MONTHYEARML20058E4401977-10-19019 October 1977 Rept on Flame Test Conducted on Cable Raceway Sys Project stage: Other ML20058E4371981-11-16016 November 1981 Flame Spread Classification Smoke & Fuel Contribution Project stage: Other ML20052G1511982-05-10010 May 1982 Forwards Notice of Exemption from Fire Protection Schedular Requirements of 10CFR50.48(c),clarification of Request for Info in Generic Ltr 81-12 & Info Re Criteria for Evaluating App R Exemption Requests Project stage: Approval ML20052G1531982-05-10010 May 1982 Notice of Exemption from Fire Protection Schedular Requirements of 10CFR50.48(c).Dates Extended to 820301. Clarification of Generic Ltr 81-12 & Info Re Criteria for Evaluating App R Exemption Requests Encl Project stage: Approval ML20058E4121982-07-16016 July 1982 Forwards Supplemental Info to Complete Response to 820301 Request for Exemption from App R Re Fire Protection Features Project stage: Supplement ML20058E4181982-07-16016 July 1982 Proposed Tech Spec Re Administrative Controls for Flammable Liquid Project stage: Other ML20058E4261982-07-31031 July 1982 Control Room Layout Project stage: Other B10630, Forwards Revision to Physical Security Plan.Revision Withheld (Ref 10CFR2.790)1982-12-0909 December 1982 Forwards Revision to Physical Security Plan.Revision Withheld (Ref 10CFR2.790) Project stage: Request B10796, Provides Addl Info Re Util Request for Exemption from 10CFR50,App R Re Control Room Fire Per 830318 Meeting. Alternate Operator Actions Can Be Completed to Facilitate Safe Shutdown Following Fire in Control Boards1983-05-25025 May 1983 Provides Addl Info Re Util Request for Exemption from 10CFR50,App R Re Control Room Fire Per 830318 Meeting. Alternate Operator Actions Can Be Completed to Facilitate Safe Shutdown Following Fire in Control Boards Project stage: Meeting ML20093E2731984-07-11011 July 1984 Suppls 830916 Request for Schedule Exemption from 10CFR50, App R & 10CFR50.48(c)(3).Request Removes Some Fire Zones, Provides List of Sys Affected in Fire Zones & Provides Compensatory Measures Consistent W/Nrc Guidance Project stage: Request ML20095L2071984-08-23023 August 1984 Exemption from Schedular Requirements Re Fire Protection of Equipment Used for Safe Shutdown by Means of Separation & Barriers Project stage: Approval B11426, Forwards Supplemental Info Supporting App R Control Exemption Request.Info Addresses Proposed Mods,Control Room Habitability,Fire Brigade Actions & Communications Between Operators & Fire Brigade Members1985-01-31031 January 1985 Forwards Supplemental Info Supporting App R Control Exemption Request.Info Addresses Proposed Mods,Control Room Habitability,Fire Brigade Actions & Communications Between Operators & Fire Brigade Members Project stage: Supplement B11637, Forwards Addl Info Re App R Exemption Requests,Per 850627 Request.Measure of Protection Used to Ensure Switchboard Wire Associated W/Msiv Solenoid Valves Will Not Be Susceptible to Hot Shorts Discussed1985-08-0707 August 1985 Forwards Addl Info Re App R Exemption Requests,Per 850627 Request.Measure of Protection Used to Ensure Switchboard Wire Associated W/Msiv Solenoid Valves Will Not Be Susceptible to Hot Shorts Discussed Project stage: Other B11644, Responds to 850715 Verbal Request for Addl Info Re App R Control Room Exemption Request.Info on How Total Flooding Halon Sys Meets NFPA-12A Code Requirements & Alternative Actions During Temporary Sys Unavailability Encl1985-08-23023 August 1985 Responds to 850715 Verbal Request for Addl Info Re App R Control Room Exemption Request.Info on How Total Flooding Halon Sys Meets NFPA-12A Code Requirements & Alternative Actions During Temporary Sys Unavailability Encl Project stage: Request ML20141M7881986-02-0404 February 1986 Notice of Environ Assessment & Finding of No Significant Impact Re Requests for Exemption from Requirements of 10CFR50,App R,Granting Relief in Eight Fire Areas Project stage: Approval ML20203B2671986-04-0707 April 1986 Submits Addl Info Re Pending Util Requests for Exemptions from 10CFR50,App R Re Revised 10CFR50.12,per 860307 Request. Special Circumstances Exist for Granting Exemptions Project stage: Other ML20203E9001986-04-15015 April 1986 Safety Evaluation Supporting Exemption from 10CFR50,App R, Section Iii.G Fire Protection Requirements Project stage: Approval ML20203E8751986-04-15015 April 1986 Exemption from 10CFR50,App R,Section Iii.G Fire Protection Requirements Re Cable & Equipment Separation to Protect Redundant Trains of Safe Shutdown Sys Project stage: Approval 1984-07-11
