ML20148D936

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-458/87-27
ML20148D936
Person / Time
Site: River Bend Entergy icon.png
Issue date: 01/19/1988
From: Callan L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Deddens J
GULF STATES UTILITIES CO.
References
NUDOCS 8801250516
Download: ML20148D936 (2)


See also: IR 05000458/1987027

Text

..

_

.

..

.. _

_ - - .

__

_ _

_ _ . . . .

_

..

,

e>

,

'

l

In Reply Refer To:

JM I 9 N

Docket: 50-458/87-27

.'

i

'

Gulf States' Utilities

ATTN: Mr. James C. Deddens

'

Senior Vice President, (RBNG)

.

Nuclear Licensing

P.O. Box 220

St. Francisv111e, Louisiana

70775

Gentlemen:

Thank you for your letter of December 18, 1987, in response to our letter

and Notice of Violation dated November 17,1987. We have reviewed your reply

and find it responsive to the concerns raised in our Notice'of Violation. We

will review the implementation of your corrective actions during a future

4

l

inspection to determine that full corrpliance has been achieved and will be

j

maintained.

-

a

"

O fginal Signed 11y

.

L. J. Callan

i

I

L. J. Callan, Director

Division of Reactor Projects

cc:

<

'

)

Gulf States Utilities

ATTN:

J. E. Booker, Manager-

l

River Bend Oversight

)

P.O. Box 2951

l

)

Beaumont, Texas

77704

!

1

,

i

Louisiana State University,

i

l

Government Documents Department

d

'

]

Louisiana Radiation Control Program Director

i

1

RIV:DRP/C3

C:0RP/C

0:DRP b

!

GLMadsen:gb

EJHoller

LJCa lan

i

I h4 /88

i //f/88

l/ /88

!

/ h()/

i

88o1250516 880119

%

!

PDR

ADOCK 05000458

,

!

o

PDR

6

_ - _ _ .-_ _ _ ___._. _ _ _ _ ... -. ~ .._._.,__.-- _ - _ ,.- - . __.

e

.

DISTRIBUTION:

bec to DMB (IE01)

bec distrib. by RIV:

  • DRP
  • Resident Inspector

R. D. Martin, RA

  • SectionChief(DRP/C)
  • Lisa Shea, RM/ALF
  • MIS System

RPSB-DRSS

  • RSTS Operator
  • Project Engineer, DRP/C
  • RIV File
  • W. Paulson, NRR Project fianager
  • R. Hall
  • DRS
  • TSS

D. Powers

  • w/766

,

1

'

!

l

_ _ _ _ _ _ _ _ _ _ _ - _

s.

ge

,

s. '

courawh

@WWL

auzr svares

vrrrrrres

UU'

!

.m . ., so ,

,,o-

m ,o.,,ci.3 m

.,.. ~eis m i m is.to m

DEC 2 81987

L.

!

'

m, com

.n .ou

u...ii

o

.

4

December 18, 1987

RBG - 27174

File Nos. G9.5, G15.4.1

'

U. S. Nuclear Regulatory Comission

Document Control Desk

Washington, D.C.

20555

Gentlemen:

l

River Bend Station - Unit 1

Refer to: Region IV

Docket No. 50-458/ Report 87-27

This letter responds to the Notice of Violations contained in NRC

Inspection Report No. 50-458/87-27. The inspection was performed by

l

Messrs. Chamberlain and Jones during the period of October 1-31, 1987 on

i

,

'

activities authorized by NRC Operating License NPF-47 for River Bend

)

Station Unit No. 1.

Gulf States Utilities Company's (GSU) response to

Notice of Violations 458/8727-01, "Failure to Obtain Required Procedure

Approval", and 458/8727-02, "Failure to Initiate Hot Work Pemit for

Grinding Activity", is provided in the enclosed attachment pursuant to

10CFR2.201. This completes GSU's response to these items.

