ML20141N881

From kanterella
Jump to navigation Jump to search
Reactor Containment Bldg Integrated Leak Rate Test Final Rept
ML20141N881
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 11/30/1985
From:
SOUTHERN CALIFORNIA EDISON CO.
To:
Shared Package
ML20141N876 List:
References
NUDOCS 8603180237
Download: ML20141N881 (17)


Text

_

t

}

.3,'

4 l

SOUTHERN CALIFORNIA EDISON COMPANY-SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 REACTOR CONTAINMENT BUILDING INTEGRATED LEAK RATE TEST FINAL REPORT NOVEMBER 1985 TEST 860:.1180'tJ7 860:sa 2 PDR ADOCK 05000362 P PDR

SONGS 3 1985 ILRT TEST REPORT PAGE'2-TABLE OF CONTENTS

1.9 INTRODUCTION

3 1.1 GENERAL 3 1.2 TEST SYNOPSIS 3 1.3 DOCUMENTS AND TEST INFORMATION 5 RETAINED AT SONGS 2.0 GENERAL DATA 6 3.8 TECHNICAL DATA 6 ,

4.0 TEST DATA

SUMMARY

7 5.8 VERIFICATION TEST DATA

SUMMARY

7 6.9 LOCAL LEAK RATE DATA

SUMMARY

8 7.9 ANALYSIS AND INTERPRETATION 8 7.1 PRESSURIZATION 8 7.2 CONTAINMENT ATMOSPHERE STABILIZATION 8 7.3 ILRT (Mass Point) 9 7.4 ILRT (Total Time) 18 7.5 IMPOSED LEAKAGE RATE VERIFICATION TEST 11 (Mass Point) 7.6 IMPOSED LEAKAGE RATE VERIFICATION TEST 12 (Total Time) 8.S LOCAL-LEAK RATE TESTING

SUMMARY

13 9.8 AS FOUND ILRT 14 2-9.1 BEFORE MAINTENANCE AND PRIOR TO PURGE 15 OR OPENING HATCHES 9.2 BEFORE MAINTENANCE AND AFTER USE OF 15 PURGE AND HATCHES

9.3 CONCLUSION

16

4, s 4 - , .

r s +

> r. y g - '

SONGS'3'1985lILRT. TEST REPbRTl 'PAGE'3

, 4' t

j ~ 1.01 INTRODUCTION 1;l faEMEE&L 4

.The . reactor conta inment' building ' Integrated ~ Leakage

. Rate - ' Test . (Type- A): ;wa C performed to demonstrate that the overall leakage rate through the - primary --

reactor . containment ' system does not exceed- the '

allowable leakage rate as specified in -the Unit '3 Technical Specification, Section 3.6.1.2 The test l was performed as part of the Unit 3 first refueling '

' outage.

-The successful Type A ' and supplemental- verification.

tests' :were' performed in ~ accordance with the requirements of ' San Onofre Nuclear Generating. ,

Station, Unit-2 & 3, Procedure'SO3-V-3.12, Revision  !

0,- Containment 1 Integrated Leak Rate Test. The

, test method utilized ' wa s ' 'the . absolute  : method t' described in ANSI /ANS-56.8-1981, Containment: System

. Leakage Testing- Requirements. The leakage rate was calculated using' thel Mass Point and Total Time

-formulae from this standard and Bechtel Topical Report, BN-TOP-1, Revision 1, " Testing Criteria .for Integrated Leakage. Rate Testing of Primary Containment Structures for Nuclear Power Plants". The test results are reported' in accordance- with the-requirements'of 10CFR58, Appendix J, Section V.B.3, and ANSI /ANS 56.8-1981 1.

1.2 TEST SYMOPSIS Pressurization was started at 9138 on 11/23/85 and test pressure was obtained 11/23/8'5. At this time, the

, Chilled Water, Chillers, and Dome . Air circulators were secured. Temperature stabilization was achieved in four hours, with the test commencing at 2288 ' on 211/23/85. Based' on ana)ysis of the test

, data, fit was determined at 0339.on 1.1/24/84 that one of the Dome Air' Circulators was' still' operating. ~I control Room Supervision confirmed that a circulator

  • was still in operation. The cause was a ' failed indicating light on the control board. The circulator was secured, resulting in a step change in the data.t The test was restarted at 8545 on 11/24/85, ' following data stabilization and concluded at 0600, 11/25/85. The Verification test was started at 9615, 11/25/85. One hour was allowed for stabilization followed by a four hour test.

