:on 970107,containment Liner Clearance Was Not IAW Plant Design Basis.Caused by Void Between Containment Liner & Concrete Containment Structure.Inspected Containment| ML20134H778 |
| Person / Time |
|---|
| Site: |
Point Beach  |
|---|
| Issue date: |
02/06/1997 |
|---|
| From: |
Weaver D WISCONSIN ELECTRIC POWER CO. |
|---|
| To: |
|
|---|
| Shared Package |
|---|
| ML20134H776 |
List: |
|---|
| References |
|---|
| LER-97-001-01, LER-97-1-1, NUDOCS 9702110462 |
| Download: ML20134H778 (4) |
|
text
,
1 NRC FORM 366 U.S. NUCLEAR REGUL ATORY COMMIS&lON APPROVED BY OMB NO. 3160 4104 14-95) '
EXPIRES 04/30/96 ESTIMATED BURDEN PER RESPONSE TO COMPLY WITH THIS INFORMATION COLLECTION REQUEST: 50.0 HRS.
LICENSEE EVENT REPORT (LER)
REPORTED LESSONS LEARNED ARE INCORPORATED INTO THE LICENSING PROCESS AND FED BACK TO INDUSTRY.
FORWARD COMMENTS REGARDING BURDEN ESTIMATE (See reverse for required number of TO THE INFORMATION AND RECORDS MANAGEMENT digits / characters for each block)
BRANCH (T-6 F33),
U.S.
NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC 20555M1. AND TO THF PAPERWORK REDUCTION PROJECT I FACILITY NAME (1)
DOCKET NUMBER (2)
PAGE (3)
Point Be:ch Nuclear Plant, Unit 2 05000301 1 OF 4 I TITLE 14)
Containment Liner Clearance Not In Accordance With Plant Design Basis l
FVENT DATE (5) l LER NUMBER 16)
REPORT DATE (7)
OTHER FACILITIES INVOLVED (8) l MONTH I YEAR I YEAR SEQUENTIAL REVISION F ACILITY NAME DOCKET NUMBER J
DAY NUMBER NUMBER MONTH DAY YEAR 05000 J
l01 07 l 97 l 97 001 --
00 02 06 97 05000 l
FACILITY NAME DOCKET NUMBER I
CPERATING l THis REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR 4: (Check one or more) (11) l j
MODE (9)
N 2o.220m 2o.22o3:aH2Hv) bo.73(aH2Ho 50.73<aH2Hvoo POWE R l
?O.2203(aH1) 20.2203(aH3Hi)
)(
50.73(sH2Hii) 50.73(a)(2)(x)
LEVEL (10) 000 20.2203<aH2Ho 20.2203<aH3Hio 50.73(a>t2Hiin 73.71 20.2203(aH2His) 20.2203(aH4) 50.73(a)(2)(ivl OTHER 20.2203(aH2Hm!
50.36tcH1) 50.73(aH2Hv) speaty m Abstrect below I
20.2203(all2Hivl 50.36tcH2) 50.73(aH2Hvii) or in NRC Form 366 A LICE N CONTACT FOR THIS LER (12) lNAME TELEPHONE NUMBER tinclude Area Code) j David Weaver (414) 221-3418 COMPLETE ONE LINE FOR E ACH COMPONENT F AILURE DESCRIBED IN THt$ REPORT 113)
CAUSE
SYSTE M COMPONENT MANUFACTUREH REPORTABLE
CAUSE
SYSTEM l COMPONENT MANUFACTURER REPORTABLE TO NPROS
[
TO NPRDS SUPPLEMENTAL REPORT EXPECTE D (14) bCTED MONTH DAY YEAR I
YES SUBMISSION (11 yes, complete EXPECTED SUBMIS$10N DATE).
X NO DATE (15)
ABSTRACT (Llrrut to 1400 spaces,4 e., approximately 15 single-spaced typewntten knes) (16)
On January 7, 1997, while Point Beach Nuclear Plant (PBNP) Unit 2 was shut down and defueled during its annual refueling outage, plant personnel identified one location where the clearance between internal Unit 2 containment structures and the containment liner was not in accordance with the plant design basis.
During a containment inspection /walkdown of Unit 2, plant personnel noted that the Unit 2 "A" containment accident fan platform was in contact with the containment liner located opposite to an i
indicated void betwcan the containment liner and concrete containment i
ctructure.
