MONTHYEARML20116L0221985-04-25025 April 1985 Informs That Revised Amend Request Re Shunt & Undervoltage Trip Attachment,Item 4.5.3 of Generic Ltr 83-28, Required Actions Based on Generic Implications of Salem ATWS Events, Will Be Submitted by 850531 Project stage: Other ML20128Q2451985-05-29029 May 1985 Proposed Tech Specs,Revising Table 4.3.1 to Provide for Testing to Confirm Operability of Shunt & Undervoltage Trip Devices of CRD Trip Breakers Project stage: Other ML20128Q2241985-05-29029 May 1985 Application for Amend to License NPF-3,revising Tech Spec Table 4.3.1 to Provide for Testing to Confirm Operability of Shunt & Undervoltage Trip Devices of CRD Trip Breakers.Fee Paid Project stage: Request ML20138R4621985-11-0404 November 1985 Requests Rev to 850529 Application for Amend to License NPF-3,changing Tech Specs to Provide for Testing to Confirm Operability of Shunt & Undervoltage Trip Devices of CRD Trip Breakers.Revised Significant Hazards Consideration Required Project stage: Other ML20205P9541987-03-27027 March 1987 Proposed Tech Specs,Adding Silicon Controlled Rectifier to Functional Unit Lists for Table 3.3-1, Reactor Protection Sys Instrumentation & Table 4.3-1, Reactor Protection Sys Instrumentation Surveillance Requirements Project stage: Other ML20205P9421987-03-27027 March 1987 Application for Amend to License NPF-3,revising Tech Spec Tables 3.3-1 & 4.3-1 in Response to Generic Ltrs 83-28 & 85-10 Re Silicon Controlled Rectifier Relays & Reactor Protection Sys Instrumentation Project stage: Request ML20205P9121987-03-27027 March 1987 Forwards Application for Amend to License NPF-3,revising Tech Spec Tables 3.3-1 & 4.3-1 in Response to Generic Ltrs 83-28 & 85-10 Re Silicon Controlled Rectifier Relays & Reactor Protection Sys Instrumentation Project stage: Request ML20147H7121988-03-0202 March 1988 Safety Evaluation Supporting Amend 108 to License NPF-3 Project stage: Approval ML20245C8401989-04-20020 April 1989 Forwards Notice of Withdrawal of 840116 & 850329 Tech Spec Change Requests 111 & 134,respectively,to License DPR-72. Util Committed to Incorporate Proposed Changes in Tech Spec Improvement Program,Per Project stage: Withdrawal 1985-05-29
[Table View] |
Text
l TOLEDO h EDISON Docket No. 50-346 RICHARD P. CROUSE vc. mant License No. NPF-3
$3333, Serial No. 1150 April 25, 1985 Director of Nuclear Reactor Regulation Attention:
Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Licensing United States Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Stolz:
On February 14, 1985 Toledo Edison requested a verbal extension of our proposed submittal date for an amendment request concerning the shunt and undervoltage trip attachment (Item 4.5.3 of Generic Letter 83-28, " Required Action Based on Generic Implications of Salem-ATWS Event") to April 30, 1985. Verbal approval was granted to extend the due date by our Project Manager. During our internal approval process, the Company Nuclear Review Board rejected the proposed amendment request. This requires the proposed change to be revised and re-submitted for internal review and approval.
Toledo Edison will submit the amendment request for Item 4.5.3 of Generic Letter 83-28 by May 31, 1985 for the Davis-Besse Nuclear Power Station Unit No. 1.
Very truly yours.
RPC: GAB:lah cc: DTr 1 NRC Resident Inspector 8505030459 850425