Depressurization was started at l',15 , 11/25/85 and completed at 8215, 11/26/85.

t i

SONGS 3 1985 ILRT TEST REPORT PAGE 4 1.2 TEST SYNOPSIS-(Continued)

The Primary Containment Integrated Leakage Rate Test

, (ILRT) was successfully completed on November 25, 1985

  • at the San.Onofre Nuclear Generating Station, Unit
3. All ILRT requirements of the Technical Specifications were satisfied.

TEST SEQUENCE START COMPLETION PRESSURIZATION 0130 - 11/23/85 1739 - 11/23/85 STABILIZATION 3745 - 11/23/85 2288 - 11/23/85 TEST 9545 - 11/24/85' 9608 - 11/25/85 VERIFICATION 9615 - 11/25/85 1115 - 11/25/85 BLOWDOWN 1215 - 11/25/85 8215 - 11/26/85 MASS POINT ANALYSIS Analysis of the measured data taken during the- test resulted in a calculated leakage rate of 9.9511/ day and 'a 95% probability upper confidence limit (UCL) leakage 'of 0.852t/ day using the Mass Point calculation technique as recommended in ANSI /ANS 56.8-1981 The leakage rate ah this upper confidence limit plus a 8.992%/ day Local Leak Rate penalty (See Section 6.9) yields an overall leakage rate of 6.954%/ day of contained air mass which satisfies the acceptance criteria of being less than 9.875%/ day.

TOTAL TIME ANALYSIS Analysis of the measured data taken during the test resulted in a, calculated leakage rate of 0.848%/ day and a 95% probability upper confidence limit (UCL) leakage of 0.052%/ day using the Total Time calculation technique as recommended in ANSI 45.4-1972 The leakage rate at this upper confidence limit plus a 8.8024/ day Local Leak Rate penalty yields an overall leakage rate of 8.954%/ day of contained air mass which satisfies the acceptance criteria of being less than 0.075%/ day.

e: y ,.; hu -

%, n

(: 2; , _; ,

.,& il ;  !

, w  : M Si3L1985"ILRT-TEST REPORT- " PAGE 5 1.2; TEST SYNOPSIS,(Continued)

VERIFICATION TEST

' Following the . completion of 'the .ILRT measurements, ,a f

, 4, -  : successful. verification test was performed with an imposed e- - g. : .

_,' leakage- rate of-7.87 sefs. The " Mass Point icalculated-P leakage - rate of :8.1274/ day established: 'during the e verification test was -within the-allowable limits Hof 3.1264/ day: to 8.1764/ day.. The.. Total: Time calculated

leakage rate of 0.1244/ day was'within the allowable. limits of 0.1234/ day to 5.1734/ day.

3 The calculated leakage rates for-this Primary Containment ILRTJ demonstrates that leakage through.the primary reactor

' containment and systems and components penetrating primary.

containment do not exceed- the allowable leakage rate

. specified;in the SONGS 3 Technical Specifications.

1.3 DOCUMENTS AND TEST INFORMATION RETAINED AT SONGS

, -i F The following documents. and test information are available-f' ,.

for review at the San Onofre Nuclear. Generating Stations

1) A listing of 'all containment penetrations, penetration size, and functions.

I

2) A. listing of normal operating instrumentation used for the leakage rate test.
3) A system lineup (at the time of the test) showing required valve positions and status of piping.
4) A continuous, sequential . log of events from initial

, . survey of containment to restoration of all: tested systems.

5) Documentation of instrumentation calibrations and standards.

~

6) The otficial test copy of the test procedure with sign-off of procedural steps.
7) computer printouts of int'egrated Leakage Rate Test Data and Reports along with Graphs and Plots of the data obtained during the test using Southern California Edison and Bechtel Power Corporation developed computer programs.
8) P&ID'S
. 9) Local Leak Rate Test History Files

(I .

