ML20128R050

From kanterella
Jump to navigation Jump to search
Part 21 & Deficiency Rept,Item 191 Re Potential for Insulation Breakdown on GE Supplied Transformers.Initially Reported on 841029.Six-month Energization Test Not Completed Due to Unavailable Equipment.Next Rept by 850913
ML20128R050
Person / Time
Site: Harris 
Issue date: 05/31/1985
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-368, REF-PT21-85, REF-PT21-85-328-000 191, PT21-85-328, PT21-85-328-000, NUDOCS 8507150136
Download: ML20128R050 (1)


Text

CD&L Carolina Power & Ught Company

...,~m.,..

vw P.O. Box 101, New Hill, NC 27562 May 31,1985 U,

f~~

Dr. 3. Nelson Grace NRC-368 :5 United States Nuclear Regulatory Commission c;

Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30323 co CAROLINA POWER & LIGHT COMPANY N

SHEARON HARRIS NUCLEAR POWER PLANT 1986 - 900,000 KW - UNIT 1 7.5 KVA INVERTERS -

INSULATION BREAKDOWN, ITEM 191

Dear Dr. Grace:

On October 29,1984, Mr. N. 3. Chiangi notified the NRC of a potentially reportable item per the provisions of 10CFR50.55(e) and 10CFR,~ Part 21.

The NRC was informed that a potential exists for insulation breakdown on G.E. supplied transformers. These transformers are part of the Westinghouse inverters supplied to the Harris Project.

Westinghouse has notified the NRC that this is a 10CFR50.55(e) item for plants under construction.

On November 28,1984, we informed the NRC via letter (NRC-296) that CP&L had not confirmed that this problem existed in the SHNPP inverters. It was planned to energize the subject inverters for a six month period. Any G. E. transformer that operates under load for a six month period without exhibiting output degradation may be considered satisfactory. At that time it was projected that a report on the reportability of this iten would be issued by June 7,1985. This date was based on the completion of the s.< month energization test.

Due to the unavailability of load testing equipment, the six month energization test has not been completed at this time as previously projected. The required testing and completion of the reportability evaluation is now projected to be accomplished and reported to the NRC by September 13,1985.

Thank you for your consideration in this matter.

Yours very truly, 8507150136 850531 D-/W PDR ADOCK 05000400

. M. Parsons S

PDR-Project General Manager Completion Assurance Shearon Harris Nuclear Power Phnt RMP/aj cc: