ML20137K885

From kanterella
Jump to navigation Jump to search
Insp Repts 50-454/96-13 & 50-455/96-13 on 961216-970310. Violation Noted.Major Areas Inspected:Plant Support
ML20137K885
Person / Time
Site: Byron  Constellation icon.png
Issue date: 03/31/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20137J710 List:
References
50-454-96-13, 50-455-96-13, NUDOCS 9704070118
Download: ML20137K885 (7)


See also: IR 05000454/1996013

Text

7

.

,

' U. S. NUCLEAR REGULATORY COMMISSION

REGION lil

Docket Nos.:

50-454; 50-455

License Nos.:

NPF-37; NPF-66

. Report No.:

50-454/96013(DRS); 50-455/96013(DRS)

Licensee:

Commonwealth Edison Company

Facility;

Byron Nuclear Generating Station, Units 1 & 2

!

Location:

4448 North German Church Road

i

Byron, Illinois 61010-9750

1

Dates:

December 16-17,23, January 9,29 30,

February 4-5,20 and March 10,1997

4

Inspectors:

J. H. Neisler, Reacter inspector

D. Schrum, Reactor inspector (January 29-30, 1997)

,

Approved by:

R. N. Gardner, Chief

Engineering Specialists Branch 2

Division of Reactor Safety

)

i

9704070118 970331

'

PDR

ADOCK 05000454

0

PDR

,

!

I

i

~

. - .

i_.

.1.,

. - , _

. . . - - _ , , ,

. _ . _

L_....

. . ? .. _ , . , , _ . .

.,

. . .

.

~

._

. _ . _

.

_

._

. _ _.

_ . _ __.

-

.

_ _ _ . . _ _ .

.

!

.

?,

l

1

!

'

Report Details

t

IV. Plant Suncort

,

F1

Control of Fire Protection Activities

F1.1

General Comments

!

Using inspection Procedure 40500, the inspector evaluated the effectiveness of the

iicensee's controls in identifying and correcting deficiencies in the plant's fire

-

protection system. The evaluation included over 260 Problem Identification Forms

{

(PlFs) associated with the Byron fire prctection system that had been initiated

,

during 1995 and the first 11 months of 1996. The number of PlFs issued during

,

this period was an indication of the plant staff's diligence in identifying deficiencies.

l

The inspectors considered this a strength. However, the inspectors noted several

'

instances where inadequate or lack of corrective actions resulted in repetitive PlFs

on the same type of issues.

F1.2 Confiauration Control

a.

Insoection Scooe (40500)

The inspectors reviewed PIFs relative to configuration control deficiencies that had

been documented during the past 22 months, in addition, the inspector

interviewed cognizant licensoo personnel.

b.

Observations and Findinas

During the review of fire protection PIFs, the inspectors noted that two PlFs had

identified mispositioned valves in the fire protection system.

j

PlF 454-201-96-1973, November 23,1996: During performance of the monthly

fire protection valve line up, two valves, OFP248 and OFP033, were identified as

.

j

not being in their required position. The valves had been closed in support of

1

another surveillance that had been suspended for lack of manpower. The valves

had not been restored to their proper position when the original surveillance was

suspended. It was not known how long the valves had been in the incorrect

configuration.

PlF 454-201-96-1990. November 26,1Jjl: An operator found two fire protection

valvos that were not in their required position. It was subsequently determined that

the valves were part of a semi-annual surveillance that was suspended with the

valves lef t in the as-left surveillance position.

The inspectors' reviews of fire protection system drawings and discussions with

j

the Byron Fire Marshal determined that no portion of the fire protection system was

inoperable as a result of mispositioned valves. The mispositioned valves and loss of

configuration appeared to be the result of the licensee's practice of suspending an

in-process surveillance procedure due to other priorities or lack of manpower while

j

leaving the system in the as-left surveillance configuration, then beginning another

,

a

1

-

r

.

.

f

surveillance before completing the original. The persons performing the second

surveillance then originated a PlF identifying the loss of system configuration.

Licensee persnnnel stated that this practice did not occur during safety-related

surveillances.

c.

Conclusions

The inspectors concluded that none of the above examples resulted in loss of

system operability. However, the licensee's established practice of allowing fire

protection valves to remain in the as-left surveillance position for indefinite periods

indicated a weakness in management's control of fire protection surveillances.

F1.3 Reactor Coolant Pumo (RCP) Oil Collection System

a.

