MONTHYEARML24165A0842024-06-13013 June 2024 NEI White Papers Supporting NRC Workshop Discussions Regarding Nuclear Regulatory Commissions (NRC) Potential Changes to Regulatory Guide 1.183 ML24114A0252024-04-0808 April 2024 Comment (4) of Charlotte Shields on DG-5080 Uas Question ML24095A3522024-04-0404 April 2024 Email Transmittal 4-4-2024 NEI Responses to the NRC Staff Comments on NEI 99-01, Revision 7 ML23270B8992023-09-27027 September 2023 Email NEI Request for an Extension of Comment Period on Proposed Revision to Standard Review Plan Section 15.0, Introduction - Transient and Accident Analyses, Docket Id NRC 2023 0079 ML23229A1202023-08-17017 August 2023 NRR E-mail Capture - Information Email Capture of Advanced Reactor Content of Application Project and Technology Inclusive Content of Application Project Guidance Document Comments ML23214A2532023-08-0101 August 2023 (Nei), Request for Review and Endorsement of NEI 99-04, Rev. 1, Guideline for Managing NRC Commitment Changes ML23171A0212023-06-16016 June 2023 NRR E-mail Capture - (External_Sender) Request for an Extension of Comment Period on Draft Interim Staff Guidance Review of Risk-Informed, Technology Inclusive Advanced Reactor Applications - Roadmap, Docket Id NRC-2022-0074 ML23153A1262023-06-0101 June 2023 NRR E-mail Capture - (External_Sender) Re Industry Discussion Topics for Arcapticap Discussion in June 7th 2023 Meeting ML23110A6772023-04-18018 April 2023 Email-Fee Exemption Request for Review and Endorsement of NEI 23-03 ML23110A6782023-04-18018 April 2023 Request for Review and Endorsement of NEI 23-03, Supplemental Guidance for Application of 10 CFR 50.59 to Digital Modifications at Non-Power Production or Utilization Facilities ML23138A1542023-03-24024 March 2023 Transmittal of NEI 22-05, Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML22349A6582022-12-14014 December 2022 NEI Responses to NRC Comments on Draft NEI 99-01, Revision 7, Developments of EALs for Non-Passive Reactors ML22349A1012022-12-12012 December 2022 LTR-22-0343 Ellen Ginsberg, Sr. Vice President, General Counsel and Secretary, Nuclear Energy Institute, Expresses Concerns Related to Issuance of Regulatory Issue Summary 2022-02; Operational Leakage ML22019A2912022-01-12012 January 2022 (External-Sender) Submittal of Proposed Revisions to Aging Management Programs XI.M33, Selective Leaching and XI.E3 ML21270A1322021-09-24024 September 2021 Transmittal Email (External Sender - NEI) NEI 17-06 - NEI Response to NRC Comments ML21263A0102021-09-17017 September 2021 Proposed Rule: Advanced Reactor Security - Email from NEI (D. Young) ML for Previous Comments on Topics Discussed and 2 Comments from Public Meeting on 9/17/2021 ML21236A2032021-08-24024 August 2021 NRC Comments on NPUF Guidance 2021 Draft Without NPUF Rule.Docx ML21236A0882021-08-23023 August 2021 Email-Request for Review and Endorsement of NEI 21-06 Guidelines for 10 CFR 50.59 Implementation at Non-Power Production or Utilization Facilities.Msg ML21257A2352021-08-19019 August 2021 Rulemaking: Proposed Rule: Advanced Reactor Physical Security, Email Exchange Between Nrc and NEI Draft Pages from NEI-20-05 Rev. E ML21223A1992021-08-0909 August 2021 Email to NRC - Rroar Discussion Items ML21208A1752021-07-26026 July 2021 Email from Bill Gross NEI, Associated with the White Paper Development of Adversary Timelines (Withheld Under 2.390) ML21161A0272021-05-31031 May 2021 NEI Industry Feedback on RG 1.183 5-31-2021 ML21153A1352021-05-26026 May 2021 Comments on NRC Proposal for TSTF-505 and PRA Methods - 05/26/2021 ML21175A0502021-05-20020 May 2021 Rulemaking: Proposed Rule: Advanced Reactor Physical Security, Email from D. Young, NEI to D. Andrukat, NRC Discussion of NEI 20-05 Target Set Term ML21137A0572021-05-14014 May 2021 Rulemaking: Proposed Rule: Advanced Reactor Physical Security-Email from Young to Andrukat, May 2021 Draft D of NEI 20-05 Methodological Approach and Considerations for a Tech Analy to Demonstrate Compliance with the Eligibility Criteria of ML21138A8872021-05-0707 May 2021 5_7 Email Transmittal for Fee Waiver Request for NEI 99-01 Rev 7 ML21120A0562021-04-29029 April 2021 NRR E-mail Capture - (External_Sender) Issuance of NEI 21-01: Industry Guidance to Support Implementation of Nrc'S Risk-Informed Process for Evaluations ML21175A0362021-04-21021 April 2021 Rulemaking: Proposed Rule: Advanced Reactor Physical Security Email from D. Young, NEI to N. Valliere, D Andrukat, S. Helton, P. Lee, NRC Summary Table Showing Key Attributes for Eligibility Criteria ML21175A0352021-04-15015 April 2021 Rulemaking: Proposed Rule: Advanced Reactor Physical Security, Email from D. Young, NEI to D. Andrukat, NRC Follow-up Questions on NRC Response to NEI Question Concerning Proposed Eligibility Criterion 10 CFR 73.55(a)(7)(i)(A) ML21175A0432021-03-22022 March 2021 Rulemaking: Proposed Rule: Advanced Reactor Physical Security, Email from D. Young, NEI to D. Andrukat, NRC Question on the Term Unmitigated as Used in Proposed Eligibility Criterion 10 CFR 73.55(a)(7)(i)(A) ML21085A0262021-03-22022 March 2021 NRR E-mail Capture - NEI Draft Industry Guidance to Support Implementation of Nrc'S Risk-Informed Process for Evaluations ML21006A3082020-12-21021 December 2020 Comments on Draft IMC-0335 ML20342A1702020-11-23023 November 2020 NEI Input on NRC Annual Fee Assessment for Non-Light Water Reactors ML20288A4992020-09-14014 September 2020 Additional Supporting Information for the Review of FAQ 20-03 ML20259C5882020-09-11011 September 2020 NEI 14-05A R1 NEI Transmittal Response 9-11 to July NRC RAIs (e-mail) ML21050A0902020-08-31031 August 2020 Staff Detailed Comments - NEI 20_07 Draft Revision B -February 2021 ML20351A2182020-08-31031 August 2020 NEI 20-07 Guidance for Addressing Software Ccf_Kscarola ML20245E5612020-08-31031 August 2020 Guidance for Addressing Software Common Cause Failure in High Safety-Significant Safety Related Digital I&C Systems ML20177A4952020-06-23023 June 2020 NEI Comments on BTP 7-19, Revision 8 Submitted June 23, 2020 ML20154K5542020-05-28028 May 2020 Email and Letter from Rmccullum: NEI Comments on Spent Fuel Reprocessing Rulemaking ML20142A2842020-05-21021 May 2020 NEI Initial Comments on RG 1.187 Rev 2 Prior to ACRS Meeting on May 20, 2020 (Email) ML20143A0292020-05-21021 May 2020 NEI Suggested Edits to RG 1.187 (Email) ML20142A2892020-05-19019 May 2020 Additional NEI Comments on RG 1.187 Rev 2 Prior to ACRS Meeting on May 20, 2020 (E-Mail) ML20135H2092020-05-13013 May 2020 5_13 Email of NEI Submittal of Response to RAI NEI 14-05A, Revision 1 ML20107D8942020-04-13013 April 2020 Email from D. Young Draft B of NEI 20-05, Methodological Approach and Considerations for a Security Assessment to Demonstrate Compliance with the Performance Criteria of 10 CFR 73.55(TBD) ML20104A3082020-04-10010 April 2020 NEI Email, Dated April 10, 2020, Draft a of NEI 20-05 ML20107G8142020-04-0606 April 2020 Email from Nuclear Energy Institute (NEI) to NRC Transmitting NEI Comments on Draft Temporary Instruction 2514/194 ML20049A0182020-02-14014 February 2020 Email - SBT Definition and Submittal Issue ML20043F4782020-02-11011 February 2020 02112020 Nuclear Energy Institute Email Draft COM-106 Review ML20043F4772020-02-11011 February 2020 NRC Acknowledgement E-mail to Nuclear Energy Institute 02112020 E-mail Draft COM-106 Review 2024-06-13
[Table view] |
Text
From: TSCHILTZ, Michael To: Fetter, Allen Cc: NICHOL, Marcus
Subject:
[External_Sender] Part 52/50 Lesson Learned Rulemaking Date: Monday, February 03, 2020 11:46:05 AM Allen, Hope all is well with you.
