Notice of Violation from Insp on 860128-31
ML20141N731
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/12/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20141N730 List:
References
50-414-86-08, 50-414-86-8, NUDOCS 8603180028
Download: ML20141N731 (2)


Text

= _ _ _ _

I 1

ENCLOSURE 1 NOTICE OF VIOLATION Duke Power Company Docket No. 50-414 Catawba Unit 2 License No. CPPR-117 The following violation was identified during an inspection conducted on January 28-31, 1986.

The Severity Level was assigned in accordance with the NRC Enforcement Policy (10 CFR Part 2, Appendix C).

Criterion V of Appendix B to 10 CFR Part 50, as implemented by FSAR, Chapter 17, Section 17.1.5 states:

" Activities affecting quality shall be accomplished in accordance with the instructions, procedures, or drawings."

The following procedural requirements apply to the Catawba 2 pipe support and restraint installation and inspection:

1.

Construction Procedure CP-115 requires that anchor bolt washers be in full contact with baseplates.

l 2.

Construction Procedure CP-635 requires that all non-NF welds be identi-fled and listed on CP-635A forms and indic1ted on hanger sketches.

[

3.

Finalwalkdowndocument(M-51c)requiresQAsign-off.

Contrary to the above, procedures for the installation, inspection, and documentation for pipe supports / restraints have not been met in that, 1.

On support 2-R-CA-CA-1645, the southeast anchor bolt has a gap of 1/8-inch because the washer is contacting a hanger weld.

2.

On support 2-R-CA-1645, and on hanger 2-R-NV-1083 the non-NF welds were not identified per CP-635.

3.

Final walkdown documentation for hangers no. 2-R-NS-1119 and 2-R-CA-1021 were not signed by QA.

ThisisaSeverityLevelVviolation(SupplementII.E).

Pursuant to 10 CFR 2.201, you are required to submit to this office within i

30 days of the date of this Notice, a written statement or explanation in reply, including:

(1) admission or denial of the alleged violations; (2) the reasons for the violations if admitted; (3) the corrective steps which have been taken j

and the results achieved; (4) corrective steps which will be taken to avoid further violations; and (5) the date when full compliance will be achieved, i

D oci !

ha l

i

Duke Power Company 2

Docket No. 50 414

' Catawba Unit 2 License No. CPPR-117 Security or safeguards information should be submitted as an enclosure to facill-l tate withholding it from public disclosure as required by 10 CFR 2.790(d) or i