ML20128K389

From kanterella
Jump to navigation Jump to search
Ack Receipt of 850613 Response to Integrated Design Insp Rept 50-400/84-28.Closeout Insp Planned to Examine Areas Requiring Further Info.Areas Requiring Reinsp &/Or Addl Info Listed in Encl
ML20128K389
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/12/1985
From: Grimes B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Utley E
CAROLINA POWER & LIGHT CO.
References
NUDOCS 8507240119
Download: ML20128K389 (15)


See also: IR 05000400/1984028

Text

e,'

w

+f

UNITED STATES

y

g

NUCLEAR REGULATORY COMMISSION

.

>

7,

j

WASHING TON, D. C. 20555

%...../

Docket No.

50-400

g gg g

Carolina Power and Light Company

ATTN:

Mr. E. E. Utley

Executive Vice President

Power Supply and Engineering

and Construction

P.O. Box 1551

Raleigh, NC 27602

Gentlemen:

SUBJECT:

INTEGRATED DESIGN INSPECTION 50-400/84-48

This refers to your letter dated June 13, 1985 which was in response to our

letter forwarding the subject inspection report dated April 15, 1985.

Thank you for informing us of the corrective and preventive actions documented

in your letter. Certain of the items of your response require additional

information, review, and/or reinspection to assess their acceptability.

In other

areas the NRC inspection team disagrees with statements made concerning the

validity of inspection findings.

However, these matters are not pursued since

you have indicated that appropriate corrective action is being taken.

A close-out inspection by members of the team is planned to examine areas

requiring furtner information. The enclosure to this letter describes areas

that will be inspected by the team. However, the team will not necessarily be

limited to the items in the enclosure, but may also inspect other items discussed

in your response to the Integrated Design Inspection (IDI) report. Although our

report did not require you to respond to observations, we note that your response

did addres,s these items.

During our review of your response to these items, several

questions were identified by the team which will also be examined during the

reinspection.

-

Please have the information described in the enclosure to this

letter available for the close-out inspection currently scheduled for July

22-24, 1985.

S

fely,

,

'

/

8507240119 850712

p

ianK.GYimes, Director

gDR

ADOCK 0s000400

g

Division of Quality Assurance, Vendor

PDR

and Technical Training Center Program

Office of Inspection and Enforcement

Enclosure:

Shearon Harris IDI Items Requiring

Reinspection and/or Additional

Information

-

.

-

-

- - - . -

-

-

- -

-

-

.

.

.

_

_

--

_

--. _ . _

__

. _ _ . .

._ .. . -.__. _

_

'

. , -

.

.

,

Mr. E. E. Utley

-2-

'

,

'

Distribution:

DCS016

i

QAVT Reading

QAB Reading

RHVollmer, IE

BKGrimes, IE

GTAnkrum, IE

JLMilhoan, IE

ELJordan, IE

PFrederickseon, RII

RAchitzel, IE

BBuckley, NRR

f'o A

!

r

.,

bY

IE:ffh{h

QAVT:QAB

IE:Q$/ [:QAB

D:I

AVT:QAB

IE: AVT:QAB

RAchitzel

JLMilh'oan

GTA6kum

BK

mes

07/,//85

07///85

07/p

-M7/g $5

4

&

. - -

. . - -

- . - - , _ . . . _ , _ - - . - - . . _ - - . . - . - _ _ _ _ . _ _ _ - _ - - , - _ , _ , , - _ _ . - . _ _ _ . _ , _

. - . . . - , - . _ _ -

~ ~. _ . -

.'

..

Carolina Power and Light

-2-

,

,

cc w/ enclosures

.

R. A. Watson, Vice President

Harris Nuclear Project

R. M. Parsons

Carolina Power and Light Company

Completion Assurance Manager

P.O. Box 165

Carolina Power and Light Company

P. O. Box 101

New Hill, NC 27562

New Hill, NC 27562

George F. Trowbridge, Esq.

Shaw, Pittman, Potts & Trowbridge

Mr. George Jackson, Secretary

1800 M Street, NW

Environmental Law Project

Washington, DC 20036

School of Law, 064-A

Univeristy of North Carolina

Richard E. Jones, Esq.

