OPERATING DATA REPORT DOCKET NO.

50-369 DATE 10/1s/Rs COMPLETED BY

.T 1 havis

- TELEPilONE 704-373-7567 OPERATING STATUS Notes

  • Nameplate Rating
1. Unit Name:

McGuire 1 l

2. Reporting Period: Sentambar 1. 14Rs-soncomhor tn_ 1985 (Gr ss We) calculated as 1450.000 MVA x.90 power
3. Licensed Thermal Power (MWt):

34II factor per Page lii, 1305

4. Nameplate Rating (Gross MWe):

NUREG-0020.

1180

5. Design Electrical Rating (Net MWe):
6. Maximum Dependable Capacity (Gross MWe):

11R0

7. Maximum Dependable Capacity (Net MWe):
6. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Gise Reasons:

None None i

9. Power Level To Which Restricted.lf Any (Net MWe):
10. Reasons For Restrictions,If Any:

This Month Yr.-to.Date Cumulative 720.0 6 551.0 33 599.0 i1. Hours in Reporting Period

12. Number Of Hours Reactor Was Critical 720.0 4 878.5 23 042.1

'~

13. Reactor Reserve Shutdown Hours

~~-

14. Hours Generator On Line 720.0 4 793.2 22 755.8 l
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Generated (MWH) 2 '!94 794-14 062 508 60 866 Rng
17. Gross Electrical Energy Generated (MWH) 803 522 4 813 645 21 042 870
18. Net Electrical Energy Generated (MWH) 773 000

_4 sgo 722 1g 974 977

19. Unit Service Factor 100.0 71.2 67.7
20. Unit Availability Factor 100.0 73.2 67.7
21. Unit Capacity Factor (Using MDC Net) 91.0 59.5 50.4
22. Unit Capacity Factor (Using DER Net) 91.0 59.5 50.4
23. Unit Forced Outage Rate 0.0 8.I 14.6

[

24. Shutdowns Scheduled Oser Next 6 Months (Type.Date.and Duration of Eschi:

wn,

25. If Shut Down At End Of Report Period. Estimated Date of Startup:
26. Units in Test Status (Prior to Comrnercial Operation):

Forecast Achiesed INITIAL CRITICAll1Y s

INITIAL ELECTRICITY CONIMERCIAL OPER ATION 8510210295 850930 i

m PDR ADOCK 05000369 P/77)

4grg, a

raa

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-369 UNIT McGuire 1 OATE 10/15/85 COMPLETED BY J.A. Reavis TELEPHONE 704-373-7567 MONTH sentomber. 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net)

.1 1 126 17 1 142 2

i 139 18 801 3

1 140 19 1 004 4

1 140 20 1 137 5

1 140 21 1 132 6

1 068 22 1 138 7

185 23 1 142 8

690 24 1 148 9

1 133 25 1 147 10 1 132 26 1 145 11 1 129 27 1 146 12 1 129 28 1 144 13 1 133 29 1 144 14 1 133 30 1 148 15 1 136 31 16 1 116 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET N0. 50-369 UNIT NAME McGuire 1 DATE 10/15/85 REPORT MONTH September 1985 COMPLETED BY J. A. Reavis T._EL_EPHONE_ _ _ _704_373-7567 5

U License Cause & Corrective u

E-EZ 5

m m

UU E

EU" Event Er En Action to No.

Date 25 E

5$5 O@O aN S3 E

E5S Report #

NO Prevent Recurrence l 29-p 85-09-01 S

B CC VALVEX Turbine Control & Stop Valve Movement i

PT's 30-p 85-09-06 F

A CB INSTRU

, Repair Reactor Coolant Pump Oil Level l

f Switch l 31-p 85-09-07 F

F XX XXXXXX Hold for Secondary Chemistry I

i

! 32-p 85-09-18 F

A HB VALVEX Moisture Separator Reheater Relief j

Valve Lifted due to faulty solenoid.

33-p 85-09-18 F

B IB INSTRU Adjust Nuclear Instrumentation 34-p 85-09-19 F

B IB INSTRU Adjust Nuclear Instrumentation 35-p 85-09-19 F

B IB INSTRU Nuclear Instrumentation Calibration 8

i i

l

-.-_.ai 1

1 2

3 4

Reason:

Method:

Exhibit G - Instructions F

rc S

7g A-Equiprnt Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)

D-Regulatory Restriction 4-Other (Explain)

File (htREG-0161)

E-Operator Training 5 License Examination F-Achinistrative 5

G-Operational Error (Explain)

Exhibit I - Same Source H-Other (Explain)

'9/77)

\\

DOCKET NO 50-369 UNIT: MCGUIRE 1 DATE: 10/15/85 NARRATIVE

SUMMARY

MONTH: September 1985 McGuire Unit 1 began September at 100% power, but reduced to 10% on 9/06 and 9/07 to repair a faulty oil level switch on a Reactor Coolant pump.