This configuration could have resulted in a containment breach during a safe shutdown earthquake which is contrary to the plant design b sis.
The Unit 2 containment structure was immediately declared inoperable.
Plant engineers walked down the remainder of the Unit 2 containment and documented eight additional locations of concern.
The Unit 1 containment was also inspected, and although several areas of concern were identified, further evaluations determined the Unit 1 containment to be operable.
9702110462 970206 PDR ADOCK 05000301 S
PDR
l lU.S. NUCLEAJ RE AULATOaY COMMis&lON I
(4 95) l LICENSEE EVENT REPORT (LER) l TEXT CONTINUATION FACILITY N AME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
I YEAR SEQUENTIAL REVISION l
Point Beach Nuclear Plant, Unit 2 05000301 NUMM R NUMMR 2 OF 4 97 001 00 itxT Uf more space is inuked, use adddoonal copes of NRC form 366A) (17)
Event Description
On January 7, 1997, while Point Beach Nuclear Plant (PBNP) Unit 2 was shut down and defueled during its annual refueling outage, plant personnel identified one location where the clearance between internal Unit 2 containment structures and the containment liner was not in accordance with the plant design basis.
During a containment inspection /walkdown of Unit 2, plant personnel noted that the Unit 2 "A" containment accident fan platform was in contact with the containment liner located opposite to an indicated void between the containment liner and concrete containment structure.
This configuration could result in a breach of containment during a safe shutdown earthquake due to differential movement and subsequent penetration of the structure through the liner.
This is contrary to the plant design basis which states the containment structural members are designed to accept a combination of normal operating loads and safe shutdown earthquake (SSE) loads without exceeding specified stress limits The Unit 2 containment was immediately declared inoperable.
Plant engineers walked down the remainder of Unit 2 containment and documented eight additional locations with smaller than expected ~ clearances.
However, they determined that the associated structures / components would not promote damage to the liner.
The decision was made to assess the operability of the Unit 1 containment structure. Plant engineers entered Unit 1 containment on January 7,
- 1997, and identified 12 locations of concern.
A prompt operabillty review determined that the Unit 1 containment was operable based upon the structural design and configuration of the associated structures.
Component and System Description:
The reactor containment structure is a right cylinder with a flat base and a shallow domed roof.
A 1/4 inch thick steel liner is attached to the inside face of the concrete shell to ensure a high degree of leak tightness.
The base liner is installed on top of the structural slab and is covered with concrete.
The structure provides biological shielding for both normal and accident conditions.
The reactor containment is designed as a seismic Class 1 structure.
Class 1 structures and components are those whose failure might cause or increase the severity of a loss-of-coolant accident or result in an uncontrolled release of excessive amounts of radioactivity.
Class 1 structures and components also include those which are vital to the safe shutdown and isolation of the reactor.
The containment structural members are designed to accept a combination of normal operating loads and safe shutdown earthquake (SSE) loads without exceeding specified stress limits.
NHC f ORM 366A 14-95)
Mhc FORM 366A U.S. NUCLEAR REEULATORY COMMISSION (4 95)
LICEWSEE EVENT REPORT (LER)
TEXT CONTINUATION FActLITV NAME til DOCKET NUMBER (2)
LER NUMBER to)
PAGE (3)
YEAR SEQUENTIAL REVISION Point Beach Nuclear Plant, Unit 2 05000301 NUMMR NUMER 3OF4 97 001 00 TEKT Ut anere space in requked, use additionalcopies of NRC Form 366M (17)
Corrective Actious 1
The Unit 2 containment was immediately declared inoperable.
A prompt operability review determined the Unit 1 containment to be operable.
All identified Unit 2 containment liner clearance deficiencies will be resolved prior to Unit 2 core load, currently scheduled to commence on February 13, 1997.
]
The Unit 1 containment liner clearance deficiencies will be corrected during the next Unit i refueling outage, which is currently scheduled to commence on May 9, 1997.
I
Cause
Further review of this plant configuration identified that all containment liner clearance deficiencies have existed since original plant construction.
Reportability
This Licensee Event Report is being submitted in accordance with the
)
requirements of 10 CFR 50.73 (a) (2) (ii) (B), "Any event or condition that resulted in the nuclear power plant being in a condition that was outside the design basis of the plant."
A 4-hour report to the NRC was made for Unit 2 under 10 CFR 50.72 (b) (2) (i).