Chapel Hill, North Carolina 27514

Associate General Counsel

Carolina Power & Light Company

Mr. Travis Payne, Esq.

411 Fayetteville' Street Mall

723 W. Johnson Street

Post Office Box 12643

Raleigh, North Carolina 27602

Raleigh, North Carolina 27605

M. David Gordon, Esq.

Associate Attorney General

Mr. Daniel F. Read

State of North Carolina

Post Office Box 2151

Post Office Box 629

Raleigh, NC 27602

Raleigh, North Carolina 27602

Thomas S. Erwin, Esq.

Bradley W. Jones, Esq.

115 W. Morgan Street

U.S. Nuclear Regulatory Comm.

Region II

Raleigh, North Carolina 27602

101 Marietta Street

Mr. George Maxwell

Atlanta, Georgia 30303

Resident Inspector / Harris NPS

c/o U.S. Nuclear Regulatory Commission

Richard D. Wilson, M. D.

725 Hunter Street

Route 1, Box 315B

Apex, North Carolina 27502

New Hill, North Carolina 27562

Charles D. Barham, Jr., Esq.

Vice President & Senior Counsel

Mr. Robert P. Gruber

Carolina ' Power & Light Company

Executive Director

Public Staff - NCUC

Post Office Box 1551

P. O. Box 991

Raleigh, North Carolina 27602

Raleigh, NC 27602

-

Mr. John Runkle, Executive Coordinator

Conservation Council of North Carolina

307 Granville Road

Chapel Hill, North Carolina 27514

Mr. Wells Eddleman

718-A Iradell Street

Durham, North Carolina 27705

Dr. Linda Little

'

Governor's Waste Management Board

513 Albemarle Building

325 North Salisbury Street

'

Raleigh, North Carolina 27611

,

.

-

.

,

O

MECHANICAL SYSTEMS

D2.2-1 (Deficiency) Missing Drawings from Westinghouse Design Interface

DrawingList(DIDL)

The team will review the latest transmittal of Design Interface Drawings from

EBASCO to Westinghouse and the response from Westinghouse indicating no

significant impact on design.

D2.2-2 (Deficiency) Errors in Westinghouse Proof of Design Calculations

The team will review the revised calculation CWS-CQL-025 to ascertain if th

licensee's preliminary conclusion was correct.

D2.3-1(Deficiency)ContainmentRecirculationSumpDesign

The team does not agree with the licensee's conclusions for this item,

therefore this item is being referred to NRR as a licensing issue.

D2.3-3 (Deficiency) Refueling Water Storage Tank Vortexing

The team will reinspect calculations EQS-2 and TANK 13 in order to resolve the

apparent differences between the original finding and the ifcensee's response.

02.3-5 (Deficiency) Containment Spray System Eductor Flow Rate

The team will review the revised calculation CT-27. The team will also review

the effect of these revised eductor flow rates in the sump pH calculation.

U2.4-1 (Unresolved Item) Cable Tray Combustible Load Calculation

The team will review the revision to calculation 46-A0.

.

D2.4-2 (Deficiency) Cable Tray Overfill

The team will review the combustible loading calculations following their

revision to reflect the as-built condition.

D2.4-3 (Deficiency) Combustible Load Within Fire Area 1-A-BAL

The team will review the revisions to calculation FP-S-1-A-BAL and the

associated FSAR change request.

4

.,

.

.

.

02.4-4 (Deficiency) Use of Minitrim (PVC) in Areas Outside Containment

The team agrees with the need to revise the applicable Engineering Section

~

Instructions 3.1 and 3.2 to ensure the Field Change Requests are reviewed for

impact on the Fire Hazard Analysis. The team will review these changes. The

team plans to review the analysis of the impact of the current use of

Minitrim.

02.6-1 (Deficiency) Installation of Charging Pump Room Air Handling Units

Further clarification of the action to be taken to resolve the inconsistencies

identified in the finding is needed. The team is concerned about other

Equipment Installation Packages that are not in compliance with Work Procedure

WP-105 with respect to torqueing of anchor bolts.

D2.7-1 (Deficiency) Non-Seismic Piping Interaction Damage Study

The team needs clarification of action to be taken to resolve the unchecked

calculation issue and subsequent use of the results. The team will review and

evaluate the procedures developed for Seismic II/I walkdown. The results of

the two Phases of the Seismic II/I walkdown will be reviewed by the NRC.

