MONTHYEARML19322C6651979-02-0202 February 1979 Discusses Revised Procedure for Ofc of Executive Legal Director Involvement in Processing OL Amend Applications. Review of Safety Evaluations & Eias Re Proposed OL Amends Will Be Discontinued as of 790215 Project stage: Approval ML19322C6631979-02-0202 February 1979 Forwards Memo Announcing Radical Change in Ofc of Executive Legal Director Activities Re OL Amend Applications Project stage: Other ML20140D1911986-01-22022 January 1986 Proposed Tech Specs,Clarifying Station Review Board Duties & Responsibilities Project stage: Other ML20140D1741986-01-22022 January 1986 Application for Amend to License NPF-3,changing Tech Specs to Clarify Station Review Board Duties & Responsibilities Project stage: Request ML20140D1451986-01-22022 January 1986 Forwards Application for Amend to License NPF-3,changing Tech Specs Clarifying Station Review Board Duties & Responsibilities.Separate Amend Application Being Prepared to Address Addl Administrative Changes.Fee Paid Project stage: Request ML20215K3801987-05-0404 May 1987 Requests Reissuance of Table 3.6-2, Containment Isolation Valves of Tech Spec 3/4.6.3,correcting Typos in 840911 Application to Amend License NPF-3 Project stage: Request ML20237K8441987-08-28028 August 1987 Requests That Revised Tech Spec 6.5.1.6,submitted w/870122 License Amend Request,Reflects Station Review Board Responsibility to Review safety-related Aspects of Proposed Procedures,Mods,Tests & Experiments,Per NUREG-0103,Rev 4 Project stage: Other ML20150B9711987-09-11011 September 1987 Discusses Plant Organizational Changes.Meeting W/E Butcher & Bryan Should Be Set Up Project stage: Meeting ML20237A6881987-12-0808 December 1987 Informs of Changes Necessary to Support Fifth Refueling Outage in Feb 1988.Key Amend Requests Placed Into 1 of 3 Listed Categories.Nrc Should Allocate Necessary Resources to Provide Timely Support for Review & Issuance of Amends Project stage: Other ML20238E5701987-12-28028 December 1987 Provides Clarification to 860122 Application for Amend to License NPF-3 Re Station Review Board Responsibilities,Per 871127 & 1202 Telcons W/Aw Deagazio & Staff,Respectively, Revising Tech Specs 6.5.1.6(b) & 6.5.3.1(a),(b),(d) & (E) Project stage: Supplement ML20149J0571988-02-17017 February 1988 Provides Addl Clarification of License Amend Request Submitted on 860122 Involving Proposed Tech Spec 6.5.3.1(c). Clarified Administrative Control Will Require Technical Reviews on Each Mod Affecting Nuclear Safety Project stage: Other ML20150C4511988-03-0909 March 1988 Amend 109 to License NPF-3,revising Responsibilities & Authority of Station Review Board & Adding Section to Technical Review & Control Project stage: Other ML20150C4621988-03-0909 March 1988 Safety Evaluation Supporting Amend 109 to License NPF-3 Project stage: Approval ML20150C4731988-03-0909 March 1988 Notice of Denial of Amend to License NPF-3 Re Deleting Requirement in Tech Spec 6.5.1.6.e Concerning Station Review Board Responsibility to Investigate & Rept Tech Spec Violations Project stage: Other ML20150B9671988-03-11011 March 1988 Requests That Encl 870911 Memo from J Scinto Be Included in Docket Files.Memo Relates to 870122 Application for Amend to License NPF-3 Re Organization Changes Project stage: Other 1987-05-04
[Table View] |
Text
i TOLEDO Docket No. 50-346 JOE VVILUAMS JR.
License No. NPF-3 Sermar Vce Presdeot-Nudes' M19} 249 2300 Serial No. 1235 M'91249 5223 January 22, 1986 Mr. John F. Stolz, Director PWR Project Directorate No. 6 Division of PWR Licensing - B United States Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Stolz:
Under separate cover, we are transmitting three (3) original and forty (40) conformed copies of an application for Amendment to Facility Operating License No. NPF-3 for the Davis-Besse Nuclear Power Station Unit No. 1.
This application requests that the Davis-Besse Nuclear Power Station Unit No. 1 Technical Specifications, Appendix A, be revised to reflect the changes attached. The proposed changes involve Sections 6.5.1.3, 6.5.1.6a-j, 6.5.1.7a-d, 6.5.3, 6.8.2 and 6.8.3.
The changes in Sections 6.5.1.6 and 6.5.1.7 are being requested to revise and clarify the Station Review Board (SRB) duties and responsibilities.
Part of these changes involve removal of the technical review aspect of SRB evaluations. This change will allow the SRB to concentrate their review on the safety-related aspect of proposed changes on matters relating to nuclear safety in cases where an unreviewed safety question does not exist. This change has been enhanced by the addition of a Technical Review and Control Section 6.5.3.
These changes, while not conforming to the Standard B&W Technical Specifications, have previously been approved by the NRC at other operating nuclear power plants.
The phrase "to serve on a temporary basis" is being removed from Section 6.5.1.3, as it is an undefined term. Changes in Sections 6.5.1.6k and j
6.5.1.7a and 6.5.1.7c on position titles are being requested to conform to administrative organizational changes already in place at Toledo Edison. These position title changes are included, where necessary.
for consistency with the position titles utilized in the SRB revision discussed above. Toledo Edison is preparing a separate amendment application for submittal to the NRC which will address the rest of the administrative organizational changes in Section 6.0.
9 8601290198 860122 gj
/p 9
PDR ADOCK 05000346
_ g P
PDR gh
'l sf THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OH!O 43652
)
1 Dock:t,No. 50-346 License No. NPF-3 i
Serial No. 1235 January 22, 1986 Page 2 Toledo Edison requests that this amendment be expeditiously issued by the NRC to support Toledo Edison's timely transition to this improved management process.
Enclosed is a check for $150.00 as required by 10 CFR 170.12(c) for a license amendment.
Very truly yours, h
ti +
JW:DBI:lah attachment ec: DB-1 NRC Resident Inspector State of Ohio i