~

SONGS 3L-1985 ILRT TEST REPORT' :PAGE 6_

2.0 GENERAL DATA (PLANT INFORMATION)-

2.1 ' Owner Southern ~ California' Edison 2.2 : Docket No. 50-361-

-2.3 Plant San Onofre Nuclear Generating Station -- UNIT 3 2.4 Location San Onofre, California 2.5 Containment Type Post-tensioned concrete,

hemispherical done 2.6 NSSS Supplier Combustion Engineering, PWR

[ 3.9 TECHNICAL DATA l

3.1 Containment Net 2,395,000 cubic feet Free Air Volume 3.2 Design Pressure 68.8 psig 3.3 Design Temperature 388.9 degrees F 3.4 Calculated Peak 55.7 psig i Accident Pressure

! (Pa)

I 3.5 Calculated Peak 287 degrees F Accident Temperature l

l l 1 i

f l

t

r ~ '

F .

SONGS 3'1985 ILRT TEST REPORT -

PAGE 7 4.8 TEST DATA

SUMMARY

4.1 Test Method Absolute Method 4.2 Data Analysis Techniques 1)' Mass Point per ANSI /ANS 56.8-1981

2) Total Time <24 hrs per BN-TOP-1

>24 hrs per ANSI /ANS 56.8-1981 4.3 Test Pressure 57.7 psig 4.4 Maximum Allowable 9.199%/ day Leakage Rate (La) 4.5 ILRT Results Leakage Rate (wt. 4/ day)

Lam 95% UCL 95% UCL + LL*

i

1) Mass Point 8.951 B.052 9.854 (See Section 7.3)
2) Total Time 0.048 9.952 0.054 (See Section 7.4)

I-5.0 VERIFICATION TEST DATA SUlMARY 5.1 Verification Test .1%/ day (7.87 scfm)

> leakage Rate 5.2 Verification Test Leakage Rate (wt. %/ day)

Results Limit Rate

! 1) Mass Point B.126-0.176 0.127 l

2) Total Time 8.123-8.173 S.124 l

\

f t

l

  • LL = Local Leak Rate Penalty t

l u

L -

p :s

L SONGS 3: 1985 ILRT. TEST- REPORT ,

PAGE 8 s

l' 6.0 LOCAL LEAK RATE TEST. DATA -

SUMMARY

During: the ILRT, the penetrations listed below were -not '

aligned to simulate.the configuration after- a postulated ,

-The measured local leakage rates obtained from accident.

L Test, Procedure SO23-V-3.13,*. Containment Penetration- Leak l- Rate Testing", are given below 'and a::e added to the : ILRT-

[

-results.

l PEN- .

LEAKAGE RATE l 9. DESCRIPTION VALVE'9 t/ day H ISB ILRT PRESS SENSOR S21595MUf38~& ,

h S215SSMU939 0.000001 l 23C ILRT, FLOW FLANGE 9.088091

!' 34 ILRT PRESS CONNECTION FLANGE 5.008072' L 42 NON-CRIT CCW INLET 2HV6211 & 2HV6223 0.001190 i

43 NON-CRIT CCW OUTLET 2HV6216 s'2HV6236 0.889379 45 CTMT NORMAL INLET 2HV9998 & 2HV9920 8.088120 46 CTMT NORMAL OUTLET 2HV9971 &'2HV9921 S.008144 TOTAL LLRT Penalty 0.091898 7.5 ANALYSIS'AND INTERPRETATION 7.1- PRESSURIEATION

! Pressurization started at 9138'on No'vember 23, 1985.

l- The test- pressure of 57.7 'psig was achieved at 1730 l on November 23, 1985. The average pressurization rate l was 3.57 psi /hr over the 16.0 hour0 days <br />0 hours <br />0 weeks <br />0 months <br /> period, using a l- 9000 cfm diesel compressor system.

l i 7.2 CONTAINMENT ATMOSPHERE STABILIEATION l:

The acceptance criteria for containment atmosphere stabilization at test. pressure is that' the rate of r change of the containment temperature (weighted j average of RTD sensors) averaged over the last hour l shall not : deviate by more than 0.5 degrees F per

! hour from the' rate of change averaged over the last

! four hours, and that the containment almosphere has L. been at test pressure for at least four hours.

Temperature commenced 1745 and stabilization at was achieved at 220s.

