:on 970423,determined That Test Criteria for H Recombiner Was Inappropriate.Caused by Low Std for for Documentation of Changes to Vendor Recommendations. Will Review Results of 1995 TS Compliance Self Assessment| ML20141K954 |
| Person / Time |
|---|
| Site: |
Zion File:ZionSolutions icon.png |
|---|
| Issue date: |
05/23/1997 |
|---|
| From: |
Brennan N COMMONWEALTH EDISON CO. |
|---|
| To: |
|
|---|
| Shared Package |
|---|
| ML20141K952 |
List: |
|---|
| References |
|---|
| LER-97-012-02, LER-97-12-2, NUDOCS 9706020157 |
| Download: ML20141K954 (5) |
|
Similar Documents at Zion |
|---|
|
text
-
l e
l LICENSEE EVENT REPORT (LER)
FACILITY NAME 30CKET NUMBER PAGE 0l5l0l0l0l2l9l5 1 l0Fl 0 l 5 j
ZION NUCLEAR POWER STATION TITLE INAPPROPRIATE TEST CRITERIA FOR HYOR0 GEN RECOMBINER BECAUSE OF INTERPRETATION OF TECH SPECS WITH MINIMAL IMPACT ON PLANT.
EVENT DATE LER NUMBER REPORT DATE OTHER FACILITIES INVOLVED MONTH DAY YEAR YEAR SEO.
REV.
MONTH DAY YEAR FACILITY NAMES DOCKET NUMBER (S)
ZION UNIT 7 0 l 5 l 0 l 0 l 0 l 3 l 0 l4 nl4 213 1
ol7 o
7 c1112 ole ois 213 ol7 I I I I I I I THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR $: (CHECK ONE OR MORE OF THE FOLLOWING) 6 20.402(b) 20.405(e) 50.73(a)(2)(iv) 73.71(b)
POWER 20.405(a)(1)(i) 50.36(c)(1) 50.73(a)(2)(v) 73.71(c) 0l0l0 LEVEL 20.405(a)(1)(ti) 50.36(c)(2) 50.73(a)(2)(vti)
OTHER (Specify in 20.405(a)(1)(fii)
X 50.73(a)(2)(1) 50.73(a)(2)(viii)(A)
Abstract below 20.405(a)(1)(iv) 50.73(a)(2)(ti) 50.73(a)(2)(viii)(B) l 36 20.405(a)(1)(v) 50.73(a)(2)(iii) 50.73(a)(2)(x)
LICENSEE CONTACT FOR THIS LER NAME TFtFPHONr NUMRrR Neil Brennan, Root Cause Ext. 2380 e1417 714181-12l ale 14 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT
^
^
CAUSE
SYSTEM COMPONENT MANUFACTURER
CAUSE
SYSTEM COMPONENT MANUFACTURER Y
TO NPROS TO NPRDS I
I l l I I I I
I I I I II I
I I I I I I I
I I I I I I
)
SUPPLEMENTAL REPORT EXPECTED EXPECTED MONTH DAY YEAR SUBMISSION
)
YES. (If yes. complete EXPECTED SUBMISSION DATE)
M NO DATE l
l l
ABSTRACT (Limit to 1400 spaces. i.e.
approximately fifteen single-space typewritten lines).
Technical specification #4.8.8. A requires readiness testing of the hydrogen recombiner in accordance with the manuf acturer's recommended tests. The plant testing procedures did not include the manufacturer's acceptance criteria for testing. Because the station tests contained acceptance criteria which were less restrictive. the specification requirements were not met. However, the testing performed j
was sufficient to confirm that the hydrogen recombiner would function as required to mitigate the effects of an accident. Though the specific root cause of the ever.t could not be determined. the apparent cause of the event was a low standard for documentation of changes to vendor information and for explicit Technical Specification compliance at Zion Station which assumed the Technical Specifications could be interpreted rather than followed explicitly. There was minimal safety significance to this event.
Corrective actions include: 1) changing the high level and low level test criteria to conform to the manufacturer's recommendations.
- 2) updating of the on site vendor manual to reflect new vendor recommendations. 3) the results of the 1995 Technical Specification compliance self assessment will be reviewed to ensure that other findings have been appropriately addressed.
I l
9706020157 970523 PDR ADOCK 05000295 S
PDR g:\\zler\\97012.ler(l)
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME DOCKET NUMBER LER NUMBER PAGE YEAR SEO.
REV.
ZION NUCLEAR POWER STATION 0l5l0l0l0l2l9l5 9l7 0l1l2 0l0 0l2 0l5
~
~
0F TEXT Energy Industry Identification System (EIIS) codes are identified in the text as [XX]
A.
PLANT CONDITIONS PRIOR TO EVENT Unit 1 MODE 6 - Refueling Rx Power 0%
RCS [AB] 74' F Atmospheric Pressure Unit 2 MODE 5 - CSD Rx Power 0%
RCS 83 F Atmospheric Pressure B.
DESCRIPTION OF EVENT
Surveillance testing of the hydrogen recombiner [BB] does not meet the Technical Specification requirement of testing in accordance with the manufacturer's recommendation as documented in the vendor technical information of record.
An independent line-by-line review of Technical Specification surveillance requirements and their im)lementing procedures was performed in response to a previous NRC commitment.
Durino tlat review process discre]ancies were found with station compliance to Technicai Specification 4.8.8.A. whic1 requires a low level and high level " readiness test in accordance with the manufacturers recommendations." A comparison was made between the manufacturer's recommended tests and the tests performed by the station.
Some of the control points and time intervals were not
)
consistent.
The tests in question are PT-15C. " Hydrogen Recombiner Low Level Readiness Test." that is performed semiannually, and TSS-15.6.105. " Hydrogen Recombiner High Level Readiness Test." that is ]erformed every five years. The low level readiness test is performed on a six mont, frequency to satisfy the requirements of the functional test.
During the initial investigation completed in November 1995.
the System Engineer determined that test procedures were consistent with the manufacturer's recommendation.
However, this was based on an understanding that the manufacturer's recommendations had changed during conversations between previous
{
System Engineers and vendor personnel.
Recent review as a result of increased emphasis on Technical Specificaticn compliance determined that the manufacturer's tests specified in the vendor technical information of record and station's tests are in conflict. The differences in heatup rates between vendor recommendation and the Zion test procedures are as follows:
l l
[
g:\\zler\\97012.ler(2)
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME DOCKET NUMBER LER NUMBER PAGE YEAR SEO.
REV.
ZION NUCLEAR POWER STATION 0l5l0l0l0l2l9l5 9l7 0l1l2 0l0 0l4 0l5
~
0F TEXT Energy Industry Identification System (EIIS) codes are identified in the text as [XX)
D.
SAFETY ANALYSIS
This inappropriate test criteria has minimal safety significance.
Per UFSAR Section 6.2.5.1. the Hydrogen Recombiner System is designed to control combustible gas i
(hydrogen and oxygen) in the Containment atmosphere during a Loss of Coolant Accident (LOCA).
Per UFSAR 15.6.5.6. the hydrogen recombiners are operated under the following conditions: hy M en concentration in the containment is less than 4% and containment pressure is be h I wig.
For the design basis LOCA this pressure is achieved after approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.to the LOCA.
At 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />, the postulated hydrogen concentration is well 4 Mw 4%.
The limit of 4% for hydrogen concentration in containment is not rea6 antil after greater than 30 days.
During a LOCA. the operation of the Hydrogen Recombiner is directed by the Technical Support Center as stated in Emergency Operating Procedure E-1 (Loss of Reactor or Secondary Coolant) step 21.
Operational guidance is provided in System Operating Instruction S0I-9G (Hydrogen Recombiner 0)eration After a LOCA).
These procedures provide guidance to connect the Hydrogen Recombiner based on plant conditions.
Per l
the UFSAR the recombiner may be connected any time after 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> following a LOCA and prior to approximately 30 days after a LOCA.
Consecuently, the discrepancy in the test criteria for heat up rates is not significant cue to the substantial amount of time available to align the recombiner for operation after an accident.
The operating temperature of the Hydrogen Recombiner is based on the auto-ignition temperature for hydrogen.