The NRC resident inspectors were also notified.
Safety Assessment
This event involved the potential breach of the containment liner due to contact from structural members during a seismic event.
Of the nine areas of concern for Unit 2, eight were determined to not be safety significant due to the design of the involved structural members.
Based on engineering judgment, if these members would have contacted the containment liner during a seismic evsnt, the members would have buckled prior to damaging the containment liner.
.c
{orm for the containment However, it was determined that the suppcy+
accident recirculation fan (2-W1A1) and tL_ containment cooling fan (2-W1A2) could have punctured the containment liner during a safe shutdown earthquake.
Connecting bolts on the structure are located opposite to an indicated void between the containment liner and the concrete containment structure.
Had this caused a breach in containment during a seismic event coincident with a loss-of-coolant accident (LOCA), a radiological release could have resulted.
However, the probability of a safe shutdown earthquake occurring at PBNP within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following a LOCA is 1.3E-9 per year, or once every 769,230,769 years.
Therefore, this plant condition created essentially no additional risk to plant personnel and the general public.-
m_.
..... _ _ _ _ _ _.. _ _. ~.. _...
__.__m.
.._._m_.__.-
._-._...._m.
NRC FORM 306A U.S. NUCLEAM f.EOJ.ATORY COMM4SION e
(4 95) i LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION r
FActLfTV NAME til DOCKET NUMBER (2)
LER NUM8ER (S i
PAGE 13)
YEAR SEQUENTIAL REVISION Point Beach Nuclear Plant, Unit 2 05000301 NUusEn NousER 4OF4 l
97 001 00 1
TEXT (11anore space os required, use additenalcopes of NRC form 366A) (17)
Similar occurrences:
No previous events have been identified involving the containment ctructure being outside of its design basis.
1 l
l i
i l
l h
l i
I.
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000266/LER-1997-001, :on 970108,safety Injection Delay Times Exceeded Design Basis Values.Caused by Degraded Voltage Conditions.Licensee Engineers Will Prepare FSAR Change Requests to Reflect LBLOCA Evaluation |
- on 970108,safety Injection Delay Times Exceeded Design Basis Values.Caused by Degraded Voltage Conditions.Licensee Engineers Will Prepare FSAR Change Requests to Reflect LBLOCA Evaluation
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000301/LER-1997-001, Forwards LER 97-001-00,re Containment Structure Where Internal Containment Structural Members Could Have Damaged Containment Liner During Safe Shutdown Earthquake | Forwards LER 97-001-00,re Containment Structure Where Internal Containment Structural Members Could Have Damaged Containment Liner During Safe Shutdown Earthquake | | | 05000301/LER-1997-001-01, :on 970107,containment Liner Clearance Was Not IAW Plant Design Basis.Caused by Void Between Containment Liner & Concrete Containment Structure.Inspected Containment |
- on 970107,containment Liner Clearance Was Not IAW Plant Design Basis.Caused by Void Between Containment Liner & Concrete Containment Structure.Inspected Containment
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) | | 05000266/LER-1997-002, :on 970109,potential to Overpressurize Piping Between Containment Isolation Valves Occurred.Caused by Original Design Not Providing Overpressure Protection for Piping.Review Completed |
- on 970109,potential to Overpressurize Piping Between Containment Isolation Valves Occurred.Caused by Original Design Not Providing Overpressure Protection for Piping.Review Completed
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000301/LER-1997-002-01, :on 970415,potential Reactor Coolant Sys Branch Connection Stresses Beyond Design Basis,Indicated.Caused by Mod Initiated to Remove RTD Bypass Line Isolation Valves. Stress Analysis Conducted on RTD Bypass Piping |
- on 970415,potential Reactor Coolant Sys Branch Connection Stresses Beyond Design Basis,Indicated.Caused by Mod Initiated to Remove RTD Bypass Line Isolation Valves. Stress Analysis Conducted on RTD Bypass Piping
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-003, :on 970109,did Not Perform Leak Test on Spare Containment Penetrations Per Ts.Caused by Lack of Routine Testing.Tested Penetrations W/Satisfactory Results |
