ML20135G743
ML20135G743 | |
Person / Time | |
---|---|
Site: | Dresden |
Issue date: | 05/14/2020 |
From: | Christopher Hunter NRC/RES/DRA/PRB |
To: | |
Littlejohn J (301) 415-0428 | |
References | |
LER 1990-002-00 | |
Download: ML20135G743 (7) | |
Text
B-62 ACCIDENT SEQUENCE PRECURSOR PROGRAM EVENT ANALYSIS LER No.: 237/90-002 Event
Description:
Reactor scram followed by a loss of offsite power Date of Event: January 16, 1990 Plant: Dresden 2 Summary Dresden 2 scrammed from 100% power on January 16, 1990. Following the scram the reserve auxiliary transformer (RAT-22) tripped off causing a loss of offsite power (LOOP). Just prior to the LOOP the operator, anticipating the LOOP, had manually started emergency diesel generator (EDG) #2, which placed the EDG in a potential overload condition. The LOOP lasted until offsite power was restored 12 h and 39 min later. Additionally, it took more than 2 h to establish shutdown cooling (SDC) through loop B because of a failed isolation valve. The conditional core damage probability estimated for this event is 3.1 x 10-6. The relative significance of this event compared to other postulated events at Dresden 2 is shown below.
F
-LER 237/90-002 1E-7 1E-6 1E-5 IE-4 1E-3 IE-2 I360 hunava1ij L360 hEP HPCS +IC LLo precursor cutoff- I1)FW + HPCI Event Description Dresden 2 tripped from 100% power on January 16, 1990, following failure of the 2D condensate pump due to a probable internal fault. The two operating reactor feed pumps tripped on low suction pressure, followed by scram on low water level approximately 10 s later. Standby feed pump 2B started on trip of the two operating pumps, and pump 2A was restarted by the operator after the scram. Both operating main feed pumps and the turbine tripped on high reactor water level.
One minute later RAT-22 tripped off due to an internal fault. Loads supplied by the RAT
B-63 transferred to the unit auxiliary transformer (UAT), supplied by the main generator.
When the generator field breaker opened, a LOOP occurred since power was unavailable to both vital AC buses. The LOOP lasted until offsite power was restored 12 h 39 min later.
Just prior to the LOOP the operator, anticipating the LOOP, had manually started DG #2 to power bus 24-1. Since automatic load sequencing is not performed during manual start, the potential for DG overload existed [operating procedure requirements to place emergency core cooling system (ECCS) pumps in pull-to-lock, which minimized this likelihood, were followed]. Swing DG 2/3 auto-started and loaded bus 23- 1.
Main steam isolation valve (MSIV) 2C closed when AC power was interrupted. The cause of the valve closing was a previously failed DC solenoid. The MSIVs on Dresden use a DC- and an AC-powered solenoid, both of which must deenergize to close the valve. Momentary interruption of AC power prior to the DG's powering the vital buses, in combination with the failed DC solenoid, caused the valve to close. All other MSIVs were closed shortly thereafter to conserve reactor inventory.
Two minutes after the MSIVs were closed, indication of a fire was received from the condensate pump room. Flames were observed coming from the 2D condensate pump vents. The fire was extinguished with a dry chemical fire extinguisher.
The isolation condenser and HPCI were used for decay heat removal. When the operator opened electromatic relief valve 2-203-3B to help control reactor pressure, the "open" lamp shorted and emitted sparks and smoke. Valve 2-203-3B was closed and valve 2-203-3C was used instead.
While taking the plant to cold shutdown, SDC pump discharge valve M02-1001-4B failed to open because of a failed pinion gear in the valve motor. (The valve had been successfully operated on January 6, 1990, during cooldown following a scram on that date.)
Additional Event-Related Information Dresden 2 has two independent sources of off-site power, RAT-22 and unit auxilary transformer 21 (UAT-2 1). Normally, five separate sources of 138-ky power feed RAT-22, which, in turn, feeds 4.16-ky Buses 22 and 24. Bus 24 supplies 4.16-ky vital Bus 24-1. The emergency supply for Bus 24-1 is EDG #2. A cross-tie also exists that can provide power to bus 24-1 via the Unit 3 RAT.
The other Dresden 2 vital 4.16-ky Bus, 23-1, is supplied by Bus 23, which, along with
B-64 Bus 2 1, is supplied by the main generator via UAT-2 1. The common Unit 2 and Unit 3 EDG (EDG #2/3 or swing EDO) provides emergency backup power to Bus 23-1. With this arrangement, the auxiliary power for Unit 2 is supplied by UAT-21 and RAT-22 with the loads divided equally between them.