D2.7-2 (Deficiency) Non-Seismic Piping Interaction Damage Study

The team is unclear regarding the action taken to resolve the Seismic II/I

condition identified in the finding. The team will review and evaluate the

procedures developed for the Seismic II/I walkdown. The results of walkdown

will be reviewed by the NRC.

02.8-1 (Deficiency) Field Installation Tolerances for Hangers

The team nseds clarification regarding what action is being taken to correct

the specific problem identified in the finding. The team will review and

evaluate the procedures developed for the walkdown. The results of the

-

walkdown will be reviewed by the NRC.

02.9-1 (Deficiency) Pump Vendor Drawing Error

The team will review the corrected vendor drawing and the revised purrp

instruction manual.

02.5-1, D2.5-3, D2.5-4, 02.5-5, 02.5-6, and 02.5-7

The team has not yet reviewed and evaluated the response to these

deficiencies. They will be evaluated during the einspection.

-

-

-

-

-

-

,

,

.

,

.

MECHANICAL COMPONENTS

D3.1-4 (Deficiency) Harris Project Pipe Support Procedures

Carolina Power and Light has merged two separate pipe support design

guidelines that contained inconsistent deflection criteria into a single

document. That document stipulates deflection criteria that are consistent

with a pending amendment to FSAR table 3.9.3-7.

The team will review these

changes.

D3.1-5 (Deficiency) Supplementary Steel

The Carolina Power and Light Harris Plant Engineering Section design

guidelines specified supplementary steel tabular data developed by

Bergen-Paterson for seismic as well as non-seismic applications. However,

Bergen-Paterson had limited the use nf that tabular data to non-seismic

supports. Carolina Power and Light i.as obtained confirmation of the seismic

qualification of that tabular data from Bergen-Paterson for incorporation into

the Harris Plant Engineering Section design guidelines. The team will review

this documentation.

D3.1-6 (Deficiency) Pipe Support Stress Check

Carolina Pcwer and Light has corrected the design guidelines and is reviewing

final calculations which were done while the erroneous equation was in effect.

The team will review these actions and efforts.

U3.1-7 (Unresolved Item) U-Bolt Load Interaction

The team will review Bergen-Paterson confirmation that use of the linear

interaction equation was appropriate, and that qualification of these U-bolts

was by ifnear analysis.

U3.1-8(UnresolvedItem)FrictionAnchorClamps

This unresolved item concerned the evaluation of stress in small-bore pipe

restrained with friction anchor clamps. The team plans review of:

a)

the Bergen-Paterson analysis for friction anchor clamps which

limits local pipe wall stresses to 12,000 psi;

b)

the work procedures for installation and inspection of friction

anchor clamps; and

c)

computer analysis stress ratios as a function of allowable stress

at friction anchor clamp node points.

D3.2-1 (Deficiency) DBE Inertia / Functional Capability

The licensee stated that a sample study of ten calculations was performed in

order to confirm the reasonableness of the assurrption that if the OBE load

case meets its stress limits, in turn so will the DBE load case. While in

most cases this is true, the team plans to review a larger sample in order to

assess functional capability.

-

- -

- - -

-

- -

-

-

-

-

-

-

'

.

,

-

.

03.2-3 (Observation) Evaluation of Valve Accelerations

The response states that a program initiated in 1982 requires that, for all

new or revised calculations, an appropriate valve evaluation sheet be prepared

and included in the calculation package. The team is still of the opinion

that for all previously released calculations where g-loading had not been

performed, as is the case of this observation, evaluations should be conducted

and documented in the stress package. Further inspection of this matter is

planned.

03.2-4 (Deficiency) Westinghouse Active Valve Qualification Program

The Itcensee response stated that previously omitted valve evaluation sheets

are now part of the calculation package 141-2. Additional inspection is

necessary in order to confirm:

(1) that for the three active valves 2CS-V600-SB-1, 2CS-V601, and

2CS-V602-SB-1, g-loading and end loading evaluation meet

appropriate limits and are properly documented;

(2) that for active valves 2CS-V601-SB-1 and 2CS-V602-SB-1, the

sketch included on the valve acceleration calculation sheets is

consistent with the mathematical model and vendor valve drawings;

and,

(3) that the procedure outlined by the response is technically

acceptable, consistent with the procedure used on a majority

of previously calculated valve g-loading evaluations, and if

it follows the same logic as used by the E8ASCO in-house pipe

program in calculating valve g-loading.