- on 970109,did Not Perform Leak Test on Spare Containment Penetrations Per Ts.Caused by Lack of Routine Testing.Tested Penetrations W/Satisfactory Results
| 10 CFR 50.73(a)(2)(1) | | 05000301/LER-1997-004-01, :on 970729,declared RHR Loop Inoperable Due to CCW Leak.Caused by Failure of RHR Heat Exchanger CCW Piping. Repaired Piping & Declared RHR Loop Operable |
- on 970729,declared RHR Loop Inoperable Due to CCW Leak.Caused by Failure of RHR Heat Exchanger CCW Piping. Repaired Piping & Declared RHR Loop Operable
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-004, :on 970113,potential for Particular Common Mode Failure That Could Affect Opposite Trains of Unit 2 Safeguards Equipment Was Noted.Caused by Lack of Physical Separation.Replaced Subject Circuit Breakers |
- on 970113,potential for Particular Common Mode Failure That Could Affect Opposite Trains of Unit 2 Safeguards Equipment Was Noted.Caused by Lack of Physical Separation.Replaced Subject Circuit Breakers
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000301/LER-1997-005-01, :on 970806,RHR Pump Was Declared Inoperable Due to Abnormal Seal Leakage from Loop a RHR 2P-10A.Repaired RHR Pump |
- on 970806,RHR Pump Was Declared Inoperable Due to Abnormal Seal Leakage from Loop a RHR 2P-10A.Repaired RHR Pump
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-005, :on 970116,1SI-852A Was Not Tested IAW Inservice Test Program Required by Tss.Caused Because Condition Revealed That Valve 1SI-852A Had Not Been Completely Tested.Tests Will Be Reviewed |
- on 970116,1SI-852A Was Not Tested IAW Inservice Test Program Required by Tss.Caused Because Condition Revealed That Valve 1SI-852A Had Not Been Completely Tested.Tests Will Be Reviewed
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-006, :on 970120,refueling Cavity Drain Failed During Loca.Caused by Inadequate Evaluation of Original Design.Design of Refueling Cavity Drains Was Revised with Respect Capability to Withstand an Earthquake |
- on 970120,refueling Cavity Drain Failed During Loca.Caused by Inadequate Evaluation of Original Design.Design of Refueling Cavity Drains Was Revised with Respect Capability to Withstand an Earthquake
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-007, :on 970124,determined That Potential Existed for EDG Overload Condition.Caused by Failure to Recognize This Condition When Plants Initially Licensed W/Two Edgs. Implemented Procedure Changes |
- on 970124,determined That Potential Existed for EDG Overload Condition.Caused by Failure to Recognize This Condition When Plants Initially Licensed W/Two Edgs. Implemented Procedure Changes
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-008, :on 970131,non-seismic Ductwork Located Above safety-related Equipment in Containment Occurred.Caused by Incomplete Seismic Evaluation.Mods Will Be Completed During Current Unit 2 Refueling Outage |
- on 970131,non-seismic Ductwork Located Above safety-related Equipment in Containment Occurred.Caused by Incomplete Seismic Evaluation.Mods Will Be Completed During Current Unit 2 Refueling Outage
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-009, :on 970214,potential for Safety Injection Failure During Filling of Safety Injection Accumulator Discovered.Caused by Situation Not Adequately Covered by Procedures.Procedure OI-100 Revised |
- on 970214,potential for Safety Injection Failure During Filling of Safety Injection Accumulator Discovered.Caused by Situation Not Adequately Covered by Procedures.Procedure OI-100 Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-010, :on 970219,svc Water & Component Cooling Water TS Action Requirements Were Not Met.Caused Because Licensee Did Not Comply W/Cold Shutdown Requirements of TS 15.3.3.C.2 & 15.3.3.D.2.Evaluations Were Performed |
- on 970219,svc Water & Component Cooling Water TS Action Requirements Were Not Met.Caused Because Licensee Did Not Comply W/Cold Shutdown Requirements of TS 15.3.3.C.2 & 15.3.3.D.2.Evaluations Were Performed
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-011, :on 970305,containment Fan Cooler Accident Fans Were Not Tested in Accordance with Tss.Caused by non-conservative Interpretation of Literal Requirements of Tss.Unit 1 & 2 Accident Fans Were Tested |
- on 970305,containment Fan Cooler Accident Fans Were Not Tested in Accordance with Tss.Caused by non-conservative Interpretation of Literal Requirements of Tss.Unit 1 & 2 Accident Fans Were Tested
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-012, :on 970304,diesel-drive Fire Pump Day Tank Not Sampled IAW TSs.Non-conservative Interpretation of TS Led to Failure.Day Tank T-30 Sample Was Drawn & Analyzed W/Satisfactory Results |
- on 970304,diesel-drive Fire Pump Day Tank Not Sampled IAW TSs.Non-conservative Interpretation of TS Led to Failure.Day Tank T-30 Sample Was Drawn & Analyzed W/Satisfactory Results
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-013, :on 970304,CCWS Found Not in Accordance W/ Plant Design Basis.Caused by Inoperable Valve Due to Overtorquing in Closed position.Cross-tie Will Be Resolved |
- on 970304,CCWS Found Not in Accordance W/ Plant Design Basis.Caused by Inoperable Valve Due to Overtorquing in Closed position.Cross-tie Will Be Resolved
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-013-01, Forwards Suppl LER 97-013-01,re Component Cooling Water Sys Not IAW Plant Design Basis.Rept Replaces LER 97-013-00 in Its Entirety & Includes Addl Similar Occurrence Not Previously Reported to NRC | Forwards Suppl LER 97-013-01,re Component Cooling Water Sys Not IAW Plant Design Basis.Rept Replaces LER 97-013-00 in Its Entirety & Includes Addl Similar Occurrence Not Previously Reported to NRC | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-014, :on 970321,auxiliary Feedwater Sys Inoperability Due to Loss of Instrument Air.Design Mods Initiated,Providing Pneumatic Supply to Control Valves |
- on 970321,auxiliary Feedwater Sys Inoperability Due to Loss of Instrument Air.Design Mods Initiated,Providing Pneumatic Supply to Control Valves
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) | | 05000266/LER-1997-015, :on 970324,control Room Ventilation Sys Declared Inoperable Due to Failures of Backdraft Damper & Vent Duct Access Door.Backdraft Damper,Replaced |
- on 970324,control Room Ventilation Sys Declared Inoperable Due to Failures of Backdraft Damper & Vent Duct Access Door.Backdraft Damper,Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-016, :on 970325,SG Level Logic Was Not Tested IAW Ts.Caused by Nonconservative Interpretation of Tss.Ts Amends Proposed to Provide Consistency Between Test Requirements & LCO Associated W/Sg Tests |
- on 970325,SG Level Logic Was Not Tested IAW Ts.Caused by Nonconservative Interpretation of Tss.Ts Amends Proposed to Provide Consistency Between Test Requirements & LCO Associated W/Sg Tests
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-017, :on 920508,containment Third Door Was Blocked Open During Refueling Operations.Caused by Interpretation That Movement of Core Components Per TS Definitions Rather than Literal Wording.Routine Maintenance Procedure Revised |
- on 920508,containment Third Door Was Blocked Open During Refueling Operations.Caused by Interpretation That Movement of Core Components Per TS Definitions Rather than Literal Wording.Routine Maintenance Procedure Revised
| 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-018, :on 970403,potential for RHR Overpressure During Accidents Was Discovered.Original Design Did Not Provide Overpressure Protection for Isolated Piping Section. Evaluation Was Performed to Determine Stress on Piping |
- on 970403,potential for RHR Overpressure During Accidents Was Discovered.Original Design Did Not Provide Overpressure Protection for Isolated Piping Section. Evaluation Was Performed to Determine Stress on Piping
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-019, :on 970404,RHR Not Aligned IAW TS Requirements. Caused by non-conservative Decision Making & Not Recognizing When TS Were Not Controlling Plant Operations.Pbnp Mgt Philosophy Re TS Interpretations Changed to Minimize Use |
- on 970404,RHR Not Aligned IAW TS Requirements. Caused by non-conservative Decision Making & Not Recognizing When TS Were Not Controlling Plant Operations.Pbnp Mgt Philosophy Re TS Interpretations Changed to Minimize Use
| 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-020-01, Forwards LER 97-020-01,describing Plant Conditions in Which Ability to Achieve & Maintain Safe Shutdown in Event of Postulated Fire May Have Been Adversely Affected | Forwards LER 97-020-01,describing Plant Conditions in Which Ability to Achieve & Maintain Safe Shutdown in Event of Postulated Fire May Have Been Adversely Affected | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | | 05000266/LER-1997-021, :on 970430,determined That Spent Fuel Pool Cooling Sys Was Not in Accordance W/Plant Design Basis.Cause Indeterminate.Closed & re-tagged Valves SF-27 & SF-28 & Investigated Basis for Fsar,App a |
