JAN 0 31985 ftEMORANDUM FOR:
H. Denton, NRR E. G. Case, NRR G. Edison, TOSB, NRR D. Eisenhut, DL F. Miraglia, DL T. Novak, DL H. Thompson, DHFS R. Vollmer, DE R. Bernero, DSI T. Speis, DST B. Snyder, TMIPO, NRR G. Holahan, ORAB D. Crutchfield, DL THRU:
A. Schwencer, Branch Chief Licensing Branch No. 2 Division of Licensing FRDM:
Robert E. Martin, Project Manager Licensing Branch No. 2 Division of Licensing
SUBJECT:
DAILY HIGHLIGHT Linerick With regard to the current suspension of construction of the Point Pleasant Diversion Project being built to supply supplemental cooling water for the Limerick facility, the licensee, Philadelphia Electric Company has informed the NRC Licensing staff that at midday January 3, 1985, Bucks County Court of Common Pleas Judge Garb ruled in favor the licensee and has ordered irmediate resumption of construction activities on this project.
'll a
Robert E. Martin, rojg.t Manager Licensing Branch t o. p Division of Licensing DISTRIBUTION Docket File (50-352/353)
LB2 Reading EHylton Rfiartin S. Black JLyons M
LB#2 LB#$
RMa rtin:dh
^'$chwencer 01/$/85 1/3 /85 SO)/00}ffU iP