Four Hour Average = 8.198 degrees F/hr Last Hour Average = 0.858 degrees F/hr Deviation = 0.858 degrees F/hr

V SONGS 3L1985 ILRT TEST REPORT. PAGE 9-7.9 ANALYSIS AND INTERPRETATION (Continued) 7.3 ILRT fMama Point)

The acceptance- criteria for a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ILRT is that the leakage rate determined .using the 954 - UCL value for the calculated leakage ' rate - plus - the local- leak rate ' penalty must. be less than 754-of the allowable leakage. rate (La) at the peak accident pressure-(Pa).

  • The Mass Point Leakage Rate calculated with a 95%

. probability UCL is 0.9524/ day. ,

8 954 UCL = 5.9524/ day

  • The LLRT. for in the ILRT is 8.5024/day.

penetrations not included.

(See Section 6.8). .

LL = 0.0024/ day

  • 75% of the allowable leakage rate of 0.194/ day is 0.0754/ day.

75% La = 5.8754/ day The acceptance criteria for the ILRT leakage rate using the Mass Point technique is satisfied, i.e.,

95% UCL + LL < .75 La 8.952%/ day + 0.0924/ day < f.9754/ day 8.854t/ day < 0.0754/ day

v' ,

SONGSi3 1985'ILRT TEST' REPORT , PAGE IS 7.0

~

ANALYSIS AND INTERPRETATION (Continued) 7.4_rtne troemi T1..)

The acceptance criteria for -the ILRT is ' that the leakage rate determined using the,95t'UCL value for Total Time calculated leakage- rate plus -the sum of the measured LLRT rates for penetrations not< included in the ILRT, must 'be less than 75% of-the' allowable leakage rate (La) at the peak accident pressure (Pa) .

The test duration was 24.25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br />.

  • 98 data points were used in the calculations.
  • Data was collected at fifteen '(15) minute intervals. i The . upper bound 954 probability value for the' calculated leak rate using the Total Time technique was 3.0524/ day. '
  • 75% of the allowable leakage rate of 0.18t/ day is 0.9754/ day.

La = 0.0754/ day.

t The acceptance criteria .for the test using 'the Total Time technique is satisfied,.i.e.,

95% UCL + LL < .75 LA 8.8524/ day + 5.0024/ day < 8.8754/ day 8.8544/ day < 0.0754/ day >

l

J .-

~

SONGS 3 1985 ILRT, TEST REPORT PAGE 11 I'

7.8 ' ANALYSIS AND INTERPRETATION (Continued) 7.5 Imposed Isakaae mate verification Test tu==a Point)

The ace:eptance criteria for the imposed leakage verification test is given by the following -

equatio'ar

  • Lo + Lcalc .25 La < Lver < Lo + Lealc + .25 La where, Lo = imposed leakage rate'which must be-in the range  :

.75 La i Lo 1 1.25 La Lcalc = ILRT calculated leakage rate Lyer = Verification test calculated leakage rate Furthermore, the calculations shall utilize at least 18 data-points, recorded over a time span of at least 4 i hours.

/

Actual Test Data is as follows:

1-

  • Lo = 0.198t/ day. (7.87 scfm)
  • 8.25 La = 8.825t/ day l

l

  • Lealc = 8.8514/ day
  • Lver = 0.1274/ day (Mass Point) ,
  • Data Points = 17 The acceptance criteria for the Mass Point technique of determining the imposed leakage rate is satisfied, i.e.,

Lo + Lealc .25 La < Lver < Lo + Lealc + .25 La 8.188 + 8.851 - 8.825 < B.127 < 0.188 + 8.851 + 5.825 I 8.126 < 8.127 < 8.176 L

f l

^

j

-l l

i 1 6 f ___- - - _ _ _ _ _

3, f

[-

. , ~

+ * '

.- - . . - ., 2 , , ,

SONGS 3~1985 ILRT TEST REPORT -

, PAGE'12 a

- . =, -

J

^

7.0 ! ANALYSIS AND' INTERPRETATION (Continued)- y I 7.6 :r= named t=mkman mate verification Test (Total Ti==) ,

The. acceptance -criteria for' the inhosed  :

leakage verification = test using' the Total Time'  !

c

~ technique is, the same as. Mass Point -defined in -

Section 7.5. + >

~

Actual Test Data is as follows: d L

  • Lo = 0.1994/ day (7.87 sefs) i
  • 8.25 La = 0.9254/ day
  • Lcalc = 0.0484/ day ,

?

