ML20137A617

From kanterella
Jump to navigation Jump to search
Advises That Operating Crews Observed During 850526-31 on-shift Special Insp Performed Duties in Prof Manner. Specific Items Noted During Startup & Low Power Physics Tests Encl
ML20137A617
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 06/18/1985
From: Boegel J
Battelle Memorial Institute, PACIFIC NORTHWEST NATION
To: Crews J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML20137A500 List:
References
NUDOCS 8508210441
Download: ML20137A617 (3)


Text

__ . ._

b,

,/

/ am ""'

OBaHelle

~

Pacific . Northwest Laboraterles

'i' P.O.Boz999

~"** Richland, hhington it$A. 99352 l

Te(cohone (500 Telex 15 2874 l

1 June 18,198!i . . _ _ _ _

i Mr. Jess crews i 1

NRC Region V 1450 Marin Lane, Sutto 210 Walnut Creek, CA 94596 l

Dear Jess:

SUBJECT:

Palo Verde Startup Special Inspection '

As a member of the oeshift special. inspection team at Palo Verde Nuclear Generattng Station (PVNGS), May 26-31,19Ei, I observed the day shift operations including pre-shift turnover briefings between on-going and off-going operating crews as well as briefings between Engineertng and Operations. In addition to the control room observations, I also made three plant tours to observe operattons outstde of the control room. i The operating crews that I observed performed their duties in a professional manner. '

They were alert, and had a very positive attitude toward their job. '

The personnel that I observed outside the control room on my plant tours were knowledgeable about their plant and procedures and were profenstonal in the perfonnance of their dutjes.

f i

During the period of observation mentioned above, 40 profenstonal staff hours i were charged to the inspection as well as 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> of casual overtime that will not be billed to the inspection.

S ely, i -

r

{ John Boegel i _. .

Senior Research Engineer

MBahk l

8508210441 850806 PDR ADOCK 05000528 ,

G PDR 1 l /

./

SPECIFIC ITEMS NOTED DURING PALO VERDE STARTUP AND LOW POWER PHYSICS TESTS MAY 27-31 1.

Low Power Phystes Tests were performed prof tetently with good communication observed between operations and engineering personnel. A ground problem was observed by shift personnel on CEA subgroup 64. Two rods legged the other rods causing a deviation alarm.

ISC was notified and began to take voltage vs the time measurements for each control rod maneuver to determine the nature of problem.

professionally.I observed these measurements, and found them to be perfonned i

2. Observed Auxtltary Feed Pump A excess flow check valve test.

did not perform satisfactorily. Check valve the problem and suggesting either repair or replacement of theProce- valve. Engini' dures were followed correctly during the test and adequate safety precautions were taken during pump run-up. Debris (gum wrappers, etc.) was observed in the 'A' ptanp sisnp and once noted, was subsequently cleaned.

3.

SIT B had a nitrogen overpressure leak throughout the entire pertod of my observation.

gressed to once perTheshift.

frequency of operator action to pressurize the tank pro-While this was an annoyance and distraction, the l operating crews perfonned this exeretse by procedure in a professional manner.

4.

D/G A was inoperable due to an excessive amount of microbes found in the fuel tank. Because of this, D/G B had to be started once per shift. After about 11 minutes had elapsed following D/G B start and loading, D/G B tripped due to excessive vibration. This placed Unit 1 into a two hour action statement i as per technical spectftcations. l shooting efforts of plant engineering on D/G B.During this period These I observed personnel carried the out trouble

, thete diagnosttes professionally and exercised the proper personnel safety precautions.

l The vibration analysts team was very responstve to the problem and the awareness that the plant was in a two hour action statement or shutdown was foremost on the minds of each team member.

l with D/G B and it was declared operable with three minutes to spare follow a startup test run at full load. During the startup for the full load test, the procedure calls for local start. This procedure step was deviated and the D/G B was Ttarted remotely. Operations explained that this was due to the new diagnostic equipment that had been installed (voltage, frequency, etc.)

and that the procedure was in the process of being changed. I did not

, see the PCN for this; change, however.

1 5.

i As per techntedl specifications, the temperature in containment was being i

recorded hourly duelto malfunctioning fire protection equipment.

t shift I observed thJt a temperature reading was not recorded on the shiftDuring one log.

- This was notef by the shift crew one hour later. The incident was pro-parly filed and will go the PRB for review.

6.

The ongoing surveillance being perfarmed on the RPS was a continuous annoyance and distraction.

The operations crews handled this professionally.

l 2_

. /

/

~.

7. In the control room, electronic equipment is available to the operations crew to give an audible alam as a reminder to make hourly log entries, keep track of elapsed time when in action statements etc. This equipment.is not being used to its fullest potential and very few of the operations crews know how to use it. The STA's seem to be the only ones trained on it.

~

l G

, pg !,

e e**

1

  • , r. _

L "y R

, i: >

3