Letter Sequence Other |
---|
|
|
MONTHYEARNG-20-0027, Post Shutdown Decommissioning Activities Report2020-04-0202 April 2020 Post Shutdown Decommissioning Activities Report Project stage: Request ML20122A1152020-04-30030 April 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Post-Shutdown Decommissioning Activities Report Project stage: Acceptance Review ML20140A3262020-06-15015 June 2020 Notification of the Availability of the Post-Shutdown Decommissioning Activities Report in the Federal Register Project stage: Other ML20288A6952020-10-16016 October 2020 Letter, Notice to Extend the Comment Period Related to the Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Other ML20288A7202020-10-16016 October 2020, 20 October 2020 DAEC Extend PSDAR Comment Period Project stage: Request ML20288A7372020-10-20020 October 2020 FRN, Notice to Reopen the Comment Period Related to the Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Other ML21006A4052021-01-0606 January 2021 NRR E-mail Capture - Final RAI - Duane Arnold - Post-Shutdown Decommissioning Activities Report Project stage: RAI NG-21-0004, Response to Request for Additional Information Related to Post Shutdown Decommissioning Activities Report2021-02-0505 February 2021 Response to Request for Additional Information Related to Post Shutdown Decommissioning Activities Report Project stage: Response to RAI ML21214A2742021-08-0404 August 2021 PSDAR Comment Extension Letter - August 2021 Project stage: Other PMNS20211170, Post-Shutdown Decommissioning Activities Report2021-09-14014 September 2021 Post-Shutdown Decommissioning Activities Report Project stage: Request Press Release-21-038, NRC to Hold Public Meeting to Receive Comments on Duane Arnold Nuclear Plant Decommissioning Activities Report2021-09-22022 September 2021 Press Release-21-038: NRC to Hold Public Meeting to Receive Comments on Duane Arnold Nuclear Plant Decommissioning Activities Report Project stage: Request ML22103A0602021-09-28028 September 2021 PSDAR Meeting Transcript - September 28, 2021 Project stage: Request ML22103A0552021-09-28028 September 2021, 13 April 2022 PSDAR Public Meeting Summary Project stage: Request ML21278A0602021-10-0606 October 2021 Slides for Duane Arnold Virtual PSDAR Meeting - October 6, 2021 Project stage: Request ML22103A0592022-04-13013 April 2022 PSDAR Meeting Summary Project stage: Meeting ML22090A1922022-05-26026 May 2022 Letter to B. Coffey, FPL from M. Doell - Duane Arnold Post Shutdown Activities Report Review Letter Project stage: Other 2021-10-06
[Table View] |
|
---|
Category:Letter
MONTHYEARL-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) NG-23-0010, Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-12-0606 December 2023 Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0009, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment NG-23-0006, Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-05-23023 May 2023 Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update ML23137A1672023-05-11011 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report NG-23-0004, 2022 Annual Radioactive Material Release Report2023-04-25025 April 2023 2022 Annual Radioactive Material Release Report NG-23-0003, 2022 Annual Exposure Report - Form 5s2023-04-21021 April 2023 2022 Annual Exposure Report - Form 5s NG-23-0002, 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report2023-03-27027 March 2023 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22339A0012022-12-22022 December 2022 Acceptance of Requested Licensing Action Amendment Request for Common Emergency Plan IR 05000331/20220032022-12-13013 December 2022 NRC Inspection Report No. 05000331/2022003 (Drss) ML22285A0072022-10-13013 October 2022 NRC Analysis of NextEra Energy Duane Arnold'S Decommissioning Funding Status Report, Docket No. 50-331 IR 05000331/20220022022-07-13013 July 2022 NRC Inspection Report Nos. 05000331/2022002(DNMS) and 07200032/2022002(DNMS) ML22090A1922022-05-26026 May 2022 Letter to B. Coffey, FPL from M. Doell - Duane Arnold Post Shutdown Activities Report Review Letter ML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell NG-22-0055, Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan2022-05-20020 May 2022 Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan ML22089A0492022-05-12012 May 2022 Sfmp Review Letter NG-22-0053, 2021 Annual Radiological Environmental Operating Report2022-05-0606 May 2022 2021 Annual Radiological Environmental Operating Report NG-22-0052, Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative2022-05-0404 May 2022 Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative IR 05000331/20224012022-04-27027 April 2022 Decommissioning Security Inspection Report 05000331/2022401 NG-22-0050, Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 02022-04-26026 April 2022 Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 0 NG-22-0049, 2021 Annual Radioactive Material Release Report2022-04-26026 April 2022 2021 Annual Radioactive Material Release Report L-2022-068, NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 