Part 21 & Interim Deficiency Rept,Item 204 Re Binding Mechanical Interlocks on Two Speed Starters Supplied by Gould,Inc.Initially Reported on 850122.Interlock Actuation Will Be Reworked.Final Rept by 850415
ML20108F206
Person / Time
Site: Harris 
Issue date: 02/21/1985
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-325, REF-PT21-85, REF-PT21-85-184-000 204, PT21-85-184, PT21-85-184-000, NUDOCS 8503120361
Download: ML20108F206 (4)


Text

  • h.,

s CP&L Carolina Power & Light Company

~

0 m=_

m

)

P.h. bx [hl, Od.*H515NC 27562 9

February 21,1985 Dr. 3. Nelson Grace NRC-325 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30323 CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT 1986 - 900,000 KW - UNIT 1 MOTOR STARTER-MECHANICAL VERTICAL INTERLOCK BINDING, ITEM 204

Dear Dr. Grace:

Attached is an interim report on the subject item which was deemed reportable per the provisions of 10CFR50.55(e) and 10CFR, Part 21 on January 22, 1985. CP&L is pursuing this matter, and it is currently projected that corrective action and submission of the final report will be accomplished by April 15,1985.

Thank you for your consideration in this matter.

Yours very truly, spy)

== cv D R. M. Parsons Project General Manager Completion Assurance Shearon Harris Nuclear Power Plant RMP/sae cc:

Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. R. C. DeYoung (NRC) 85031%@h$$0$$400 PDR PDR S

DFFICIAL COPt se7/1 M

\\\\

t a

'u,.

i 1

i 4

CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT i

f i

UNIT 1 i

4 INTERIM REPORT l

MECHANICAL INTERLOCK BINDING i

NEMA 5/2 SPEED - 1 WINDING STARTER t

I ITEM 204 i

i

}

4 FEBRUARY 20, 1985 i

I i

i

[

REPORTABLE UNDER 10CFR 50.55(e) and 10CFR 21 1

i 4

1 i

o i

WKAB01 l- -.....

v

SUBJECT:

Shearon Harris Nuclear Power Plant Unit No. 1 10CFR50.55(e) and 10CFR Part 21 Reportable deficiency involves binding mechanical interlocks on two speed starters which prevent low speed operation of fan coolers.

ITEM:

480 V NEMA 5/2 speed - I winding starter SUPPLIED BY:

Gould Inc., Westminster, Maryland NATURE OF DEFICIENCY:

Due to variations in tolerance, the vertical interlock installed between the tie contactor and the corresponding starter binds, preventing the full transfer between high and low speed.

DATE PROBLEM IDENTIFIED:

Shearon Harris received vendor notification of a potential problem January 7, 1985. HPES verified that this binding problem existed at Shearon Harris and evaluated this item as reportable.

DATE PROBLEM REPORTED:

On January 22, 1985, CP&L (Mr. N. J. Chiangi) notified the NRC (Mr. A. Hardin) that the item was reportable per the provisions of 10CFR 50.55(e) and 10CFR Part 21.

SCOPE OF PROBLEM:

The problem could occur in any of eight identical safety-related starters supplied by Gould Inc. under Ebasco Purchase Order NY-435143.

SAFETY IMPLICATIONS: When the interlock binds, the associated motor cannot change speeds.

In an attempt to go from high speed to low speed, this perturbation would prevent operation of the motor, as the low speed contactor would be prevented from closing. This would prevent the motors from performing their safety function of driving fan cooler units that are needed te provide de-humidification and air mixing of the containment atmosphere.

REASON DEFICIENCIES ARE REPORTABLE:

The deficiencies are reportable because the inoperable fan coolers could lead to hydrogen pocket formation in the containment. This compromises safety systems and adversely reduces the degree of protection to public health.

WKAB01

i

.. - s 1 8'.,

+

f T,

CORRECTIVE ACTION:

A vendor representative was dispatched to SHNPP to rework the interlock actuator to an improved design developed by Gould Inc.

FINAL REPORT: 'The corrective action and verification process a

required to resolve this item is expected to be completed prior to April 15, 1985. Therefore, it is projected that the final report will be issued at that time.