At a specific temperature, hydrogen and oxygen exothermically react and recombine to form water.
Based on the Condensed Chemical Dictionary (Tenth Edition revised by Gessner G. Hawley), this temperature is 1075 degrees F.
The minimum acceptable temperature in the Zion high level readiness test is 1100 degrees F.
Thus, the ability of the hydrogen recombiner to achieve the temperatures required to perform its function is confirmed by the Zion test criteria.
)
In addition, a review of nine low level performance tests showed that the equipment did res)ond in accordance with recommendations by the manufacturer.
Although the time to reac1600 F was not specifically documented in the tests, the tests require operators to record the system temperatures at 15 minute increments.
Eight of the nine tests showed that the heater outlet temperature was greater than 600 F at the i
thirty minute increment.
One test was not greater than 600 degress F at thirty minutes but was at 45 minutes.
A review of high level readiness tests found that the manufacturer's criteria specified in the vendor technical information manual of record were not met.
The time required to attain 1300 F was approximately two hours rather than the fifty minutes prescribed in the manufacturer's operating manual.
A review of the station's pre-operational test and the manufacturer's pre-shi) ment shop test indicated that a two hour heatup to 1300 F is expected.
The vendor las stated that the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> heatup time is apr 7priate for the Zion recombiners.
However, the heater size installed at Zion is sufhcient to attain the temperature necessary to perform the required function and I
would remove hydrogen as required for post accident usage. Therefore, there was minimal safety impact on the plant.
9 :\\zler\\97012.ler(4) l
LICENSEE EVENT REPORT (LER) TEXT CONTINVATION FACILITY NAME DOCKET NUMBER LER NUMBER PAGE YEAR SEO.
REV.
ZION NUCLEAR POWER STATION 0l5l0l0l0l2l9l5 9l7 0l1l2 0l0 0l5 0l5
~
0F TEXT Energy Industry Identification System (EIIS) codes are identified in the text as (XX)
L E.
CORRECTIVE ACTIONS
1.
The low level readiness test 3rocedure (PT-15C) will be changed prior to the next performance to include t1e manufacturer's acceptance criteria.
2.
The high level readiness test procedure (TSS-15.6.105) m ll be changed prior to the next performance to include the updated manufacturer s acceptance criteria.
3.
Technical Specification amendment policies in place now require detailed review and personal accountability for changes to the Technical Specification to ensure comph ance.
4.
The onsite vendor manual for the Hydrogen Recombiner will be updated to reflect the new vendor recommendations.
5.
Management's expectations for maintaining procedural and Technical Specification ccep iance were communicated to personnel during a series of meetings conducted in the fall of 1996.
6.
The results of the 1995 Technical Specification Compliance Self Assessment will be reviewed to ensure that other findings have been appropriately addressed.
F.
PREVIOUS EVENTS SEARCH AND ANALYSIS Emergency Diesel Generator Re? orts were issued late because Regulatory Assurance personnel misinterpreted the Regulatory Reporting Requirements.
Containment Sump Recirculation Level Calibration was placed on wrong inspection frequency due to Technical Specification misinterpretation.
There are other Licensee Event Reports such as the missed surveillance for Radiation Monitors and Steam Line Flow.
G.
COMPONENT FAILURE DATA
None r
l g.\\zler\\97012.ler(j)
~
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000295/LER-1997-001-01, Forwards LER 97-001-01,which Clarifies Info on Root Cause,Safety Analysis & Event Description.Corrective Actions Updated to Show Status of Items | Forwards LER 97-001-01,which Clarifies Info on Root Cause,Safety Analysis & Event Description.Corrective Actions Updated to Show Status of Items | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000295/LER-1997-001, Forwards LER 97-001-00 Which Involved Discovery of Lack of Sump Cover Plate Holes Contrary to Plant Structural Drawing Details,Per 10CFR50.73(a)(2)(ii)(B) | Forwards LER 97-001-00 Which Involved Discovery of Lack of Sump Cover Plate Holes Contrary to Plant Structural Drawing Details,Per 10CFR50.73(a)(2)(ii)(B) | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000295/LER-1997-001-14, :on 970110,recirculation Sump Cover Plate Holes Were Not Installed at Original Construction.Caused by Construction Error.Holes Installed IAW Emergency Exempt Change Prepared Prior to Ramp Down |
- on 970110,recirculation Sump Cover Plate Holes Were Not Installed at Original Construction.Caused by Construction Error.Holes Installed IAW Emergency Exempt Change Prepared Prior to Ramp Down
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) 10 CFR 50.73(e)(2) | | 05000295/LER-1997-001-03, :on 970110,recirculation Sump Covers Were Not Installed at Original Construction.Cause Is Unknown & Impact on Plant Operation Is Unknown.Sump Cover Was Removed,Holes Were Drilled & Cover Replaced Prior to Expiration of LCO |
- on 970110,recirculation Sump Covers Were Not Installed at Original Construction.Cause Is Unknown & Impact on Plant Operation Is Unknown.Sump Cover Was Removed,Holes Were Drilled & Cover Replaced Prior to Expiration of LCO
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-001-11, :on 970902,Unit 2 Instrument Bus Perturbation Occurred.Caused by Insufficient Policy/Guidelines. Development of Policy for Proper Use of Protective Gear, Equipment & Tools |
- on 970902,Unit 2 Instrument Bus Perturbation Occurred.Caused by Insufficient Policy/Guidelines. Development of Policy for Proper Use of Protective Gear, Equipment & Tools
| 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-001, Forwards LER 97-001-00 Per 10CFR50.73(a)(2)(iv) Which Requires Written Rept Using NRC Form 366, License Event Rept, within 90 Days of Discovery of Event.Attachment a Contains Commitments Associated W/Ltr | Forwards LER 97-001-00 Per 10CFR50.73(a)(2)(iv) Which Requires Written Rept Using NRC Form 366, License Event Rept, within 90 Days of Discovery of Event.Attachment a Contains Commitments Associated W/Ltr | 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000295/LER-1997-002, Forwards LER 97-002-00.Commitments Made by Util Listed | Forwards LER 97-002-00.Commitments Made by Util Listed | 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-002-01, :on 970117,containment Isolation Valves Were Not Tested Prior to Leaving Cold Shutdown.Caused by Mgt Deficiencies in TS Implementation Process.Containment Isolation Valves Will Be Verified Tested Prior to Mode 4 |
- on 970117,containment Isolation Valves Were Not Tested Prior to Leaving Cold Shutdown.Caused by Mgt Deficiencies in TS Implementation Process.Containment Isolation Valves Will Be Verified Tested Prior to Mode 4
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-002-09, :on 971012,inadvertent Isolation of Svc Water Cooling to 2B DG During Sys Alignment,Occurred.Caused by Shift Mgt Not Ensuring All Operability Requirements Met. Valve 2MOV-SW0023 Opened to Restore Flow to 2B EDG |
- on 971012,inadvertent Isolation of Svc Water Cooling to 2B DG During Sys Alignment,Occurred.Caused by Shift Mgt Not Ensuring All Operability Requirements Met. Valve 2MOV-SW0023 Opened to Restore Flow to 2B EDG
