ML20112F552

From kanterella
Jump to navigation Jump to search
Final Deficiency Rept,Item 176 Re Electric cables-hi Pot Test Failure.Initially Reported on 840619.Two Parallel Feeder Circuits W/Damaged Single Conductor 500 MCM Cables Replaced
ML20112F552
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 12/12/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-302 176, NUDOCS 8501150404
Download: ML20112F552 (4)


Text

. _ _ _ _

UtiNFC PISI A T L A.'. T A.

E Carolina Power & Light Company 8 <l D E C 17 #$+~l " -

P. O. Box 101, New Hill, N. C. 27562 December 12, 1984 Mr. James P. O'Reilly NRC-302 United States Nuclear Regulatory Commission Region 11 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30323 CAROLINA POWER & LIGHT COMPANY O-Q(6k SHEARON HARRIS NUCLEAR POWER PLANT 1986-900,000 KW - UNIT 1 ELECTRIC CABLES - HI-POT TEST FAILURE, ITEM 176

Dear Mr. O'Reilly:

Attached is our final report on the subject item which was deemed reportable per the provisions of 10CFR50.55(e) on June 19, 1984. With this report, Carolina Power & Light Company considers this matter closed.

If you have any questions regarding this matter, please do not hesitate to contact me.

Yours very truly, W

R. M. Parsons Project General Manager Completion Assurance Shearon Harris Nuclear Power Plant RMP/rt Attachment cca Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. R. C. DeYoung (NRC) hD OC 0

040 hh)

S PDR rt/9/1

t CAROLINA POWER & LIGHT COMPANY I'.

SHEARON HARRIS NUCLEAR POWER PLANT UNIT NO.1 FINAL REPORT ELECTRIC CABLES HI-POT-TEST FAILURE ITEM 176 DECEMBER 12,1984 REPORTABLE UNDER 10CFR50.55(e)

\\'

E

\\

s a

rt/9/3

~ -'

SUBJECT:

Shearon Harris Nuclear Power Plant, Unit No.1,10CFR50.55(e) reportable deficiency.

Single conductor power cables were

~

damaged during installation but not detected by inspection and testing.

ITEM: '

Single conductor 600V. power cable

? SUPPLIED BY:

The Kerite Company,49 Day Street, Seymour, Connecticut 06483

NATURE OF DEFICIENCY:

Cables ll755A-SB and 11755B-5B were installed in accordance with documented design requirements, site installation procedures, i

and accepted based on inspection procedures. However, due to a low initial megger reading in one of the phases in each of the two H

(2) three-single conductor 500 MCM parallel feeder circuits, the cables were, suspect and additional -testing, not required by procedures'or design documents, was' performed. As a result of additional high-potential testing, cable damage was detected in both circuits.

I DATE PROBLEM

~

' OCCURRED:

May 10,1984

DATE PROBLEM WAS REPORTED
:

On' June 19, 1984, CP&L (Mr. K. V. Hate') notified the NRC (Mr.

A.' Hardin) that this item was reportable per the provisions of 10CFR50.55(e).

SCOPE OFl PROBLEM:

The' scope of the problem, initially unknown, was found to be isolated to the two parallel feeder circuits,11755A-SB and 11755B-SB, in~which one of the three 1/C-300 MCM ~ cables in each circuit was damaged.

An; investigation:of the. two failed cables showed

_.that damage occurred at the same location in the raceway. We are confident the damage occurred during installation, but the exact cause could not be determined.

SAFETY

' IMPLICATION: -.

If undetected damage occurred to safety-related cables, failure could occurL resulting in^ a lossL of n power to safety-related -

equipment.

REASON-

~ DEFICIENCY 15 f

HP51tTATEET

' This is a reportable deficiency since the possibility existed that

' safety related power cables which have been installed, inspected, and accepted in accordance with design = requirements and site -

procedures could be damaged and fail when put in service.

1, I

._4'-

w -

,', 1.

,").'rt/9/4 X

+

a

[? ~ x.

j

. i CORRECTIVE -

ACTION:

The two (2) parallel feeder circuits in which one of the three-single conductor 500 MCM cables was found damaged were replaced. Both circuits were satisfactorily meggered and high-potential tested following installation.

An effort was made to identify safety related single conductor 500 MCM power cables installed as of May 22, 1984. Additional high-potential testing approved by Harris Plant Engineering p-r FCR-E-2573 was then performed on these cables and the results were satisfactory. In addition to 500 MCM power cable testing, other safety and non-safety single conductor power cables installed as of May 22, 1984 were randomly selected and subjected to high-potential testing to confirm cable jacket /insulatica integrity and were also found to be satisfactory.

%:'S

' PREVENTIVE' MEASURES:

. Cor:struction Work Procedure WP-209. General Meggering and Hi-Potting Procedure for Equipment and Cable was revised on August 23,1984 to incorporate a requirement that the Electrical Discipline Engineer be notified when installed cables exhibit low initial megger readings and/or when a difference of 300% or more in megger readings exists between conductors in a. cable.

The Electrical Discipline Engineer will be responsible for investigating the problem to determine the cause and

- provide an acceptable resolution.

Construction Work Procedure WP-210, installation and Termination of Safety Related Wire <ind Cable was also revised on August 23,1984 to incorporate that the Electrical Discipline Engineer, Electrical Superintendent, or Construction Inspector may request a megger or a

. high-potential test before cable removal from a reel to insure cable

integrity prior to pulling.

4

)

s

'l t

rt/9/5?

w

.