ML20141N731

From kanterella
Jump to navigation Jump to search
Notice of Violation from Insp on 860128-31
ML20141N731
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/12/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20141N730 List:
References
50-414-86-08, 50-414-86-8, NUDOCS 8603180028
Download: ML20141N731 (2)


Text

= _ _ _ _ _ . _ _ _

I 1

ENCLOSURE 1 NOTICE OF VIOLATION Duke Power Company Docket No. 50-414 Catawba Unit 2 License No. CPPR-117 ,

The following violation was identified during an inspection conducted on January 28-31, 1986. The Severity Level was assigned in accordance with the NRC Enforcement Policy (10 CFR Part 2, Appendix C).

Criterion V of Appendix B to 10 CFR Part 50, as implemented by FSAR, Chapter 17, Section 17.1.5 states: " Activities affecting quality shall be accomplished in accordance with the instructions, procedures, or drawings."

The following procedural requirements apply to the Catawba 2 pipe support and restraint installation and inspection:

1. Construction Procedure CP-115 requires that anchor bolt washers be in full contact with baseplates. l
2. Construction Procedure CP-635 requires that all non-NF welds be identi- ,

fled and listed on CP-635A forms and indic1ted on hanger sketches. [

3. Finalwalkdowndocument(M-51c)requiresQAsign-off.

Contrary to the above, procedures for the installation, inspection, and documentation for pipe supports / restraints have not been met in that,

1. On support 2-R-CA-CA-1645, the southeast anchor bolt has a gap of 1/8-inch because the washer is contacting a hanger weld.

! 2. On support 2-R-CA-1645, and on hanger 2-R-NV-1083 the non-NF welds were not identified per CP-635.

3. Final walkdown documentation for hangers no. 2-R-NS-1119 and 2-R-CA-1021 were not signed by QA.

ThisisaSeverityLevelVviolation(SupplementII.E).

Pursuant to 10 CFR 2.201, you are required to submit to this office within i 30 days of the date of this Notice, a written statement or explanation in reply, including: (1) admission or denial of the alleged violations; (2) the reasons for the violations if admitted; (3) the corrective steps which have been taken j and the results achieved; (4) corrective steps which will be taken to avoid -

further violations; and (5) the date when full compliance will be achieved, i D oci !

ha -

l i

Duke Power Company 2 Docket No. 50 414

' Catawba Unit 2 License No. CPPR-117 Security or safeguards information should be submitted as an enclosure to facill- l tate withholding it from public disclosure as required by 10 CFR 2.790(d) or i 10 CFR 73.21. ,

Date: MR 18 m i i

e n I

e i

i P

f I

i I