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-002, Forwards LER 97-002-00,per 10CFR50.73(a)(2)(v)(B),which Requires 30 Day Written Rept.Commitments Associated W/Correspondence,Encl | Forwards LER 97-002-00,per 10CFR50.73(a)(2)(v)(B),which Requires 30 Day Written Rept.Commitments Associated W/Correspondence,Encl | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | | 05000295/LER-1997-003, :on 970117,determined That EDG Tests Completed in Previous Refueling Outages Failed to Meet TS Requirement. Caused by Programmatic Deficiencies.Corrected Deficient Procedures & Completed Tests on Operating Unit |
- on 970117,determined That EDG Tests Completed in Previous Refueling Outages Failed to Meet TS Requirement. Caused by Programmatic Deficiencies.Corrected Deficient Procedures & Completed Tests on Operating Unit
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-003, Forwards LER 97-003-00 Re Unit 2 RHR Sys Declared Inoperable,Per 10CFR50.73(a)(2)(v)(B) | Forwards LER 97-003-00 Re Unit 2 RHR Sys Declared Inoperable,Per 10CFR50.73(a)(2)(v)(B) | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2) | | 05000304/LER-1997-003-10, :on 971014,unit 2 RHR Sys Declared Inoperable. Caused by Oil Leak from Oil Bulb.Leak Coming from Oil Bulb on Ob CC Pump Stopped by Removing Bulb & Inspected |
- on 971014,unit 2 RHR Sys Declared Inoperable. Caused by Oil Leak from Oil Bulb.Leak Coming from Oil Bulb on Ob CC Pump Stopped by Removing Bulb & Inspected
| 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) | | 05000304/LER-1997-004-08, :on 971015,small Bore Containment Penetration Line Inadequately Supported Since Plant Construction Was Noted.Cause Cannot Be determined.Non-destructive Exams Performed to Determine Condition & Integrity of Pipe |
- on 971015,small Bore Containment Penetration Line Inadequately Supported Since Plant Construction Was Noted.Cause Cannot Be determined.Non-destructive Exams Performed to Determine Condition & Integrity of Pipe
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2) | | 05000304/LER-1997-004, Forwards LER 97-004-00,per 10CFR50.73(a)(2)(i).Commitments Associated W/Correspondence,Encl | Forwards LER 97-004-00,per 10CFR50.73(a)(2)(i).Commitments Associated W/Correspondence,Encl | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000295/LER-1997-004, Forwards LER 97-004-00 Re Failure to Start Pump in Required Time & Led to Declaring 1C Containment Spray Pump Inoperable | Forwards LER 97-004-00 Re Failure to Start Pump in Required Time & Led to Declaring 1C Containment Spray Pump Inoperable | | | 05000295/LER-1997-004-04, :on 970221,identified Failure to Start Pump in Required Time & Led to Declaring 1C Containment Spray Inoperable.Caused by Clogged Fuel Filter & Defective components.1C Containment Spray Pump Fuel Drained & Flushed |
- on 970221,identified Failure to Start Pump in Required Time & Led to Declaring 1C Containment Spray Inoperable.Caused by Clogged Fuel Filter & Defective components.1C Containment Spray Pump Fuel Drained & Flushed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-004-01, :on 970221,reactor Was Shutdown,Per LCO 3.6.1 Due to One Inoperable Containment Spray pump.1C CS Pump Day Tank Was Drained,Flushed,Refilled w/biocide-added Fuel from Different Source |
- on 970221,reactor Was Shutdown,Per LCO 3.6.1 Due to One Inoperable Containment Spray pump.1C CS Pump Day Tank Was Drained,Flushed,Refilled w/biocide-added Fuel from Different Source
| 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000295/LER-1997-005, Forwards LER 97-005-00 IAW 10CFR50.73(a)(2)(i)(B).Actions Listed | Forwards LER 97-005-00 IAW 10CFR50.73(a)(2)(i)(B).Actions Listed | 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-005, Forwards LER 97-005-00 Which Documents Event That Occurred at Zion Nuclear Power Station,Unit 2.Commitment Made within Ltr,Encl | Forwards LER 97-005-00 Which Documents Event That Occurred at Zion Nuclear Power Station,Unit 2.Commitment Made within Ltr,Encl | 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-005-07, :on 971021,failed to Test 2A SI Pump Suction Valve in Prescribed Periodicity.Caused by Inadequate Program to Ensure That TS IST Requirements for Each Component Are Met.Ist Group Will Include Second Check in Review |
- on 971021,failed to Test 2A SI Pump Suction Valve in Prescribed Periodicity.Caused by Inadequate Program to Ensure That TS IST Requirements for Each Component Are Met.Ist Group Will Include Second Check in Review