- on 970430,determined That Spent Fuel Pool Cooling Sys Was Not in Accordance W/Plant Design Basis.Cause Indeterminate.Closed & re-tagged Valves SF-27 & SF-28 & Investigated Basis for Fsar,App a
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-022, :on 970507,discovered That Postulated Control Room Fire May Cause Electrical Hot Short That Disables Limit or Torque Switches for Certain Movs.Mods Initiated to Remedy Condition |
- on 970507,discovered That Postulated Control Room Fire May Cause Electrical Hot Short That Disables Limit or Torque Switches for Certain Movs.Mods Initiated to Remedy Condition
| 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | | 05000266/LER-1997-023, :on 970508,discovered Noncompliant Emergency Lighting for Postulated App R Fires.Caused by Alternative Provisions Made in Original Safe Shutdown Analysis.Emergency Lights Will Be Installed |
- on 970508,discovered Noncompliant Emergency Lighting for Postulated App R Fires.Caused by Alternative Provisions Made in Original Safe Shutdown Analysis.Emergency Lights Will Be Installed
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000266/LER-1997-024, :on 970501,determined Post Accident Sampling Sys Degradation.Caused by Inadequate Design Review.Will Upgrade Containment Atmosphere Sample Sys & Will Perform Mod to Reduce Dose within GDC 19 Dose Limits |
- on 970501,determined Post Accident Sampling Sys Degradation.Caused by Inadequate Design Review.Will Upgrade Containment Atmosphere Sample Sys & Will Perform Mod to Reduce Dose within GDC 19 Dose Limits
| | | 05000266/LER-1997-025, :on 970520,pressurizer Level Was Controlled Higher than Assumed in Accident Analysis.Caused by Inappropriately Changing Procedures W/O Adequate Consideration.Listed Affected Procedures Will Be Revised |
- on 970520,pressurizer Level Was Controlled Higher than Assumed in Accident Analysis.Caused by Inappropriately Changing Procedures W/O Adequate Consideration.Listed Affected Procedures Will Be Revised
| 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-026, :on 970521,discovered TS Violation of Operability Requirement of MSL Isolation.Caused by Inadequate Consideration for Operability of All Required Functions.Verified Low RCS Sys Average Temp |
- on 970521,discovered TS Violation of Operability Requirement of MSL Isolation.Caused by Inadequate Consideration for Operability of All Required Functions.Verified Low RCS Sys Average Temp
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-027, :on 970521,non-environmentally Qualified Matl Existed in Containment Hatch Applications.Caused by Inadequate Design Review.Mods Will Be Performed to Remove Existing Teflon Material |
- on 970521,non-environmentally Qualified Matl Existed in Containment Hatch Applications.Caused by Inadequate Design Review.Mods Will Be Performed to Remove Existing Teflon Material
| | | 05000266/LER-1997-031, :on 970619,discovered That Auxiliary Feedwater (AFW) Pump Low Suction Pressure Trip Setpoints May Not Ensure Adequate Suction Pressure Protection for AFW Pumps Following Tornado Event.Caused by Inadequate Design |
- on 970619,discovered That Auxiliary Feedwater (AFW) Pump Low Suction Pressure Trip Setpoints May Not Ensure Adequate Suction Pressure Protection for AFW Pumps Following Tornado Event.Caused by Inadequate Design
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-032, :on 970630,discovered Inadequately Rated Electrical Buses Could Disable Switchgear & Cause Secondary Fires.Caused by Characteristic of Original Design. Established twice-per-shift Fire Watches |
- on 970630,discovered Inadequately Rated Electrical Buses Could Disable Switchgear & Cause Secondary Fires.Caused by Characteristic of Original Design. Established twice-per-shift Fire Watches
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000266/LER-1997-034, :on 970707,discovered Unplanned Loss of Voltage on Train B Safeguards Buses.Caused by Inadequate Design & Design Review for Installation of New Train B Edgs.Incorrect Wiring Reworked |
- on 970707,discovered Unplanned Loss of Voltage on Train B Safeguards Buses.Caused by Inadequate Design & Design Review for Installation of New Train B Edgs.Incorrect Wiring Reworked