Inspection Scone

The inspectors reviewed PlFs, operability assessments, fire analysis report, system

drawings, and interviewed licensee person' riel relative to the Byron Reactor Coolant

Pump Oil Collection System,

b.

Observations and Findinas

PiF 454 200-96-0032, dated June 24,1996, identified that all potential oil leaks on

the reactor coolant pumps did not have drip pans to collect and route the oil to a

(

safe collection point as required by 10 CFR 50, Appendix R.

The inspectors reviewed Byron Operability Assessment 96-025, dated June 25,

1996, and Byron RCP Oil Collection System Fire Protection Evaluation, dated

June 24,1996. The licensee's evaluation states, " Contrary to Byron's Fire

Protection, Sections 3.7.G and AS.7.lli.0, all potential oil leakage points are not

provided with pans to collect drips and seepage. Specifically, there are two bolted

flanges and two drain plugs associated with the oil cooler on each RCP that were

not initially provided with drip pans." The licensee's evaluation also states,

" Appendix R to Part 50 of Title 10 of the Code of Federal Regulations requires the

installation of an oil collection system to collect oil front all potential pressurized

and unpressurized leakage sites." However, the licensee determined it was

acceptable to operate with this condition.

10 CFR 50, Appendix R, Section lil, O, requires that RCP lube oil collecting systems

shall be capable of collecting luba oil from all potential pressurized and

unpressurized leakage sites in the RCP lube oil systems.

NUREG-0876, Safety Evaluation Report, Supplerr at No. 5, pages 9-17, closed an

NRC unresolved issue identified in the Safety Evaluation Report regarding the

provision of an oil collection system for the RCPs. This was based on the

licensee's commitments in the fire protection report and letter dated August 20,

1984, to install an oil collection system capable of collecting oil from all potential

pressurized and unpressurized leakage sites.

2

-

r

.

,

The Byron Fire Protection Report, pages 3.7-3 and A5.7-35,36, stated that the

RCP lube oilleakage collection system complied with NRC and Appendix R

requirements. PlF 454 200-96-0032 identified that the licensee was not in full

compliance.

<

As corrective action to PlF 454-200-96-0032, the licensee installed additional drip

pans under the bolted flanges and drain plugs and lengthened one drain pan. Work

had been completed on both units.

.c.

Conclusions

The licensee identified this issue and took appropriate corrective action. An

Operability Assessment was completed on July 25,1996, that documented

continued operability of both units. However, the licensee was not in compliance

with 10 CFR 50, Appendix R, Section O requirements since plant construction in

addition, the licensee failed to notify the NRC, pursuant to 10 CFR 50.73, that this

condition was outside the Byron design basis. The licensee stated that the RCP oil

collection system was not outside the Byron design basis and therefore was not

i

reportable. This issue is unresolved (50-454/455/96013-01(DRS)) pending review

of the licensce's requested response to this issue.

'

F1.4 OC HoM Points

a.

Insoection Scope

The inspectors reviewed PlFs relating to work performed on the fire protection

system to ascertain whether quality controls were effective,

b.

Observations and Findinas

The inspectors reviewed six PlFs detailing missed quality control (OC) hold points.

Hold points are steps within a work procedure or work order past which the activity

cannot proceed until that step has been performed. The missed hold points were

mostly OC cleanliness inspections on components prior to maintenance closing the

component after work had been completed. The licensee's corrective action and

closure of each of the missed hold points appeared to be appropriate.

The licensee had developed a program to reduce or eliminate missed OC hold points

'

during maintenance activities. The program tracks missed hold points and initiates

]

appropriate corrective action,

o

c.

Conclusions

j

,

4

The inspectors concluded that the licensee had appropriately addressed the missed

QC hold points and that the program to eliminate or reduce the missed hold points

'

reviewed during this inspection should be effective.

,

l

3

s

.

. -

-

.

.

e.

.

.

.

F1.5 Recetitive Deficiencies identified by PIF

a.

Insoection Scoce

The inspectors reviewed PIFs that were repetitive in that they identified the same

type of deficiencies. The inspectors discussed these repetitive PlFs with licensee

representatives.

b.

Observations and Findinas

,

The inspectors noted instances where action to correct a fire protection deficiency

identified by a PIF had not been effective in preventing the recurrence of the same

l

type deficiency. Each deficiency identified was corrected without fully establishing

the reason for the deficient condition or providing effective measures to prevent

recurrence. All the repetitive deficiencies appeared to result from personnel errors

and inattention to detail.

c.