| 10 CFR 50.73(a)(1), Submit an LER 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2) | | 05000295/LER-1997-005-03, :on 970221,supplement to Unapproved Mode Change W/Ts Required Equipment Inoperable Were Noted.Caused by Inadequate Planning & Briefing.Both Units Have Been Placed in Cold Shutdown W/Rcs at Atmospheric Pressure |
- on 970221,supplement to Unapproved Mode Change W/Ts Required Equipment Inoperable Were Noted.Caused by Inadequate Planning & Briefing.Both Units Have Been Placed in Cold Shutdown W/Rcs at Atmospheric Pressure
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(viii)(B) | | 05000304/LER-1997-006-07, :on 971028,informed of Potential to Exceed 10CFR50.46 ECCS Acceptance Criteria.Caused by Fuel Clad Gap re-opening & 17% Maximum Cladding Oxidation Limit.Performed Conservative Corrosion Calculations |
- on 971028,informed of Potential to Exceed 10CFR50.46 ECCS Acceptance Criteria.Caused by Fuel Clad Gap re-opening & 17% Maximum Cladding Oxidation Limit.Performed Conservative Corrosion Calculations
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) | | 05000304/LER-1997-006, Forwards LER 97-006-00 Per 10CFR50.73(a)92)(ii)(B) Which Requires 30 Day Written Rept When Any Event or Condition Occurs That Resulted in Condition of Nuclear Power Plant. Regulatory Commitments Encl | Forwards LER 97-006-00 Per 10CFR50.73(a)92)(ii)(B) Which Requires 30 Day Written Rept When Any Event or Condition Occurs That Resulted in Condition of Nuclear Power Plant. Regulatory Commitments Encl | 10 CFR 50.73(a)(2) | | 05000295/LER-1997-006, :on 970222,Zion Station Exceeded Limiting Condition for Operation Due to Inadequate Procedure Controls.Standing Order to Require Review of TS During OOS Procedure Implementation,Was Issued |
- on 970222,Zion Station Exceeded Limiting Condition for Operation Due to Inadequate Procedure Controls.Standing Order to Require Review of TS During OOS Procedure Implementation,Was Issued
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-007-06, :on 971030,failure to Maintain Required Number of Svc Water Pumps Operable Was Identified.Caused by Failure of Mgt Personnel to Adhere to Requirements for Reviewers to Use Applicable Drawings.Procedure Rev to Provide Guidanc |
- on 971030,failure to Maintain Required Number of Svc Water Pumps Operable Was Identified.Caused by Failure of Mgt Personnel to Adhere to Requirements for Reviewers to Use Applicable Drawings.Procedure Rev to Provide Guidance
| 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-007-02, :on 970311,operator Opened Local Sys Auxiliary Transformer Panel.Cause of Sys Auxiliary Transformer Trip Could Not Be Conclusively Determined.Unit 2 Sys Auxiliary Transformer Tested for Damage |
- on 970311,operator Opened Local Sys Auxiliary Transformer Panel.Cause of Sys Auxiliary Transformer Trip Could Not Be Conclusively Determined.Unit 2 Sys Auxiliary Transformer Tested for Damage
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) 10 CFR 50.73(a)(7)(ii) | | 05000295/LER-1997-007, Forwards LER 97-007-00 Re Automatic Actuation of Esf. Submitted Table Identifies Actions Committed to by Util | Forwards LER 97-007-00 Re Automatic Actuation of Esf. Submitted Table Identifies Actions Committed to by Util | 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000304/LER-1997-007, Forwards LER 97-007-00 Per 10CFR50.73(a)(2)(v)(B) Which Requires Written Rept for Any Event or Condition That Could Prevent Fulfillment of Safety Function of Structures or Sys Needed to Remove Residual Heat.W/Commitments Attach | Forwards LER 97-007-00 Per 10CFR50.73(a)(2)(v)(B) Which Requires Written Rept for Any Event or Condition That Could Prevent Fulfillment of Safety Function of Structures or Sys Needed to Remove Residual Heat.W/Commitments Attached | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | | 05000295/LER-1997-008, :on 970321,air Filters Containing Al Were Inadvertently Installed in Containment Due to Faulty Parts Selection Process.Hepa Filters Containing Al Will Be Removed or Replaced w/non-Al Containing Filters |