  • Lver = 0.1244/ day (Total Time) ,

i l

'* Data Points = 17 < ,

The acceptance criteria for'the Total Time ' technique j

, of determining the imposed leakage rate is satisfied, > '

L 1.e.,

Lo + Lcalc .25 La < Lver .< Lo.+'Lcalc + .25 La .

0.100 + 0.048 - 5.825 < f.124 < 0.100 + 8.048 + 5.025 .i L

8.123 < 0.124 < 0.173 t

8.8 LOCAL LEAK RATE TESTING SURNARY , i Penetration (Type B and C) testing was accomplished in 4 accordance witi the requirements of the. Technical Specification 3/4.6.1 and Mr' 8023-V-3.13. The penetrations were tested using the pressure decay method, i and local test panels. The allowable leakage for all .;

penetrations is 0.964/ day-(0.6 La) of the mass of air in i j the containment at 55.7 psig.  ;

j At no time during Modes 1, 2, 3 or 4 did the allowable- t n leakage for all penetrations exceed 8.864/ day using IE  :

l Information Notice No. '85-71 methods for determining the >

l through penetration leakage.

/

l l'

, t l  !

L 1

SONGS'3~1985 ILRT TEST REPORT PAGE 13-

, 8.0 LOCAL LEAK RATE TESTING

SUMMARY

The following is an Operational History of Unit 3 since'the first ILRT (Preoperational Test) and the through penetration j leakage expressed in t/ day.

Date Description _ t/ day. l 3/30/82 Preoperational ILRT 5.002 1/ 6/83 Entar Mode 4 0.005 8/29/83 Initial Criticality 0.006 l j 9/16/83 Full Power License 0.006 i 11/17/83 100% Power 0.006' 1/ 8/84 Mode 5 - Initial Commercial Power Outage 0.006 [

3/ 2/84 Enter Mode 4 0.013  !

4/ 1/84 Commercial Power 0.013 l 6/13/84 Mode 5 - RCP Seal Replacement Outage 0.013 7/ 2/84 Enter Mode 4 '0.013 7/20/84 Mode 5 - E089 Leakage Outage 0.013 8/05/84 Enter Mode 4 0.013 10/30/84 Mode 5 - re89 Leakage Outage 0.013 11/27/84 Enter. Mode 4 0.012 1/29/85 Mode 5 - PVS1008 Leakage Outage 0.012 l 2/16/85 Enter Mode 4 0.012 3/12/85 Mode 5.- Press Boundary Leak-Inspection 0.012 1

3/16/85 Enter Mode 4 0.012 9/17/85 Mode 5 - First Refueling Outage 0.011 I I

11/23/85 First Refueling Outage ILRT 5.006 t

l ,

?

SONGS 3 1985 ILRT TEST REPORT PAGE 14 4

8.0 LOCAL LRAK RATE TESTING SUISIARY (Continued)

In December 1982 and January 1983, all the LLRT's were performed prior to initial startup of the Unit. In January and Pobruary 1984, .all the LLRT's were performed prior to startup for initial commercial Operation. In September, October & November 1985, all LLRT's were ' performed prior to the First Refueling Outage ILRT.

9.0 AS POUND ILRT IE Information Notice No. 85-71 outlines the methodology for determining an As-Pound ILRT using LLRT results. Since the Notice was received late in the outage planning, LLRT's could not be performed just prior to use of Purge or defeating of the interlocks and opening of the Personnel Batch and the Escape Match. As a result, a higher contain-ment total was recorded for the initial LLRT than would be represented by the as found condition. LLRT's were performed on the Purge Valves (7/25/85), the Escape (8/29/85) and Personnel (8/30/85) Batch as part of the Surveillance Program. All outstanding Naintenance Orders were reviewed to determine if any of the planned work would affect the seating of the containment isolation valves or affect the pressure boundary of a penetration. Por those items that affect the LLRT's, a LLRT was performed prior to and after Maintenance to provide as-found status of the LLRT's. An LLRT was performed on the transfer tube flange prior to its removal.

Approximately one month af ter purge initiation, LLRT's on the purge penetrations were performed. These initial LLRT's revealed unacceptably large leakage rates, which are typical for the purge valves after use. The cause for the large initial leakage rates is believed to be seat contamination caused by placing containment purge inservice.

The following summarises the purge and hatch LLRT's.