Sincerely,

l

l

J. C. Deddens

Senior Vice President

River Bend Nuclear Group

JCD/DRD/JWL/sN/ ERG JHM/tl

cc:

U.S. Nuclear Regulatory Commission

611 Ryan Plaza Drive, Suite 1000

Arlington, TX 76011

NRC Resident Inspector

P. O. Box 1051

St. Francisville, LA 70775

4

i n a a A A

',r ug,

m

h

g

.-,pr

a

g

b

---

- - - -

'

e

. .

J'

UNITED STATES OF AMERICA

NUCLEAR REGULATORY COMMISSION

STATE OF LOUISIANA

)

PARISH OF WEST FELICIANA

)

In the Matter of

)

Docket No. 50-458

50-459

GULF STATES UTILITIES COMPANY

)

(River Bend Station,

Unit 1)

AFFIDAVIT

J.

C.

Deddens,

being

duly sworn, states that he is a

Senior Vice President of Gulf States Utilities Company; that

he

is

authorized

on

the part of said company to sign and

file with the Nuclear Regulatory

Commission

the

documents

attached

hereto;

and

that all such documents are true and

correct to

the

best

of

his

knowledge,

information

and

belief.

(

//w

J. C. beddens

Subscribed

and

sworn

to before me, a Notary Public in

and for the St.ste and Parish above named, this

/8Yb day of

h0PfY1hPr

, 19 S 0 .

.

M 1,

i

!I

- 1)

-

/Joan W. Middlebrooks

M otary Public in and for

West Feliciana Parish,

Louisiana

My Commission is for Life.

-

r

, ,

).

ATTACMENT

Response To Notice of Violation 50-458/8727-01

Level V

REFERENCE:

Notice of Violation - letter from L. J. Callan to J. C. Deddens, dated

November 17, 1987.

VIOLATION - Failure to Obtain Required Procedure Approval

River Bend Station Technical Specifications, Section 6.5.2.1, require

that each procedure and program of Specification 6.8, which includes

surveillance and test activities of safety-related equipment, shall be

approved, prior to implementation, by the Plant Manager or one of the

Assistant Plant Managers or the Supervisor-Radiological Programs.

Contrary to the above, on October 6,1987, during observation of a

maintenance activity, the senior resident inspector found that Station

Operating Procedure No. TP-87-29, "RCIC Signature Testing", was being

implemented to test safety-related motor operated valves in response to

NRC Bulletin 85-03. This procedure had been approved by the Director of

Field Engineering, and not by the Plant Manager or one of the Assistant

Plant Managers.

REASON FOR THE VIOLATION:

The Engineering Department was reorganized in September of 1986. A new

group within the engineering department was formed from several existing

Technical Staff Groups combined with Nuclear Plant Engineering's

Mechanical Engineering group to fom the Field Engineering Group. The

functions of the Technical Staff Groups were also assigned to the Field

Engineering Group, along with the procedures necessary for

implementation. Control of those procedures was transferred to the

'

Director-Field Engineering by a change to ADM-0003, "Development

Control and Use of Procedures", which controls the issuance and

modification of procedures in the Station Operating Manual. However,

Technical Specification (TS) Section 6.5.2.1 was not changed to reflect

that the Director - Field Engineering has assumed signature authority

for procedures in the Field Engineering area of responsibility.

It was

felt that Plant Manager approval of the change to ADM-0003 constituted

j

adequate control. Therefore, the root cause was a result of the

reorganization of engineering, and a misunderstanding of the changes

required to allow transfer of procedural responsibility to the Field

Engineering Group.

l

..

.

..

..

'

.

CORRECTIVE STEPS WHICH HAVE BEEN TAKEN AND THE RESULTS ACHIEVED:

The reorganization of the Engineering Department is now complete.

Procedures which had been signed solely by the Director-Field

Engineering were reviewed and signed as required by T.S. 6.5.2.1.

Thus,

the Field Engineering related procedures now have the required

approvals.

CORRECTIVE STEPS WHICH WILL BE TAKEN TO AVOID FURTHER VIOLATIONS:

Corrective measures have been taken to assure STPs in use are properly

approved. The Director-Field Engineering now initials applicable Field

Engineering procedure changes and forwarde them for approval in

accordance with T.S. 6.5.2.1.

