCI CST Test Return Yalve A) B) 5 M0-2(3)-24 HPCI CST Test Loop Isolatfon Yalve A) B) 6 M0-2(3)-31 HPCl/RCIC Test Flush Valve A) B) 7 M0-2(3)-20 HPCI Injection Yalve Test Yalve A) B) 8 M0-2(3)-14 HPCI Steam Admission Yalve A) B) l M0-2( 3)- 15 HPCI Steam Line inboard A) ll Isolation Yalve M0-2(3)-16 HPCI Steam LIne Outboard A) B) lll i
I lsolat1on Yalve l
M0-4244A HPCI Vacuum Breaker Line A) B) (1)
Yll L
N0-5244A isolation Yelves
(*) TEST METHODS A) Baseline M0YATS Testing - all valves except HPCI M0-2(3)- 19 due to inaccessibility.
Identical valve M0-2(3)-20 to be tested for proper torque switch settings.
B) Instrumented differentfal pressure testing. Currently planned for Unit 2 0NLY.
Unit # valves are identical to Unit 2.
C) Non-instrumented differential pressure testing at design basis conditions.
NOTE ( 1) - Elther the HPCI or RCIC vacuum breaker isolation valve will under@ dP testing.
l 1
l