The unit returned to 100% and operated at that level until 9/18. A Moisture Separator Reheater relief valve lifted and would not reset.

The unit dropped to 20% before the valve could be closed and then returned to 100% and operated at that level for the balance of September.

l l

l l

i

MONTHLY REFUELING INFORMATION REQUEST 1.

Facility name:

McGuire Unit 1 2.

Scheduled next refueling shutdown:

June. 1986 i

3.

Scheduled restart following refueling:

Sep temb er. 1986 4.

Will refueling or resumption of operation thereafter require a technical l

specification change or other license amendment?

Yes If yes, what will these be? Technical Specification Revision i

l i

4 If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions? N/A 5.

Scheduled date(s) for submitting proposed licensing action and supporting information:

N/A 6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analyrt, methods, significant changes in design or new operating procedures).

f 7.

Number of fuel assemblies (a) in the core 193 (b) in the spent fuci pools 152 i

8.

Present licensed fuel pool capacity:

1463 Size cf requested or planned increases 9.

Projected'date of last refueling which can be accommodated by present licensed capacity: Aucust. 2010 DUKE POWER COMPANY Dates igfaber 15. 1985 Name of

Contact:

J. A. Reavis Phones,704-373-7567 l

l l

- ~

~

OPERATING DATA REPORT DOCKET NO.

50-370 DATE 10/15/85 i

COMPLETED BY J.A. Reavis TELEP110NE

'7nd-373-7567 i

OPERATING STATUS Notes

  • Nameplate Rating
l. Unit Name:

Mm uire 2 (Gross MWo) calculated as

2. Reporting Period: September 1,1985-September 30,198:

~

3. Licensed Thermal Power IMWt):

3411 1450.000 MVA x.90 power factor por Page 111,

4. Nameplate Rating (Gross MWe):

1305*

NUREG-0020.

1180

5. Design Electrical Rating (Net MWe):
6. Maximum Deper.dable Capacity (Gross MWe):

1180

7. Masimum Dependable Capacity (Net MWe):

l

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.Giie Reasons-None Nono
9. Power Level To hhich Restricted. If Any (Net MWe):
10. Reasons For Restrictions.lf Any:

i i

This Month Yr..to Date Cumulative II. Hours in Reporting Period 720.0 6 551.0 13 895.0 l

12. Number Of Hours Reactor Was Critical 720.0 1 648.8 9 787.0 l
13. Reactor Resene Shutdown liours

~~-

L

14. Hours Generator on Line 720.0 3 350.1 9 441.2
15. Unit Resene Shutdown Hours
16. Gross Thermal Energy Generated (MWH) 2 ast 943 10 742 738 30 113 409 l
17. Gross Electrical Energy Cenerated (MWH) 854 117 1 736 817 10 574 540 I
18. Net Electrical Energy Generated (MWH) 823 869 3 554 302

_10 112 102 l

19. Unit Senice Factor 100.0 51.1 68.0 l
20. Unit Asailabi!:ty Factor 100.0 51.1 68.0

(

j

21. Unit Capacity Factor (Using MDC Net) 97.0 46,0 61.7 l

t

22. Unit Capacity Factor (Using DER Net) 97.0 46.0 61.7

{

23. Unit Forced Outage Rate 0.0 33.5 23.2
24. Shutdowns Scheduled Over Nest 6 Months (Type. Date.and Duration of Eacht:

i Nonc i

25. If Shut Down At EnJ Of Report Period. Estimated Date of Startup:

i

26. Units in Test Status (Prior to Commercial 0peration):

Forecast Achleted

(

INITl \\ L CRITICA LITY INITIAL ELECTRICIfY i

C0\\lMERCIAL OPER A Il0N t

i j

(9/77)

I

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-370 UNIT McGuire 2 DATE 10/15/85 COMPLETED BY J.A.