ADM-0003, Figure 1, has been changed to

eliminate signature authority for the Director-Field Engineering and has

been replaced with the Plant Manager or Assistant Plant Manager. This

assures that none of the applicable procedures will be issued without

the approvals as required by T.S. 6.5.2.1.

An initial review of other

available procedures controlling signature authority under T.S. 6.8.1

was performed and determined that adequate signatures were controlled.

To ensure that the appropriate procedures are identified and controlled

in accordance with T.S. Sections 6.5.2.1 and 6.8.1, a Quality Assurance

review will be performed. This review is expected to be completed

during January 1988.

,

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED:

The Technical Specifications applicable procedures in active use are

-

signed by the PM or APH. The revisions or changes will be signed by the

PM or APM as they are written.

Quality Assurance evaluations will be

completed during January 1988. Any recommendations will be reviewed for

further corrective action.

,

i

.

.- , .

ATTACMENT

y

Response To Notice of Violation 50-458/8727-02

Level V

,

REFERENCE:

Notice of Violation - letter from L. J. Callan to J. C. Deddens, dated

November 17, 1987.

VIOLATION - Failure to Initiate Hot Work Permit for Grinding Activity

Technical Specification 6.8.1.g requires that written procedures be

established, implemented, and maintained for activities implementing the

fire protection program.

Fire Protection Procedure (EPP)-0060, "Hot work Pemit." states that, "A

Hot Work Pemit shall be required whenever an ignition source is to be

used in any area of the plant, except those areas designated as Hot Work

Area." An ignition source is defined as an open flame apparatus,

welding, abrasive cutting and grinding, brazing, and other devices whose

temperature exceeds the heat of ignition of materials in contact or

close proximity to the device.

Contrary to the above, on October 24, 1987, at approximately 2 a.m.

(CDT), the resident inspector observed grinding operations on the

inboard main steam isolation valve 1821*A0V022C for the removal of a

bolt stud without a Hot Work Permit having been obtained.

The area had

not been designated as a Hot Work Area, nor had a firewatch been

established.

Combustible materials were located within close proximity

of the grinding activity.

REASON FOR THE VIOLATION:

Procedure FPP-0060 defines the use of a Hot Work Permit during operation

and outage work and requires a pemit whenever an ignition source is

used in any area of the plant, except those areas designated as

permanent Hot Work Areas.

During the rework of main steam isolation

valves on MWO #105963, two repairmen violated procedure FPP-0060. After

attempting unsuccessfully to remove a seized body-to-bonnet nut on

1821*A0VF022B using nomal means, the person in charge of the field work

elected to "crack" the nut off.

This process involved grinding a notch

in the nut and then using a cold chisel to crack the nut in half. The

grinding process created sparks in the area. This was a procedure

violation because there was not a designated fire watch nor did the

repairmen have a valid Hot Work Permit.

The event occurred at about 0200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> (eight hours into a 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

shift).

Dress out requirements included double PC's and a respirator.

The person in charge of the field work decided to continue the job

instead of leaving the work area to ensure a valid Hot Work Permit was

in effect (a loss of time on the job estimated at two hours).

Therefore

the root cause of the incident is determined human error. The mechanics

assumed that a Hot Work Pemit existed rather than one of them leaving

the work area to check,

.

c.

(

CORRECTIVE STEPS WHICH HAVE BEEN TAKEN AND THE RESULTS ACHIEVED:

The person in charge of the field work was given disciplinary action

(verbal reprimand) by the Mechanical Maintenance Supervisor. Both

repaimen also received disciplinary action and personal instructions on

,

the requirements for use of Hot Work Permits.

CORRECTIVE STEPS WHICH WILL BE TAKEN TO AVOID FURTHER VIOLATIONS:

On November 3, 1987, D. R. Derbonne (Assistant Plant Manager -

Maintenance) issued memo number APM-M-87-342 which states the

circumstances of the event and promulgates Maintenance Management's

!

position on adherence to procedures.

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED:

Gulf States Utilities Company is currently in full compliance.

,