- on 970321,air Filters Containing Al Were Inadvertently Installed in Containment Due to Faulty Parts Selection Process.Hepa Filters Containing Al Will Be Removed or Replaced w/non-Al Containing Filters
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-008-07, :on 971122,safety Related Snubber Not in Snubber Program & Subsequently Was Not Inspected Per Ts. Cause Unknown.Procedure TSS 15.6.48 Revised to Incorporate Unit 2 Snubber |
- on 971122,safety Related Snubber Not in Snubber Program & Subsequently Was Not Inspected Per Ts. Cause Unknown.Procedure TSS 15.6.48 Revised to Incorporate Unit 2 Snubber
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-008, Forwards LER 97-008-00 Per 10CFR50.73(a)(2)(i)(B),which Requires 30 Day Written Rept.Attachment a Provides Commitments Associated W/Correspondence | Forwards LER 97-008-00 Per 10CFR50.73(a)(2)(i)(B),which Requires 30 Day Written Rept.Attachment a Provides Commitments Associated W/Correspondence | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000295/LER-1997-009-01, :on 970114,1FCV-CS0002 Was Inoperable Between 970115 & 0208.Caused by Failure to Verify That Acceptance Criteria for Return to Service Was Met.Disciplined Unit Supervisor & Will Cover Event in Licensed Operator Training |
- on 970114,1FCV-CS0002 Was Inoperable Between 970115 & 0208.Caused by Failure to Verify That Acceptance Criteria for Return to Service Was Met.Disciplined Unit Supervisor & Will Cover Event in Licensed Operator Training
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-009, Forwards LER 97-009-00 IAW 10CFR50.73(A)(2)(i)(B) Which Requires Listed Corrective Actions | Forwards LER 97-009-00 IAW 10CFR50.73(A)(2)(i)(B) Which Requires Listed Corrective Actions | | | 05000304/LER-1997-009-08, :on 971202,test Relay SIX1-AX Did Not Unlatch as Required During Restoration of PT 10-3.Caused by Failure to Follow Procedures.Rewired Test Relay SIX1-AX |
- on 971202,test Relay SIX1-AX Did Not Unlatch as Required During Restoration of PT 10-3.Caused by Failure to Follow Procedures.Rewired Test Relay SIX1-AX
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000304/LER-1997-009, Forwards LER 97-009-00,re Event Which Occurred at Zion Nuclear Power Station,Unit 2.Commitments Made within Ltr Also Encl | Forwards LER 97-009-00,re Event Which Occurred at Zion Nuclear Power Station,Unit 2.Commitments Made within Ltr Also Encl | 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000295/LER-1997-010, :on 960316,reactor Trip Due to Equipment Failure Occurred.Caused by New But Defective Pneumatic Vol Booster on Valve.Pneumatic Vol Booster for 1C Main FW Regulating Valve Replaced |
- on 960316,reactor Trip Due to Equipment Failure Occurred.Caused by New But Defective Pneumatic Vol Booster on Valve.Pneumatic Vol Booster for 1C Main FW Regulating Valve Replaced
| 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000295/LER-1997-010-01, :on 970404,radiation Area Surveys Were Missed. Caused by Inadequate TS Review.Nso,Unit Supervisor & Shift Engineer,Counseled |
- on 970404,radiation Area Surveys Were Missed. Caused by Inadequate TS Review.Nso,Unit Supervisor & Shift Engineer,Counseled
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000295/LER-1997-012-02, :on 970423,determined That Test Criteria for H Recombiner Was Inappropriate.Caused by Low Std for for Documentation of Changes to Vendor Recommendations. Will Review Results of 1995 TS Compliance Self Assessment |
- on 970423,determined That Test Criteria for H Recombiner Was Inappropriate.Caused by Low Std for for Documentation of Changes to Vendor Recommendations. Will Review Results of 1995 TS Compliance Self Assessment
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-012, Forwards LER 97-012-00,which Documents 970423 Event That Occurred at Zion Generating Station.Commitments Made by Util,Listed | Forwards LER 97-012-00,which Documents 970423 Event That Occurred at Zion Generating Station.Commitments Made by Util,Listed | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000295/LER-1997-013-02, :on 970412,VT-3 Insp Requirements of Relief Request CR-13 for Reactor Head Bolting Were Not Performed. Caused by Failure to Revise ISI Database After SER Received from Nrc.Procedure Revised |