I am hoping to get some clarification on the areas where it was unclear how certain issues suggested by the industry to be included in the rulemaking have been dispositioned.
- 1. Overall schedule for the Part 50/52 rulemaking - the industry would benefit from accelerating the schedule for the rulemaking. The current schedule for the rule leaves little time between the completion of this rule and the creation of a technology-inclusive regulatory framework by 2027 as required by Nuclear Energy Innovation and Modernization Act. Has the staff considered accelerating the rulemaking?
- 2. Transformational Changes - the staff has characterized certain changes in the proposed rulemaking as transformational, such as aligning the change process for DCs with the 10 CFR 50.59 process, adding definitions of Tier 1, Tier 2 and Tier 2* information, and consideration of reducing requirements for standardization for certified designs. There has been little to no dialogue on the nature of these changes with the public. Can the NRC make additional information public on what is being developed for the draft regulatory basis?
- 3. Changes during Construction - the industry has put significant effort into making the case for the need to be able to make changes to the licensing basis of a facility during construction without the need for preapproval from the staff. Previously the industry had been informed that the staff had determined that this issue would require rulemaking to address but at the November 21st meeting the staff noted that they were proceeding with a draft regulatory guide to address this issue and that is was not included in the rulemaking. This remains a significant issue to be resolved and public interaction is needed to ensure this issue is addressed in a thorough and comprehensive manner that doesnt create undue burden without any benefit to public health and safety. It would be beneficial to have a public meeting on the Draft Regulatory Guide to gain a better understanding of the proposed changes before the DG is published for public comment.
- 4. Delays in issuance of COLs due to errors in certified design - the industry has had several public meetings and there has been several rounds of correspondence in an attempt to propose viable solutions to this issue to prevent recurrence in the issuance of future COLs. The last correspondence from the NRC on May 10, 2019 indicated that this issue would be considered in the rulemaking. It would be beneficial for the staff to provide additional information on how this issue is being addressed.
- 5. Consideration of Vogtle 3 and 4 license amendments in determining the scope of the rule changes - during the meeting the industry questioned the staff if they were incorporating lessons learned from Vogtle 3 and 4 into the rulemaking. As a part of that effort all license amendments would need to be reviewed to determine if there were issues that could have been avoided through changes/ clarifications to the regulations. NRC indicated that they had considered lessons learned but were unable to provide any details about issues had been included in the rulemaking effort and the screening of other issues. The staffs work on these issues have not been transparent and have lacked public involvement. It would be helpful if the staff could indicate how
each of these issues were considered and why they are or are not being included in the rulemaking.
- 6. Defining the term essentially complete design - developing an accepted definition for the term essentially complete as described in 10 CFR 52.41 has significant ramifications for future applicants and the level of design detail needed to submit design certification application. There should be more public interaction in developing such a definition.
Please let me know if you would like to discuss how to address these concerns.
Best.
Mike Tschiltz Nuclear Energy Institute 1201 F Street NW, Suite 1100 Washington, DC 20004 www.nei.org M: 202.471.0277 E: mdt@nei.org This electronic message transmission contains information from the Nuclear Energy Institute, Inc. The information is intended solely for the use of the addressee and its use by any other person is not authorized. If you are not the intended recipient, you have received this communication in error, and any review, use, disclosure, copying or distribution of the contents of this communication is strictly prohibited. If you have received this electronic transmission in error, please notify the sender immediately by telephone or by electronic mail and permanently delete the original message. IRS Circular 230 disclosure: To ensure compliance with requirements imposed by the IRS and other taxing authorities, we inform you that any tax advice contained in this communication (including any attachments) is not intended or written to be used, and cannot be used, for the purpose of (i) avoiding penalties that may be imposed on any taxpayer or (ii) promoting, marketing or recommending to another party any transaction or matter addressed herein.