Conclusions

The licensee identified and promptly corrected each deficiency described in the

PlFs. However, the repetitive occurrences indicate a need for improvement in the

licensee's root cause determination and corrective action processes.

j

F1.6 Freezina Pioes

l

J

1

a.

Insnection Scone

The inspectors reviewed PlFs documenting frozen fire protection pipes and

discussed freeze protection for plant components with cognizant licensee

personnel.

b.

Observations and Findinas

During the review of PlFs documenting fire protection issues, the inspectors noted

four instances in the winter of 1995/1996 when fire protection system piping had

frozen as a result of open exterior doors or louvers which cxposed the pipes to

subfreezing outside temperatures. Two of the frozen pipe occurrences were due to

mechanical prcblems with closure equipment on the exterior openings. However,

the licensee did not apply compensatory measures to prevent pipe freezing. In

response to the inspectors' queries, licensee representatives stated that there were

no procedures or directives controlling the length of time an exterior opening could

remain open during cold weather.

On January 17,1997, an equipment attendant found the north entrance door to the

circulating water pump house propped open which resulted in all the fire protection

'

instruments on panel OPL 52J freezing. In addition, this resulted in the loss of main

control board indication for the fire protection header pressure. Finally, it resulted

in fire pump OA and the jockey pump being inoperable. Corrective action, as stated

by the operations manager, was to fire the contractor worker who propped the door

4

,

.

.

..

. - - . . - ~

- - - -

. .

- - . - . . . - - - .

.- .

..-

,

i

,

i

<

10 CFR 50, Appendix B, Criterion XVI, requires that in the case of significant

,

conditions adverse to quality, measures shall be estab!ished to assure the cause of

1-

the conditions is determined and corrective action taken to preclude repetition.

c.

Conclusions

Licensee management was not effective in preventing repetitive freezing and loss of

equipment during cold weather. Failure to provide effective corrective action

'

'

continued to result in frozen, inoperable fire protection cquipment. This is a

i

4

violation of 10 CFR Part 50, Appendix B, Criterion XVI (50-454/455/96013-

02(DRS)).

-

'

V. Manaaement Meetinas

l

XI Exit Meeting Summary

The inspectors met with licensee representatives on January 9,30, February 20 and by

telephone March 10,1997, to discuss the scope and findings of the inspe'ction. During

'

I

the exit meetings, the inspectors discussed the documents and processes reviewed by the

inspectors during the conduct of this inspection and the likely informational content of the -

,

1

inspection report. The licensee representatives did not identify any such documents on

process as proprietary.

1

!

!-

t

,

4

-

!. -

1

5

,

'

.

. _ , .

.

-

. . .

_ _

.f

.

e,

.d

'

PARTIAL LIST OF PERSONS CONTACTED

Licensee

,

R. Colglazer, NRC Coordinator, Regulatory Assurance

J. Feinster, Lead System Engineer

T. Gierich, Operations Manager

_

K. Kofron, Site Manager

,

R. Linboom, Senior Inspector, SOV

F. Pollak, Fire Protection System Engineer.

D. Popkins, Administrator, Operations Engineering

D. Robinson, Project Engineer

R. Scheidecker, Fire Marsha!

M. Snow, Work Control Superintendent .

D. Wozniak, Site Engineering Manager

US NRC

' S. Burgess, Senior Resident inspector

N. Hilton, Resident inspector

LIST OF DOCUMENTS REVIFWED

OBVS 7.10.1.1.G 1, October 31,1995, Revision 6, Unit 0, Fire Suppression Water

Systems Fire Hydrant Flow Test

BAP 1100-1, February 14,1992, Revision 9, Fire Protection Program

OBOS 7.10.1.1.e-1, July 1,1996, Revision 10, Fire Protection Testable Valve Yearly

Cycte Surveillance

BAP 300-1, January 10,1995, Revision 3, Conduct of Operations

BAP 330-2. July 31,1996, Revision 13, Temporary Alterations

BAP 3301, September 26,1996, Revision 25, Station Equipment Out-of-Service

Procedure

OBVS 7.10.1.1.a-3, November 29,1995, Revision 3, Fire Protection Pumpf, Flow and

Pressure Test

LIST OF ACRONYMS

SOV

Site Ouality Verification

FP

Fire Protection, Fire Pump

PlF

Problem identification Form

CAR

Corrective Action Request

EA.

Equipment Attendant

LCOAR

Limiting Condition for Operation Action Request

O

Components Shared Between Unit

RCP

Reactor Coolant Pump

g.

i :.

6

,