- on 970412,VT-3 Insp Requirements of Relief Request CR-13 for Reactor Head Bolting Were Not Performed. Caused by Failure to Revise ISI Database After SER Received from Nrc.Procedure Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-014-02, :on 970502,TS Surveillances on Radiation Monitors Were Missed Because Technical Interpretation That Kept 1(2)RT-PR15 Operable Was Inoperable.Revised Station Procedures |
- on 970502,TS Surveillances on Radiation Monitors Were Missed Because Technical Interpretation That Kept 1(2)RT-PR15 Operable Was Inoperable.Revised Station Procedures
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-015-01, :on 970724,Unit 1 EDGs & Unit 2 RHR Sys Was Declared Inoperable Which Resulted in Inadvertent ESF While Performing TS Related Surveillance.Caused by Unclear Expectations.Declared EDG Operable on 970729 |
- on 970724,Unit 1 EDGs & Unit 2 RHR Sys Was Declared Inoperable Which Resulted in Inadvertent ESF While Performing TS Related Surveillance.Caused by Unclear Expectations.Declared EDG Operable on 970729
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000295/LER-1997-015-02, :on 970724,Unit 1 EDGs & Unit 2 RHR Sys Were Declared Inoperable & Inadvertent Esg Actuation Was Noted While Performing TS Related Surveillances.Cause Is Under Investigation.Restored ESF Equipment |
- on 970724,Unit 1 EDGs & Unit 2 RHR Sys Were Declared Inoperable & Inadvertent Esg Actuation Was Noted While Performing TS Related Surveillances.Cause Is Under Investigation.Restored ESF Equipment
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) | | 05000295/LER-1997-016-01, Forwards LER 97-016-01,which Clarifies Info on Event Description,Root Causes & Safety Analysis.Cas Have Been Updated.Attachment a Provides Commitments Associated W/ Correspondence | Forwards LER 97-016-01,which Clarifies Info on Event Description,Root Causes & Safety Analysis.Cas Have Been Updated.Attachment a Provides Commitments Associated W/ Correspondence | | | 05000295/LER-1997-016, Forwards LER 97-016-00 Re Failure to Recognize That 125 Vdc Buses Were Inoperable During Inter Unit cross-tie.Event Investigation Is Ongoing & Corrective Actions Will Be Provided in Supplemental LER | Forwards LER 97-016-00 Re Failure to Recognize That 125 Vdc Buses Were Inoperable During Inter Unit cross-tie.Event Investigation Is Ongoing & Corrective Actions Will Be Provided in Supplemental LER | | | 05000295/LER-1997-016-02, :on 970905,failed to Recognize That 125 Vdc Buses Were Inoperable During Inter Unit cross-tie.Cause Indeterminate.Corrective Actions Will Provided in Supplemental Response to LER |
- on 970905,failed to Recognize That 125 Vdc Buses Were Inoperable During Inter Unit cross-tie.Cause Indeterminate.Corrective Actions Will Provided in Supplemental Response to LER
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-017-02, :on 970806,TS Surveillance on Containment Isolation Valve Operability Was Missed After Maint.Cause Undetermined.Revised & Performed PT-306 for Affected Valves Prior to Units 1 & 2 Reaching Mode 4 |
- on 970806,TS Surveillance on Containment Isolation Valve Operability Was Missed After Maint.Cause Undetermined.Revised & Performed PT-306 for Affected Valves Prior to Units 1 & 2 Reaching Mode 4
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000295/LER-1997-017, Forwards LER 97-017-00,informing That TS Surveillance Containment Isolation Valve Operability Was Missed After Maint.Commitments Made within Ltr,Encl | Forwards LER 97-017-00,informing That TS Surveillance Containment Isolation Valve Operability Was Missed After Maint.Commitments Made within Ltr,Encl | | | 05000295/LER-1997-017-01, :on 970806,TS Surveillance on Containment Isolation Valve Operability After Maint Was Missed.Caused by Personnel Error.Procedure Writer Who Failed to Identify Remaining Procedures by 1993 UFSAR Rev Has Been Counseled |
- on 970806,TS Surveillance on Containment Isolation Valve Operability After Maint Was Missed.Caused by Personnel Error.Procedure Writer Who Failed to Identify Remaining Procedures by 1993 UFSAR Rev Has Been Counseled
| |
|