Reavis TELEPHONE 704-373-7567 HONTH September, 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Ne t) 1 1 145 17 1 150 2

1 146 18 1 149 3

1 146 19 1 148 4

1 146 20 1 149 5

1 146 21 1 145 6

1 146 22 1 145 7

1 142 23 1 149 8

1 140 24 1 152 9

1 140 25 1 1 51 10 iiw 26 i i si i

11 1 139 27 1 149 12 1 137 28 1 120 13 1 136 29 1 148 14 1 137 30 1 152 15 1 140 3;

16 1 145 INSTRUCTIONS On this format, list the average daily unit power level in HWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

l UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-370 UNIT NAME McGuire 2 DATE 10/15/85 REPORT MONTH September 1985 COMPLETED BY J. A. Reavis

. TELEPHONE 70_4_-373-7567 o

gj License Cause & Corrective y

c32 "a

v5E No.

Date

~.

%h 3

,g g Event h

h Action to S

5E E

%.E k Q

8 '8 F

o-o:

xmo Report #

mu av Prevent Recurrence 26-p 85-09-28 F

A SH XXXXXX Hydrogen Mitigation System Inoperable i

I t

I i

i__.__

i a

1 2

3 4

Reason:

Method:

Exhibit G - Instructions

[

A-Equipment Failure (Explain) 1-Manual for Preparation of Data C

e 7g B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)

D-Regulatory Restriction 4-Other (Explain)

File (NUREG-0161)

E-Operator Training 6 License Examination F-Administrative 5

G-Operational Error (Explain)

Exhibit I - Same Source H-Other (Explain) 9/77)

DOCKET NO. 50-370 UNIT: MCGUIRE 2 DATE: 10/15/85 i

i l

NARRATIVE

SUMMARY

MONTH: September 1985 McGuire Unit 2 operated at 100% during the entire month of September, except for a reduction to approximately 81% on 9/28 to investigate a Hydrogen Mitigation System problem.

l l

I l

I t

i

=...

MONTIILY REFUELING INFORMATION REQUEST 1.

Facility name: Mccufre Unit 2 2.

Scheduled next refueling shutdown: April. 1986 3.

Scheduled restart following refueling:

June. 1986 4.

Will refueling or resumption of operation thereafter require a technical specification change or other li cnse amendment?

yen If yes, what will these be? Technical Specification Revision If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

N/A 5.

Scheduled date(s) for submitting proponed licensing action and supporting information:

N/A 6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, aignificant changco in design or new operating procedures).

7.

Number of fuel assemblies (a) in the core 193 (b) in the spent fuel pool 65 8.

Present licensed fuel pool capacity:

1463 Size of requested or planned increase 9.

Projected date of last refueling which can be accommodated by present licensed capacity: Aucust. 2010 DUKE POWER COMPANY Datel _0ctober 15. 1985 Name of

Contact:

J. A. Reavis Phones 704-373-7567

1 McGUIRE NUCLEAR STATION r

Hocthly Operating Status Report 1

1.

Personnel Exposure j

For the month of August, no individual (s) exceeded 10 percent of their l

allowable annual radiation dose limit.

2.

The total station liquid release for August has been compared with the Technical Specificationa maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for August has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

i I

I 1

l I

l l

l l

1

4 Duxi: l'owtut G(DWANY l'.O. lH)4 !!!llflD CllAlit.OTTE. N.O. MilM SM HAL II. Tt*CKrH vst r e,somm (704) t:7:s-4n:le October 15, 1985

..u...-4, i

Director i

Office of Inspection and Enforcement l

U. S. Nuclear Regulatory Commission Washington. D. C.

20555 Attention: Docuwnt Control Desk Ret McGuire Nuclear Station Docket Nos. 50-369 and 50-370 Dear Sir Please find attached inforestion concerning the performance and operating l

status of the McGuire Nuclear Station for the month of September,1985.

I Very truly yours.

L s llal B. Tucker

.iARisib Attachment cc Dr. J. Nelson Croce, Regional Adminintrator American Nuclear Insurorn U. S. Nuclear Regulatory Commission c/o Dottle Sherman, ANI Library l

Region II 1ho F.xchango, Suite 245 101 Marietta Street NW, Suite 2900 270 Farmington Avenue l

Atlanta, Georgia 30323 Farmington, Connecticut 06032 l

Mr. Phil Ross INPO Records Center i

U. S. Nuclear Regulatory Commission Sutic 1500 tciBB-5715 1100 Circio 75 Parkway Washington, D. C.

20555 Atlanta, Coorgia 30339 1

l Mr. Darl llood Ma. Judy Dovers Office of Nuclear Renctor Regulation Nuclear Assuranco Corporation l

U. S. Nuclear Regulatory Commission 5720 Peachtroo Parkway l

Washington, D. C.

20555 Norcronn, Coorgia 30092 l

Mr. W. T. Orders NRC Senior Resident Inspector McGuiro Nuclear Station 1

eli