22022-04-25025 April 2022 NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 2 ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval NG-22-0035, Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 02022-04-13013 April 2022 Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 0 NG-22-0047, Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2022-04-11011 April 2022 Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool NG-22-0042, Registration of Independent Spent Fuel Installation Storage Casks2022-04-0808 April 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0041, and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0031, 2021 Annual Exposure Report - Form 5s2022-03-23023 March 2022 2021 Annual Exposure Report - Form 5s NG-22-0030, Registration of Independent Spent Fuel Installation Storage Casks2022-03-23023 March 2022 Registration of Independent Spent Fuel Installation Storage Casks ML22080A1822022-03-22022 March 2022 Letter to B. Coffey from M. Doell - Duane Arnold ISFSI QAPD RAI Letter L-2022-012, Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3)2022-03-16016 March 2022 Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22059A7462022-03-10010 March 2022 ISFSI-Only Physical Security Plan License Amendment Approval NG-22-0025, Registration of Independent Spent Fuel Installation Storage Casks2022-03-0808 March 2022 Registration of Independent Spent Fuel Installation Storage Casks IR 05000331/20220012022-03-0404 March 2022 Subject: NRC Inspection Report Nos. 05000331/2022001(DNMS) and 07200032/2022001(DNMS) NG-22-0021, Registration of Independent Spent Fuel Installation Storage Casks2022-02-24024 February 2022 Registration of Independent Spent Fuel Installation Storage Casks ML22007A2722022-02-11011 February 2022 Cover Letter - NRC Duane Arnold Exemption Issuance NG-22-0014, Registration of Independent Spent Fuel Installation Storage Casks2022-02-10010 February 2022 Registration of Independent Spent Fuel Installation Storage Casks ML22028A2822022-02-0303 February 2022 Defueled Physical Security Plan License Amendment Approval ML22033A0802022-02-0202 February 2022 Supplement to License Amendment Request (TSCR-188): Proposed Change to the Physical Security Plan for the Post-Shutdown and Permanently Defueled Condition IR 05000331/20210012022-01-25025 January 2022 NRC Inspection Report Nos. 05000331/2021001(DNMS); 07200032/2021001(DNMS); and 07200032/2021002(DNMS) - Duane Arnold Energy Center ML21172A2172022-01-21021 January 2022 Issuance of License Amendment to Adopt ISFSI-Only Technical Specifications NG-22-0009, Registration of Independent Spent Fuel Installation Storage Casks2022-01-20020 January 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0001, Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61BTH Type 2 Dry Shielded Canister2022-01-0606 January 2022 Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61BTH Type 2 Dry Shielded Canister NG-21-0038, Registration of Independent Spent Fuel Installation Storage Casks2021-12-22022 December 2021 Registration of Independent Spent Fuel Installation Storage Casks NG-21-0035, Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister2021-12-10010 December 2021 Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister 2024-01-25
[Table view] |
Text
June 15, 2020 Mr. Don Moul Executive Vice President, Nuclear Division and Chief Nuclear Officer Florida Power & Light Company Mail Stop: NT3/JW 15430 Endeavor Drive Juno Beach, FL 33478
SUBJECT:
DUANE ARNOLD ENERGY CENTER - NOTIFICATION OF THE AVAILABILITY OF THE POST-SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT IN THE FEDERAL REGISTER (EPID L-2020-LLL-0005)
Dear Mr. Moul:
On April 2, 2020, NextEra Energy Duane Arnold, LLC (NEDA) submitted a letter enclosing the Post-Shutdown Decommissioning Activities Report (PSDAR) and included the Site-Specific Decommissioning Cost Estimate (DCE) for the Duane Arnold Energy Center. The PSDAR, including the DCE, have been made publicly available in the U.S. Nuclear Regulatory Commissions (NRCs) Agencywide Documents Access and Management System Accession No. ML20094F603. The purpose of this letter is to inform you that the NRC staff will publish a notice in the Federal Register informing the public of a meeting to discuss and accept comments on the PSDAR and DCE. It is the NRC staffs intention to hold the public meeting on July 28, 2020, at the Palo Community Center in Palo, Iowa.
A copy of the Federal Register notice is enclosed. If you have any questions, please contact me at 301-415-2855, or by e-mail at Scott.Wall@nrc.com.
Sincerely,
/RA/
Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
Federal Register Notice cc: Listserv
ENCLOSURE FEDERAL REGISTER NOTICE NEXTERA ENERGY DUANE ARNOLD, LLC DUANE ARNOLD ENERGY CENTER DOCKET NO. 50-331
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-331; NRC-2020-0148]
NextEra Energy Duane Arnold, LLC Duane Arnold Energy Center Post-Shutdown Decommissioning Activities Report AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of receipt; availability; public meeting and request for comment.