03.2-6 (Deficiency) Emergency Condition Stress Ratio

The licensee response stated that several changes were incorporated into the

.

reanalysis.resulting in the significant reduction of emergency condition

stress levels. The team plans to inspect the revised calculation to evaluate

the influence of the design changes for all loading conditions.

,

03.2-8(Deficiency)ThermalExpansionInput

Calculation 141-1 was rerun and the licensee stated that there was no impact

on the existing design. The team will review the revised calculation.

03.2-9(Deficiency)VolumeControlTankNozzleDisplacement

The licensee stated that calculation 142-3 was rerun with the previously

omitted nozzle displacement and the existing design has been demonstrateo to

be adequate. The team will inspect the revised calculation to evaluate the

influence of the corrected 250F thennal mode on the existing design.

03.2-17 (Deficiency) Regenerating Heat Exchanger Seismic Analysis

The team will review documentation of EBASCO's plans to model the vertical

restraint adjacent to the tube side inlet nozzle of the regenerative heat

-

- -

- -

.'

,

.

.

,

exchanger as a snubber and rerun calculation 3006 with the revised modeling

upon its next revision.

U3.3-1 (Unresolved Item) ITT Grinnell Air Operated Valves

EBASCO and Westinghouse have developed a modeling procedure to address the

analysis of ITT Grinnell diaphragm-operated valves originally procured as

rigid and determined to be flexible. The team will review the procedure for

analysis

of the. valves and plans for implementation of the procedure.

D3.4-1 (Deficiency) Pipe Support Strut Design

The response to this deficiency does not acknowledge that the dynamic stresses

and deflections of slender struts subjected to a seismic event can be

significant, and states that such an evaluation was not performed for the

struts installed in the plant. However, the team will review and evaluate

licensee actions taken to address this concern.

03.4-2 (Deficiency) B-P/CP&L Pipe Support Design

The team will review revised pipe support calculation A-6-236-1-CS-H-2027.

U3.5-1(UnresolvedItem)WestinghouseSuppliedNon-ActiveValves

EBASCO has obtained formal concurrence from Westinghouse that end inads for

Westinghouse-procured non-active valves need not be considered. The team

plans to review this documentation.

_ CIVIL / STRUCTURAL

04.2-4 (Deficiency) Preparation of Calculation

Inspection of the remedial work which has been performed to address this

deficiency is planned.

-

D4.2-7 (Deficiency) Shear Area

The licensee indicated that some reanalyses were performed. The team had

reviewed part of the reanalyses during the initial inspection and found that

they were acceptable. The team will review the remainder of the reanalyses

during the reinspection.

D4.4-1 (Deficiency) Loading Combinations

Calculation books CAS -1 and 2168-G-253-502 will be examined during the

reinspection to verify that the licensee's evaluation is properly documented.

-

-

.

-

. .

.

.

.

',

.

.

.

04.5-1(Deficiency)SlabDesignUsingDirectDesignMethod

EBASCO states that they have perfomed confinnatory calculations for the

Reactor Auxiliary Building and Fuel Handling Buf1 ding slab panels to show that

the existing design is adequate. These calculations will be inspected to

determine their acceptability.

D4.5-3 (Deficiency) Load Combination for Slab Design

The team will inspect the latest load combination calculations used for slab

design.

D4.5-4 (Deficiency) Seismic Analysis for Masonry Walls

EBASCO has perfomed analysis to demonstrate that these walls are adequate.

This analysis will be inspected to determine its acceptability.

04.5-5(Deficiency)UseofFloorSpectra

EBASCO has performed analysis using the broadened response spectra. An

inspection of this analysis is planned.

D4.5-6 (Deficiency) Design of Masonry Wall Around Stairway A-4

The team considers the response to be inadequate. The response states that

although the design changes were reviewed, the original calculation was not

revised. Specifically, the team believes that EBASCO should perform an

analysis of the final configuration of the wall to determine its structural

adequacy. This analysis should include a frequency analysis of the wall to

determine the seismic loads. The team will inspect the frequency analysis for

the block wall, if such an analysis has been performed.

04.8-1 (Deficiency) Load Combinations for Main Dam Spillway

EBASCO perfomed additional analyses of the main dam spillway to show that the -

existing design is adequate. The team will inspect the analysis of the main

dam spillway to verify that the existing design is adequate.

D4.8-2 (Deficiency) Main Dam Spillway Abutment Design

EBASCO has performed reanalysis of the abutment wall using the correct weight

to show that the existing design is adequate. This reanalysis will be

inspected.

04.9-1(Deficiency)BoronRecycleHold-upTankSeismicLoads

EBASCO has performed analyses of slabs supporting large tanks in the Fuel

Handling Building, Reactor Auxiliary Building and the Waste Processing

Building. The response states that these analyses show that the existing

designs are adequate. These calculations will be inspected to assess their

adequacy.

.

.

.

.

.

.

,

.

D4.10-1 (Deficiency) Cable Tray Support Frequency

The team will inspect both the calculation for all supports shown on sample

drawings and the frequency analysis for longitudinal bracing.

D4.11-1 (Deficiency) Frequency of HVAC Ducts

EBASCO has identified five cases for which they are in the process of

confirming the support and duct adequacy. These calculations will be reviewed

by the team.

D4.11-2(Deficiency)LoadsonHVACDuctSupports

EBASCO has identified various cases where actual loads are higher than those

used in the support design.

They are still performing confirmatory analyses

on these supports to establish their design adequacy. These calculations will

be inspected.

D4.11-3 (Deficiency) Frequency of HVAC Duct Supports

EBASCO has initiated a program to evaluate the calculations for all supports

shown on sample drawings. This evaluation will be inspected to determine

whether the supports have frequencies above 16 Hz.

i

ELECTRICAL POWER SYSTEMS

V5.2-1 (Unresolved Item) Electrical Power Design Procedures & Guidelines

The team is concerned that the guidelines which are still in preparation

apparent 1y'have not been issued to the working unit. The team will revhw the

completed Harris Plant Engineering Section electrical unit's Design Procedures

and Guidelines. Please provide a status of the 13 proposed guidelines.

.

US.3-1(UnresolvedItem)IndependenceofElectricSystems

The team will review the design change notices and the revised drawings

associated with this modification.

D5.4-1 (Deficiency) Protection of Safety-Related Buses

The team will review the SLAP computer program and the associated procedure

for controlling loads connected to the affected buses. Additionally, the team

will review the Harris Plant Engineering Section procedure for analyzing bus

loading.

D5.4-2 (Deficiency) Motor Operated Valve Thermal Overload Settings

The generation of a new procedure for selection of safety-related motor

operated valve thermal overload settings is considered an acceptable solution

- -

-

-

-

-

.

'

.

.

,

.

a

to the procedural error. However, it is still the intent of the licensee to

have the start-up group select the overload heaters.

.

The team will review the newly developed Harris Plant Engineering Section

design criteria relating to selection of overload heaters for intermittent

duty motors. The team will also review the start-up organization implementing

procedure.

D5.4-3 (Deficiency) Design Verification of Thermal Overload Settings

Revision of procedure 1/2-9000-E-01 to include an independent review of the

heater selection and verification of those overload heaters previously

selected is considered an acceptable solution. The new procedure

(1/2-9000-E-06) for motor driven valve operators will be reviewed as part of

,

the follow-up for deficiency 05.4-2.

05.4-4 (Deficiency) Station Service Transformer Protective Relaying

The team will review the revised relay settings and implementation of the load

control program.

US.4-5 (Unresolved Item) Procurement of Quality Components

The response to the this item does not contain sufficient information to

evaluate the adequacy of the verification process to be used to certify

terminal boxes purchased without a certificate of compliance. Additionally,

no response was provided concerning the substitution of " equivalent" terminal

boxes. The team requests that information be provided regarding how

equive'ency was detemined.

05.5-1 (Deficiency) Battery Sizing Calculations

The team will review calculations 56-JRG and 57-JRG which have superseded

calculation 52-AMM.

In so doing the team will confirm the revised inputs

used in the calculation and verify that the first minute discharge is now the

,

critical period for sizing the Shearon Harris batteries.

05.5-2 (Defic.iency) DC Equipment Rated Maximum Voltage

This deficiency identified the fact that the licensee had not confirmed the

qualified operating voltage range for de equipment.

In the response, the

Itcensee stated 3 possibilities that they would pursue to detemine the rated

maximum voltage for the safety-related de equipment. The response stated that

the primary method you planned to be used to verify the capability of the de

equipment to operate at maximum voltage will be a comparison of vendor data

with the requirements of the specification. The team is concerned that many

of the specifications for the equipment in question did not specify the

maximum de voltage range.

. - . - -

-

.'

.'

.

.

.

-

.

The team also questions how the second and third alternative will address the

over voltage concerns.

The team will review implementation of the resolution to this deficiency,

particularly the details of alternatives 2 and 3.

D5.5-3 (Deficiency) Battery Discharge Voltage Profile

The team will review calculation No. 20-WRE, which has superseded calculation

No. 43-SKD, to evaluate the revised voltage profile.

05.5-4 (Deficiency) DC System Minimum Voltage

The team will review calculation No. 20-WRE, which has also superseded

calculation No. 44-SKD, to evaluate the base voltages used in the close and

trip circuit voltage drop calculations and the resulting circuit restrictions

on cable size and length.

i

g

05.6-1(Deficiency)PenetrationProtectionQualification

3

The team will review the revised control wiring diagrams associated with this

change to confim the independence between the primary and backup protection

for these penetrations.

DS.7-1 (Deficiency) Use of Motor Data in Setting Procedure

'

'

The team is concerned that the work has proceeded with the Harris Plant

Engineering Section guideline for relay protection not being completed. The

team will review the revised relay setting calculations and coordination

curves as well as Harris Plant Engineering Section guideline No. 7.5.G for

relay protection. The team will examine how these calculations and curves

will be verified and when the guideline will be completed.

-

D5.7-2 (Deficiency) 480 V Bus Undervoltage Alarm

.

The team will review the revised relay setting drawings, the supporting

voltage study and relay setting calculations. The team will also review your

justification for setting the bus undervoltage relays below the minimum rated

,

'

motor voltage.

05.8-1 (Deficiency) DC Motor Operated Valve Voltage Drop

The team will review your cable sizing criteria for de motor operated valves

and the resulting voltage drop calculations or analysis supporting the

selection of the revised cable sizes.

1

05.9-1 (Deficiency) Reactor Vessel Level Instrumentation System RCP Input

The team will review the revised control wiring diagram CAR-2166-B-401 sheet

140 and Design Change Notice 251-257 to confirm the degree of independence

added between the RCP status inputs to each RVLIS train.

- -

-

-

-

.'

.

.

.

05.10-1 (Deficiency) Site Engineering Design Change Control

The team will review the calculation prepared for sizing the new cables for

the auxiliary transfer panels, and the new design guideline for control and

verification of cable and circuit breaker sizing.

INSTRUMENTATION AND CONTROL

D6.1-2 (Deficiency) FSAR/ Instrument Index Consistency

The team identified a number of differences between statements in the FSAR and

data provided in the EBASCO Instrument Index.

With regard to the specific

items noted by the team, this deficiency is considered to be closed; however,

,

the team will examine the recently revised EBASCO E-65-SH procedure mentioned

in the response with respect to applicable standards and codes used for

equipment procurement.

06.1-6 (Observation) CVCS Design Basis

During the review of an EBASCO Design Basis Document for the chemical and

volume control system, the team observed a classification difference for the

Chiller Surge Tank level transmitter between design documents and the Design

Basis Documents which exist for this system. The response stated that the

particular document reviewed by the team was not the appropriate one for this

transmitter. The team will review Design Basis Document 0B0-108 for the boron

thermal regenerative portion of the chemical and volume control system.