| 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000266/LER-1997-035, :on 970516,discovered Inadequate Seismic Support for Reactor Coolant Pump Rotor Stand.Caused by Rotor Stand Being Stored Since Initial Plant Construction.Moved Rotor Stand & Verified as Seismically Adequate |
- on 970516,discovered Inadequate Seismic Support for Reactor Coolant Pump Rotor Stand.Caused by Rotor Stand Being Stored Since Initial Plant Construction.Moved Rotor Stand & Verified as Seismically Adequate
| 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | | 05000266/LER-1997-036, :on 970826,potential Common Mode Failure in DC Power Supply Which Could Disable AFW Sys Was Noted.Caused by Inadequate Design & Design Review.Plant Mods Were Performed to Eliminate Potential Common Mode Failure |
- on 970826,potential Common Mode Failure in DC Power Supply Which Could Disable AFW Sys Was Noted.Caused by Inadequate Design & Design Review.Plant Mods Were Performed to Eliminate Potential Common Mode Failure
| | | 05000266/LER-1997-037, :on 970903,potential Failure of EDG Load Sequence Occurred.Caused by Inadequate Design of EDG Load Sequencing Logic.Mod Restored Operability of EDG During Load Sequencing |
- on 970903,potential Failure of EDG Load Sequence Occurred.Caused by Inadequate Design of EDG Load Sequencing Logic.Mod Restored Operability of EDG During Load Sequencing
| | | 05000266/LER-1997-038, :on 970926,determined That Inoperability of Standby Emergency Power Placed Unit 2 in 7-day Lco.Caused by Failure That Occurred When EDG G-03 Was Shutdown.Repaired Governor & Returned EDG G-03 to Service |
- on 970926,determined That Inoperability of Standby Emergency Power Placed Unit 2 in 7-day Lco.Caused by Failure That Occurred When EDG G-03 Was Shutdown.Repaired Governor & Returned EDG G-03 to Service
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-039-01, :on 970615,RHR Loop Inoperable.Caused by Removal of CCW Pump from Svc.Ccw Pump Restored |
- on 970615,RHR Loop Inoperable.Caused by Removal of CCW Pump from Svc.Ccw Pump Restored
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-039, Forwards LER 97-039-00 Re RHR Loop Inoperable,Due to Inoperable CCW Pump.New Commitments within Rept Indicated in Italics | Forwards LER 97-039-00 Re RHR Loop Inoperable,Due to Inoperable CCW Pump.New Commitments within Rept Indicated in Italics | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000266/LER-1997-040-01, Forwards LER 97-040-01 Which Documents Event That Occurred at Point Beach Nuclear Plant,Unit 1.Commitments Made within Ltr,Encl | Forwards LER 97-040-01 Which Documents Event That Occurred at Point Beach Nuclear Plant,Unit 1.Commitments Made within Ltr,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000266/LER-1997-041, :on 971023,potential Common Mode Failure in Afws Control Circuits Was Noted.Caused by AFW Control Circuits Installed by Plant Mods.Temporary Mods Will Restore Physical Separation for Cables |
- on 971023,potential Common Mode Failure in Afws Control Circuits Was Noted.Caused by AFW Control Circuits Installed by Plant Mods.Temporary Mods Will Restore Physical Separation for Cables
| | | 05000266/LER-1997-042, :on 971030,discovered That Upper Containment Personnel Air Interlock Had Been Inoperable.Caused by Removal of Remote Operating Gear.Reinstalled Remote Operating Connector Gear |
- on 971030,discovered That Upper Containment Personnel Air Interlock Had Been Inoperable.Caused by Removal of Remote Operating Gear.Reinstalled Remote Operating Connector Gear
| 10 CFR 50.73(a)(2)(1) | | 05000266/LER-1997-043-01, Forwards LER 97-043-01,re Discovery That TS Surveillance of Reactor Trip Sys Interlocks Were Not Adequate. Supplemental Info Is Provided at End of Rept.Previous Commitments Made within Rept Also Encl | Forwards LER 97-043-01,re Discovery That TS Surveillance of Reactor Trip Sys Interlocks Were Not Adequate. Supplemental Info Is Provided at End of Rept.Previous Commitments Made within Rept Also Encl | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000266/LER-1997-044, :on 971216,use of Dedicated Operators During IST of Containment Spray Sys Constituted Operation Prohibited by Ts.Caused by Improper Consideration for Use of Dedicated Operators.Revised Procedures |
- on 971216,use of Dedicated Operators During IST of Containment Spray Sys Constituted Operation Prohibited by Ts.Caused by Improper Consideration for Use of Dedicated Operators.Revised Procedures
| |
|