Forwards Final Exercise Rept for 940209,plume Exposure Pathway Exercise of Offsite Radiological Emergency Response Plans
ML20138E595
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 03/10/1995
From: Hepler O
Federal Emergency Management Agency
To: Spessard R
NRC (Affiliation Not Assigned)
Shared Package
ML20136C539 List: ... further results
References
FOIA-96-485 NUDOCS 9503220292
Download: ML20138E595 (1)


Text

-

- 2 i

Federal Emergency Management Agency

%fashingon, D.C. 20472 NMR 10 EE6 l

Mr. R. Lee Spessard, Director j

Division of Technical Support i

Office of Nuclear Reactor Regulation j

U. S. Nuclear Regulatory Commission 2.

Washington, D. C.

20555

Dear Mr. Spessard:

i Enclosed is a copy of the final exercise report for the

}

February 9, 1994, plume exposure pathway exercise of the offsite t

radiological emergency response plans site-specific to the St.

l Lucie Nuclear Power Plant.

The state of Florida partially participated and St. Lucie and Martin Counties' fully participated in the exercise.

This report was prepared by the Faderal.

Emergency Management Agency (FEMA) Region IV staff.

A copy of l3 the final report will be provided to the State of Florida by the j j FEMA Region IV staff.

j There were no Deficiencies identified during this exercise.

There were, however, three Areas Requiring Corrective Action i

identified.

FEMA Region IV staff will monitor the status of the I

corrective actions.

i Based on the results of the February 9, 1994, exercise, the 3

offsite radiological emergency response plans and preparedness l

for the State of Florida and the affected local jurisdictions,.

1 site-specific to the St. Lucie Nuclear Power Plant, can be i

implemented and are adequate to provide reasonable assurance that appropriate measures can be taken offsite to protect the health and safety of the public in the event of a radiological emergency j

at the site.

Therefore, the Title 44 CFR, Part 350, approval of 1

the offsite radiological emergency response plans and preparedness for the State of Florida site-specific to the St.

i~

Lucie Nuclear Power Plant, granted on February 15, 1984, will remain in effect.

Should you have any questions, please contact Dr. Anne Marie T.

SuPrise,-Chief, State and Local Regulatory Evaluation and Assess-

)

ment Branch, at (202) 646-4065.

j Sincerely, b

/

[
0. Megs Hapler, III

)

Director i

Exercises Division j'

Preparedness, Training, and Exercises Directorate 4

@6C.322o7A D'J)

Attachment 4

.