On a loss of auxiliary power the reactor will scram; conversely, the UAT is the on-site power source from the main generator and by design it is lost following a turbine trip. In this event, the RAT tripped about 1 min after the turbine tripped but before the generator tripped. Buses 22 and 24, which were being carried by the RAT, automatically transferred to the UAT. (Bus 22 made four attempts to close onto the UAT before it was successful.) Consequently, when the main generator tripped the UAT tripped off and caused the LOOP.
Two other occurrences at this site (LERs 237/85-034 and 249/89-001) involved a LOOP plus a scram. All three events (this LER and the previous two) involved a failed RAT.
When EDG #2 receives an automatic start signal, the feeder breaker supplying normal 4.16-ky power from Bus 24 to Bus 24-1 is opened, thus shedding the loads on Bus 24.
After the EDG is at rated speed and voltage, it is automatically loaded onto its emergency bus, Bus 24-1, and vital loads required for safe shutdown of the plant are sequenced onto the bus. If the EDG is manually started, the feeder breaker from Bus 24 to Bus 24-1 is not opened. In this case, the EDG could potentially attempt to power Buses 24 and 24-1. Additional potential loads on Bus 24 would include two service water pumps, one circulating water pump, one control rod drive pump, and two condensate pumps.
In this event (LER 237/90-002), the operator was preparing to synchronize the EDO with the bus when he noticed that the swing EDG had automatically started. He then placed the control switch back to the auto position to allow EDG #2 to auto synchronize onto the dead bus. Had the EDG been manually loaded, anticipated loads would be expected to have been less than design basis loads since an ECCS signal did not exist and Dresden operating procedures require the low-pressure ECCS pumps to be placed in pull-to-lock during manual loading to minimize the likelihood of DO overload. The operators are also trained to avoid DG overload conditions.
SDC is comprised of three 50% capacity loops, each consisting of one pump and one heat exchanger. Shutdown heat loads require that two loops be operational for 24 h, and after that only one loop is necessary to maintain the reactor cooled below 125'F.
B-65 ASP Modeling Assumptions and Approach This event was modeled as a reactor scram and plant-centered LOOP with one of three SDC loops unavailable. Manual loading of DG #2 was not assumed to impact reliability of the DG during this event.
Analysis Results The conditional probability of severe core damage estimated for this event is 3.1 X 10-6.
The dominant sequence to core damage, highlighted on the following event tree, involves a potential transient-induced LOCA due to relief valve failure to close, followed by HPCI failure and failure to depressurize using ADS.
Additional information concerning this event is provided in AlT report 50-237/90-004.
B-66 EP2 EP I~'~' ~
. II I I I IR~
END Ox OK 41 CORE DWM.AGE OK OK 42 COPE DAMAGE 43 COPE DAMAGE COREDAMAGE OK 45 CORE DAMAGE OKc 44 CORE DAMAGE 47 COPE DAMAGE 48 COPE DAMAGE OK OK 42 CORE DAMAGE OK OK 50 COPE DAMAGE O9 OK SI COR.E DAMAGE OK 52 CORE DAMAGE OK 83 CORE DAMAGE 54 CORE DMG 58 CORE DAMAGE OK 54 CORE WAMAGE OK OK 57 57 COPEDAMAGE OK 84 COP-EGAPAGE ON ON 59 COREDAMAGE ON 40 COREDAMAGE EM ON 41 CORE DAMAGE 42 COPE DAMAGE CORE DAMAGE 98 ArWS ON ON 64 COPEDAMAGE 45 COPEDAMAGE ON so COPEDAMAGE 87 COPEDAMAGE OK ON ON 44 COPEDAMAGE 45 COPEDAMAGE 44 COPEDAMAGE 97 AliAS Dominant core damage sequence for LER 237/90-002
B-67 CONDITIONAL CORE DAMAGE PROBABILITY CALCULATIONS Event Identifier: 237/90-002 Event
Description:
Reactor scram and LOOP with SOC train unavailable Event Date: 01/16/90 Plant: Dresden 2 INITIATING EVENT NON-RECOVERABLE INITIATING EVENT PROBABILITIES LOOP 3 .OE-D1 SEQUENCE CONDITIONAL PROBABILITY SUNS End State/Initiator Probability CO)
LOOP 3 .IE-06 Total 3. 1E-06 ATWS LOOP 9 .2E-06 Total 9 .2E-06 SEQUENCE CONDITIONAL PROBABILITIES (PROBABILITY ORDER)
Sequence End State Prob N Rec**
55 LOOP -emerg.power -rx.shutdown srv.chall/loop.-scram srv.cloae CD 1.3E-06 1.5E-01 hpci srv.ads 84 LOOP emerg.power -rx.shutdown/ep EP.REC CD 9. 6E-07 2.4E-01 65 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scram CD 2 .7E-07 1.7E-01
-srv.close isol.cond hpci 67 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scraxn CD 2.3E-07 1.7E-01 srv.close hpci 64 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scram CO 1.6E-07 8.1E-02
-srv.close isol.cond -hpci SDC lpci(cc)/lpci 66 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scram CD 1 .3E-07 8.1E-02 srv.close -hpci SDC lpci(cc)/lpci 98 LOOP -emerg.power rx.shutdown ATWS 9.OE-06 3.OE-01
- non-recovery credit for edited case SEQUENCE CONDITIONAL PROBABILITIES (SEQUENCE ORDER)
Sequence End State Prob N Rec**
55 LOOP -emerg.power -rx.shutdown srv.chall/loop.-scrain arv.close CD 1.3E-06 1 .5E-01 hpci srv.ads 98 LOOP -emerg.power rx.shutdown ATWS 9.OE-06 3.OE-01 64 LOOP emerq.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scram CD 1. 6E-07 8.1E-02 isol.cond -hpci SDC lpci(cc)/lpci
-srv.c lose 65 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scrain CD 2 .7E-07 1.7E-01
-srv.close isol.cond hpci 66 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scram CD 1. 3E-07 8.1E-02 Event Identifier: 237/90-002
B-68 srv.close -hpci SDC lpci(cc)/lpci 67 LOOP emerg.power -rx.shutdown/ep -EP.REC srv.chall/loop.-scram CD 2.3E-07 1.7E-0l srv.close hpci 84 LOOP emerg.power -rx.shutdown/ep EP.REC CD 9.GE-07 2.4E-01
- non-recovery credit for edited case SEQUENCE MODEL: c: \asp\l989\bwrbseal.cmp BRANCH MODEL: c: \asp\1989\dresden.sll PROBABILITY FILE: c:\asp\19B9\bwr-csll.pro No Recovery Limit BRANCH FREQUENCIES/PROBABILITIES Branch System Non-Recov Dpr Fail trans 3.4E-04 1.DE+OD LOOP 1.6E-05 > 1.6E-05 3.6E-01 > 3.DE-D1 Branch Model: INITOR Initiator Freq: 1.6E-05 loca 3.3E-06 5.DE-01
- ~shutdown 3.OE-DS 1.DE+00 rx .shutdown/ep 3.5E-04 1.0E+00 pcs/trans 1 .7E-01 l.OE+00 srv.chall/trans.-acram 1.OE+OD 1.DE+DD srv.chall/loop.-scram 1 .OE+OO 1. DE+OO srv.close 1.6E-02 1. DE+00 emerg.power 2.9E-03 B.OE-D1 EP .REC 6.6E-02 > 1.4E-03 1. OE+DD Branch Model: l.OF.l Train 1 Cond Prob: 6.6E-02 > 1.4E-03 fw/pcs .trans 2.9E-01 3.4E-01 hpci 2.9E-02 7.OE-O1 isol .cond 2 .DE-D2 1.02+00 crd 1 .DE-D2 l.0E+00 1. DE-02 srv. ads 3.7 E-03 7. lE-01 1.OE-02 lpcs 2 .OE-03 3.4E-01 lpc i 1. DE-03 7.1E-01 SIC 2.9E-03 > 3.2E-02 3.4 E-01 1. DE-D3 Branch Model: 1.OF.3+ser+opr Train 1 Cond Prob: 3.DE-D2 > Failed Train 2 Cond Prob: 1.OE-01 Train 3 Cond Prob: 3.DE-D1 Serial Component Prob: 2 .DE-D3 lpci (cc) l.DE-03 3.4E-01 lpci (cc) /lpci 1 .OE+00 l.DE+0O lpci (cc) /-lpci D.DE+DD l.0E+00 firewater 1 .DE+DD 1.DE+00 2. DE-03
- branch model file
- forced Mina rick 08-06-1991 17: 3D:15 Event Identifier: 237/90-002