[Table View] |
Text
(
7590-01 UNITED STATES NUCLEAR REGULATORY COMMISSION NORTHEAST NUCLEAR ENERGY COMPANY DOCKET NO. 50-336 ENVIRONMENTAL ASSESSMENT AND FINDING 0F NO SIGNIFICANT IMPACT The U. S. Nuclear Regulatory Commission (the Commission) is considering issuance of an exemption from the requirements of Appendix R to 10 CFR Part 50 to Northeast Nuclear Energy Company, et al. (the licensee), for the Millstone Nuclear Power Station, Unit No. 2, located in New London County, Connecticut.
ENVIRONMENTAL ASSESSMENT Identification of Proposed Action: The exemption would grant relief in eight fire areas to the extent that redundant safe shutdown related cable and equipment are not separated and/or protected in accordance with Section III.G.2 of Appendix R.
The eight fire areas are as follows: Main Control Room, Closed Cooling Water Pump /.rea, Boric Acid Pump Area, Chemical-Addition Tank Area, Cable Vault, Intake Building, Charging Pump Room and Auxiliary Feed Pump Pit.
Also, the exemption would grant relief for the main control room from the req:Iirements of Sections III.G.3 and III.L of Appendix R concerning independence for the alternate shutdown capability.
n The exemptions are responsive to the licensee's applications for exemptions
- ij dated March 1 and July 16,1982; April 15 and May 25, 1983, and January 31 and I.
August 7, 1985.
9 The Need for the Proposed Action: The proposed exemption is needed because j
the. features described in the 1.icensee's requests regarding the existing and j
proposed fire prote' tion at the plant for these items are the most practical methods for meeting the intent of Appendix R and literal compliance would not significantly enhance the fire protection capability.
NO
$6 F
, _ _ -,_ n_,
~
.2_
-i Environmental Impacts of the Proposed Action: The proposed exemption will provide a degree of fire protection such that there is no increase in the i
risk of fires at this facility. Consequently, the probability of fires has not been increased and the post-fire radiological releases will not be greater than previously determined nor does the proposed exemption otherwise affect radiological plant effluents. Therefore, the Commission concludes that there are no significant radiological environmental impacts associated with q
this proposed exemption.
With regard to potential nonradiological impacts, the proposed exemption involves features located entirely within the restricted area as defined in 10 CFR Part 20. They do not affect nonradiological plant effluents and have 1
no other environmental impact. Therefore, the Commission concludes that there are no significant nonradiological environmental impacts associated with the pfoposed e,xemption.
Alternative Use of Resources: This action involves no use of resources not previously considered in the Final Environmental Statements for the Millstone Nuclear Power Station, Unit No. 2.
1 Agencies and Per' sons Consulted:
The NRC staff reviewed the licensee's request and did not consult other agencies or persons.
FINDING 0F NO SIGNIFICANT IMPACT The Commission has determined not to prepare an environmental impact statement for the proposed exemption.
Based upon the foregoing environmental assessment, we conclude that the s
proposed action will not have a significant effect on the quality of the human environment.
h
_s.
7 I
j For further details with respect to this action, see the applications for the exemptions previously listed, which are available for public inspection at the Comission's Public Document Room,1717 H Street, N.W., Washington, D.C.,
and at the Waterford Public Library, 49 Rope Ferry Road, Waterford, Connecticut 06385.
\\
Dated at Bethesda, Maryland this 4th day of February,1986.
FOR THE UCLEARREGUAATORYCOMMISSION (Y6T Ashok Thadani, Director PWR Project Directorate #8 Division of PWR Licensing-B e