D6.1-9 (Deficiency) EBASCO Procurement Specification

Numerous differences were noted by the team in the specification of industry

standards and codes between EBASCO instrumentation procurement specifications

and the EBASCO E-65-SH procedure used as an input document for procurement

specification preparation, reviei<, and approval. EBASCO has indicated

technical differences of opinion with the team on which standards are

required, and has stated that some procurement specifications reflected

.

over-conservative cross-referencing. The team agrees with each of these

EBASCO comments, particularly since EBASCO has not attempted to impose system

level considerations on some vendors.

In the interim, EBASCO has revised

1

procedure E-65-SH to reflect those codes, standards, and NRC Regulatory Guides

listed as requirements in the instrumentation specifications. The team plans

to review this revised procedure.

06.1-10(Deficiency)IncompleteandUnissuedDraftingManual

At the Shearon Harris site, the team noted that issued instrumentation and

control drawings were being modified without a Drafting Manual for the

1

..

.

..

.

._

_ ______

-

.

.

'.

.

-

,

.

instrumentation and control discipline as required by ANSI h45.2.11-1974.

Carolina Power and Light has indicated that the manual has been prepared and

issued, and that an internal Quality Assurance audit indicated that only minor

changes were required to correct those drawing discrepancies noted. The team

will inspect review of the Drafting guide and the QA audit report.

D6.3-2 (Deficiency) Conduit Separation

During the inspection of main control room panels at the plant, the team noted

numerous instances of redundant flexible conduits that were in direct contact

with one another. IEEE Std. 384-1974 requires that, where cables are enclosed

within conduit panels, a one inch air gap separation distance be maintained

between the redundant conduits unless lesser distances are supported by an

analysis of the particular installation. At the time of the inspection.

Westinghouse had not perfonned such an analysis for their panels, and EBASCO

had permitted their panel vendor to follow the Westinghouse practice without

requiring an analysis by the vendor.

EBASCO has performed a separate engineering analysis on the basis of wire

size, control circuit fusing, voltage level separation, and control wiring

insulation characteristics. This separation analysis will be reviewed by the

team.

U6.3-3 (Unresolved Item) Instrument Impulse Line Separation Distance

l

The team believes that the Carolina Power and Light construction criteria for

instrument impulse lines may be technically acceptable; however,further

discussion and inspection are warranted regarding the basis for selection of a

minor change designation for this change. Review of the justification

analysis for FCR-I-1029, and review of a number of specific instrument tubing

reroute changes is planned.

D6.4-2 (Deficiency) Vendor Conformance to Specification

The team will review the complete analysis provided by the remote sample

'

dilution panel vendor to determine the acceptability of the installed hardware

l

for worst case environments.

1

U6.5-1 (Unresolved Item) Design Basis for Safety-Related Instrument Setpoints

j

The team remains concerned that design basis documentation will not be

provided for all safety-related balance-of-plant setpoints. During the

reinspection the team plans: (1) further discussions with Carolina Power and

Light regarding these balance-of-plant setpoints; (2) review of EBASCO

setpoint calculations for HVAC and other temperature measurements; (3) review

of EBASCO setpoint calculation EQS-19 for Emergency Service Water; (4) further

discussion with EBASCO regarding the RAB sump pump setpoint documentation; (5)

review of the Carolina Power and Light calculation for the Spent Fuel Pool;

and (6) review of the new Carolina Power and Light Harris Plant Engineering

Section Instruction 3.8.

_ _

_ _ _ _

r

'

.

.

.

D6.7-1 (Deficiency) Westinghouse Reactor Coolant Pump Instrumentation

The team noted that variations in instrument ranges existed for bypass flow

switches for the reactor coolant pumps. The response stated that Westinghouse

documentation has been revised, and that EBASCO documentation will be updated.

This deficiency will be followed-up by the team's review of the Westinghouse

specification sheet and the EBASCO Instrument Index.

D6.8-5 (Deficiency) Battery Room Service Sink

This item will be followed-up with the team's review of the change documents

for this particular material change.

D6.8-6 (Deficiency) Calculation Basis for Licensing Amendment

This deficiency will be followed-up with the team's review of this Carolina

Power and Light calculation and the revised Harris Plant Engineering Section

instruction.

Items Common to More Than One Discipline

The licensee's response to the findings which were common to more than one

discipline (IDI report section 7) have not yet been reviewed by the team. The

response to these items will be evaluated during the reinspection.

.

e

I