LLRT Description (acca) NOTES i' Pen 4 18 - CNTMT PURGE SUPPLY Quarterly ( 7/25/85) 2641 1

, Initial (10/18/85) 20458 2 i PreILRT (11/21/85) 256 Pen 4 19 CNTMT PURGE EXHAUST

i. Quarterly ( 7/25/85) 2196 1
Initial (10/18/85) 25250 2

! PreILRT (11/22/85) 1028

4 80NG8 3 1985 ILRT TEST REPORT PAG 3 15 9.0 AS-POUND ILRT (Continued)

LLRT Description (acca) NOTES Pen 6 203 - Escape Hatch ,

Semi-Annual (8/29/85) 174 3 Initial (11/20/85) 348 5 i

Pen 6 406 - Personnel Hatch Semi-Annual (8/30/85) 744 4 Initial & PreILRT (11/20/95) 4083 5 NOTES 1: 51 days prior to start of the outage and purge operation.

2: 34 days after start of the outage and purge operation.

3: 20 days prior to start of the outage.

4: 19 days prior to start of the outage.

53 62 days after start of the outage.

The As-Found ILRT was determined by adjusting the -ILRT results in the following manner: ,

The differences between the before-maintenance and after-maintenance LLRT's were added to the Type A Leakage.

9.1 BEFORE MAIhTENANCE & PRIOR TO PURGE OR OPENING MATCHES

! Before After Local Leak Rate Test Maintenance Mainterance Difference  !

l ...___________ .._________ ... ________ .___ -...... ..._______

LL (scca) 19709 13736 5973 LL (t/ day) 0.009 0.006 0.003 [

Total Time As-Found ILRT Las + Difference = .048 + 0.003 = 0.0514/ day 95% UCL + Difference = .052 + 0.003 = 0.055t/ day Mass Point As-Found ILRT Las + Difference = .051 + 0.003 = 0.054t/ day '

95% UCL + Difference = .052 + 0.003 = 0.055t/ day L 9.2 BEFORE MAINTENANCE & AFTER USE OF PURGE & HATCHES l Before After

! Local Leak Rate Test Maintenance Maintenance Difference l

i LL (scca) 64092 13736 50356 LL (t/ day) 0.029 0.006 0.023 I

t i f l

l l _ _ _ _ . . _ _ _ _ _ _. ._ . _ . . _ . _ _ _ _ _ _ _

i SONGS 3 1985'ILRT TEST REPORT PAGE 16 1

?

9.2 BEFORE NAINTENANCE & AFTER USE OF PURGE & HATCHES (Continued)

TotalTimbAs-FoundILRT Lam. + Difference = .048 + .523 = 0.0714/ day 954 UCL + Difference = .352 + .823 = 0.8754/ day Nass Point'As-Found ILRT Lam , + Difference = 851 + .523 = 0.974t/ day 95% UCL + Difference = .052 + .823 = 0.0754/ day The details of the . LLRT's shown above is recapped in the following table (See Page 17).

9.3 CONCLUSION

i No matter which philosophy is used for determining the As-Found LLRT, both analytical methods meet the Technical Specification requirement for the Type A leakage of less than or equal to 0.75 La (or 0.0754/ day).

f-4 6

6

.i e

4

i ', k .

I *

. SONGS 3'1985 ILRT TEST REPORT PAGE 17 1-UET 3 IfrX. IHK NEE' IIB'ieHEB fnID@t M M 4

asanonum mHomonnet REGt a islEH ISC Rn3 a isDG IEE - MElDRP PBi 'IIEE' ImeGC ME' IBe3 Ma' IBeim l 10. IEntDTEN UDE 10 set DEE (smal UEE , (sma$ UHE (san $

d

, 1- letUEGtsecut aamus s ansn1 IMIAE5 7 W21In 7IVidHe 32 -

, 2- ranneteInin assas a ama67 sv27/as 23m W27As 21sa W3es 2nd .

+- inrIm soeu
aamma, masp a anos sv2Ms 3ss sgzMs 3se IV es. se '

. 6- at nemtz mer aussu a m'maren mms sv2ps 4 W2Ms 4 .1 M e s 7

. 7- IC sueIsmarrr assan s ma:na e svaes a sv2Hs e

s- aus sur ma rzam assus a sumean22 WIMs 3 wuAs 3 W2Ms 3 ,

t Elue asam susseems a snnessas W3aps a wlMs e W W s5 e n- urusetamasino asen a sn43sen6 W2iAs 1 W2iAs 1w2Ms 1 i 1

12- as saa sosts m a n a anasta 3MsMs see w s M s see IV1ps 3 -

1> o u r a w In ossta m ese a 3masas WnAs 3sa wn/as 3m w n/as m2

14- rna samwww manasa s essans s/ans 2as sv2es 2as svae s 2as 15- anLwut' Inst aisons a inuos IV3Ms so Ivles se IVWas se 36*oor a sosts nameamen sv27As s sv27As e sv27/as e L 16sasse a sosts asenamsm $27As e sv27/as s sv27A s s 3dH::oorasosta 3 emus a 3w?ms IMuHe e3MuHz eapuvas s Ilh aer RRE a5str '#E8EM rsen, spes, sDe 7/255 26G 3045 Bes IV2W5 276 i

5- oor RRE Besur 350 sal, sEB, ssW, sesi 7/255 2197 WWE5 25a5 IV2W5 3s3 '

2s- anscaseatissar sussats73 a sussatazi W2Ms las $2Ms 3m sv2Ms la 21- saw K z a suas2stan a stamtes 1svzlAs desw2Ms de 3sMzMs 4m i 2> nanuara ammes a staaracs16 IVIMs u 3v1Ms n IV1ps n i

2> Ale anstrm sur anser a staestnut ways 3s W1Was n W1Ms 3s

2>s oor ADt sORz MJetE sV18@s i sVisHs 1 sv3sva5 1 2xaerasosta rusas sv1Ms i svisHs 1 svisHs 1 i

2F asuLossornL sn21stnse a sn23DnW1IVl@s 274 IV3Ms 274IVwas 274

, as erImusum 3eris12 a auns13 sv2Ms 21 sv2Ms 21 w20s 21

! 2x ourametR ames6 s aumni 3Mes e 3Muves e3euHs e

! asAourmmeta amest a swam W2Ms 2 W2Ms 2 wwas 2 1 3sa cormmeKm smass,3mals s amant le2]As n W21As n *zum n a 5 CIUra aBUIsNt 'esmu,assM s 3I3536 $27/95 7 $274 7 W274 7 i 31- a e r HI Rset 3m8946 s immaat mms 2as M $ 5 i'a M$t5 2as 39 3tN"EIraBeEIIIIFUeGB W3&ti 214 W3@t5 214 W36 tl 214 e- lascaraw nur ans211 s 3mman waps 132 W2es am w2es laa o- loeoerawonur 3musus a anusas 1svaes dat .1sMaes est W20s det e- one nosso usar ansees a 3sasas sgaes 13e sgaps las tv2 M s las e- oorlossLasur 3mem a anssai sgaps 157 sv2Hs a svaves 157 o- oorweE os wer ann 25e a sw2w sgaps as sv2Ms as 3Mys 2e 67- IstE-IC IGP 1 NR 3 Wee 4 s sI130tas7 s/145 6 W3Ms 6 3HQ/95 W ah nuseeramm sumanas a snmetam wuAs err WIMs eart W2es 21s

'5- AMIuJeersept sI1313tSU a M11'arma sv2Ms 4 sv2Ms 4W2Ws 4 I t

71- last-fC IEP 2 ItR 3R843 a fGlatels mms 6 FIMs 6 34tlAs la ~

l 74- In nutz ausen a 30ss38 s/Isps 72 s/1sHs 72 sv3sHe 72 7F is amormsEr asses a saauetase svwas 1ss Mes 3ss sgaes Joe Mb BestuctlupsE 3(25 IV3K95 174 IV44s 30s IV34s 30s l 33- MEntE30 NeeL 333 M74 347 M7As 347 3$tW5 34s l 31sh- RE35tI30 NIEL 3 31s M7As 18 67As 38 349Hs is 311- ItEntEX.IfIEL 3 331 M7As 21 M7/tl 21 M7As 21 31> EEBUDL1seeL 3312 M7As 139 M7/tl 119 M7/95 119 ab lus30eLlesof 3056 IV3Ms 74413/2Ms est 33/2Ms SKA 4L9- 10HNGr1950f 30G9 Geer $7/95 1 M7AE5 11VZW5 4

'ttal in sum 171 5 6432 17736 j 'ttal in V4 s.85 s.s3 s.56 e