SUMMARY
- On April 2, 2020, the U.S. Nuclear Regulatory Commission (NRC) received the post-shutdown decommissioning activities report (PSDAR) for the Duane Arnold Energy Center (DAEC). The PSDAR, which includes the site-specific decommissioning cost estimate (DCE), provides an overview of NextEra Energy Duane Arnold, LLCs (NEDA or the licensee) planned decommissioning activities, schedule, projected costs, and environmental impacts for DAEC. The NRC will hold a public meeting to discuss the PSDARs content and receive comments.
DATES: Submit comments by [INSERT DATE 120 DAYS FROM DATE OF PUBLICATION OF THIS FEDERAL REGISTER NOTICE]. Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.
ADDRESSES: You may submit comments by any of the following methods:
Federal Rulemaking Web Site: Go to https://www.regulations.gov and search for Docket ID NRC-2020-0148. Address questions about NRC docket IDs to Jennifer Borges; telephone: 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For
technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
Mail comments to: Office of Administration, Mail Stop: TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting comments, see Obtaining Information and Submitting Comments in the SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Scott P. Wall, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001, telephone: 301-415-2855; e-mail: Scott.Wall@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments A. Obtaining Information Please refer to Docket ID NRC-2020-0148 when contacting the NRC about the availability of information for this action. You may obtain publicly-available information related to this action by any of the following methods:
Federal Rulemaking Web Site: Go to https://www.regulations.gov and search for Docket ID NRC-2020-0148.
NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number 2
for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document.
B. Submitting Comments Please include Docket ID NRC-2020-0148 in your comment submission.
The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC will post all comment submissions at https://www.regulations.gov as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information.
If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment submissions into ADAMS.
II. Discussion NEDA is the holder of Renewed Facility Operating License No. DPR-49 for DAEC. The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the NRC now or hereafter in effect. The facility consists of one boiling-water reactor located adjacent to the Cedar River approximately 2.5 miles northeast of the town of Palo in Linn County, Iowa. By letter dated January 18, 2019 (ADAMS Accession No. ML19023A196), the licensee submitted its notification of permanent cessation of power operations for DAEC. In this letter, NEDA notified the NRC of its intent to permanently cease power operations at DAEC in the fourth quarter of 2020. By letter dated March 2, 2020 (ADAMS Accession No. ML20062E489), the 3
licensee submitted a revised notification of permanent cessation of power operations for DAEC. In this letter, NEDA notified the NRC of its intent to permanently cease power operations at DAEC on October 30, 2020.
On April 2, 2020, NEDA submitted the PSDAR, including the site-specific DCE for DAEC, in accordance with § 50.82(a)(4)(i) of title 10 of the Code of Federal Regulations (ADAMS Accession No. ML20094F603). The PSDAR includes a description of the planned decommissioning activities, a proposed schedule for their accomplishment, the site-specific DCE, and a discussion that provides the basis for the NRC to conclude that the environmental impacts associated with the site-specific decommissioning activities will be bounded by appropriate, previously issued generic and plant-specific environmental impact statements.
III. Request for Comment and Public Meeting Due to the COVID-19 Public Health Emergency (PHE), the NRC has delayed holding a public meeting to obtain comments from the public on the DACE PSDAR, including the DCE. However, with recent announcements for relaxing PHE restrictions by Iowa Governor Reynolds, the NRC is tentatively planning to hold the PSDAR meeting and receive comments on Tuesday, July 28, 2020, from 6 p.m. until 9 p.m., at the Palo Community Center, 2800 Hollenbeck Rd, Palo, Iowa 52324. If PHE restrictions do not allow the meeting to be held on July 28, 2020, the NRC will notify the public by revising the date on the NRC Public Meeting Schedule on the NRCs public Web site at https://www.nrc.gov/pmns/mtg. The NRC requests that comments provided outside the July 28, 2020 meeting be submitted as noted in Section I, Obtaining Information and Submitting Comments, of this document in writing by [INSERT DATE 120 DAYS FROM DATE OF PUBLICATION OF THIS FEDERAL REGISTER NOTICE].
4
Dated: June 15, 2020.
For the Nuclear Regulatory Commission.
/RA/
Nancy L. Salgado, Chief, Plant Licensing Branch III, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
5
ML20140A341 (Package)
ML20140A326 (Letter)
ML20140A345 (FRN) *via e-mail OFFICE NRR/DORL/LPL3/PM* NRR/DORL/LPL3/LA* NMSS/DUWP/RDB/BC*
NAME SWall SRohrer BWatson DATE 05/27/2020 05/26/2020 06/09/2020 OFFICE NRR/DORL/LPL3/BC* NRR/DORL/LPL3/PM*
NAME NSalgado SWall DATE 06/15/2020 06/15/2020