Discusses 851016 Proposed Change to Commitment to Perform Complete Survey,Including Photography of Main Breakwater Following Major Storm.Annual Survey to Detect Settlement or Horizontal Displacement Suggested
ML20140E481
Person / Time
Site: Pilgrim
Issue date: 03/25/1986
From: Zwolinski J
Office of Nuclear Reactor Regulation
To: Harrington W
BOSTON EDISON CO.
References
TAC-60317, NUDOCS 8603270590
Download: ML20140E481 (2)


Text

. .

March 25, 1986 Docket No. 50-293 DISTRIBUTION Docket RGrimes NRC PDR JPartlow Mr. William D. Harrington Local PDR Pleech Senior Vice President, Nuclear PD#1 RDG CJamerson Roston Edison Company RRernero JZwolinski 800 Boylston Street 0 ELD ACRS (10)

Roston, Massachusetts 0?199 EJordan BDLiaw RWescott DVassallo

Dear Mr. Harrington:

RDions (w/ TAC) Pilgrim File

SUBJECT:

MAIN BREAKWATER SURVEY (TAC 60317)-

Re: Pilgrim Nuclear Power Station By letter dated October 16, 1985, you proposed a chance in Boston Edison's commitment to perform a complete survey, including photoaraphy, of the main breakwater at. Pilgrim Nuclear Power Station followina a ma.ior storm. Such a storm is defined in Attachment A to Boston Edison's letter dated March 30, 1981, as "when onshore winds are in excess of 50 mph for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> as measured at the site."

The proposed change would replace the complete survey following a major storm with a walkdown and comparison of field conditions to the most recent photographs of the breakwater. If the walkdown/ohoto comparison indicates .the need for a more complete survey, it would be conducted.

This change would not affect Boston Edison's commitsnent to perform its annual breakwater survey, which includes taking photographs from established benchmarks on the shoreline. It is our understanding that the annual survey also includes the use of survey instruments to detect settlement or horizontal displacement and we recommend that this practice be continued.

We believe that any future storm damage which could impair the break-water's safety function would involve significant displacement of the cap stones and would be readily noticeable. Therefore, we agree that a complete survey of the breakwater need not be performed after winds meeting the 50 raph for 2-hour criterion unless damage is noted during the walkdown/choto comparison.

With respect to the reporting requirements, please modify them to require that- the NRC project manager or myself be notified by telephone of the results soon after a walkdown/ photo comparison is conducted.

These results and your plans for any necessary repairs should also be described in a letter addressed to me, with a copy to NRC, Region I.

Sincerely, 8603270590 B60325 ORICIWn UG" "'

O p John A. Zwolinski, Director RWR Pro.iect Diractorate #1 Division of RWT Licensing cc: See next page l DBL:PD#

L DBL:PD#12[

CJamerso@h DBL:PD#

Pleech:jg JZwolinski i

3/h86 3/k/86 3 /24/86

Mr. William D. Harrington Bcston Edison Company Pilgrim Nuclear Power Station cc:

Mr. Charles J. Mathis, Station Mgr.

Boston Edison Company RFD #1, Rocky Hill Road Plymouth, Massachusetts 02360 Resident Inspector's Office U. S. Nuclear Regulatory Commission

  • Post Office Box 867 Plymouth, Massachusetts 02360 Mr. David F.~Tarantino Chairman, . Board of Selectman 11 Lincoln Street Plymouth, Massachusetts 02360 Office of the Commissioner Massachusetts Department of Environmental-Quality Engineering One Winter Street Boston, Massachusetts 02108 Office of the Attorney General 1 Ashburton Place 19th Floor Boston, Massachusetts .02108 Mr. Robert M. Hallisey, Director Radiation Control Program Massachusetts Department of Public Health 150 Tremont Street Boston, Massachusetts 02111 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 Mr. A. Victor Morisi Boston Edison Company 25 Braintree Hill Park Rockdale Street Braintree, Massachusetts 02184