Part 21 & Third Supplemental Final Deficiency Rept Re Bonnet Studs Improperly Torqued on DHR Valves.Initially Reported on 811222.Work on Studs for One Valve Will Be Completed by 841231
ML20108C582
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 09/25/1984
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
REF-PT21-85-036-000 PT21-85-036-000, PT21-85-36, NUDOCS 8411160627
Download: ML20108C582 (1)


Text

_

TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 374ot 400 Chestnut Street Tower II September 25, 1984 jq g g P/,. g BLRD-50-438/82-04 BLRD-50-439/82-04 U.S. Nuclear Regulatory Commission Region II

-Attn:

Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

Dear Mr. O'Reilly:

BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - BONNET STUDS IMPROPERLY TORQUED ON DECAY HEAT REMOVAL VALVES - BLRD-50-438/82-04, BLRD-50-439/82 THIRD SUPPLE E NTAL' REPORT The subject deficiency was initially reported to NRC-0IE Inspector R. V. Crlenjak on December 22, 1981 in accordance with 10 CFR 50.55(e) *as NCR 1686. This was followed by our interim reports dated January 20, April 15, June 28, August 24, and November 1, 1982 and January 10, 1983, our final report dated April 13, 1983 and our supplemental reports dated December 22, 1983 and February 1, 1984. Below is our third supplemental report. We consider 10 CFR Part 21 applicable to this deficiency.

As discussed with NRC-0IE Inspector S. Weise on September 13, 1984, the date of September 15, 1984 for completion of corrective actions indicated in our final report on this matter would not be met. All bonnet studs have i

been torqued, but studs for one valve were inadvertratly overtorqued necescitating the procurement of additional material to redo the work. The corrective action on this matter will be completed by December 31, 1984.

If you have any questions concerning this matter, please get in touch with i

R. H. Shell at FTS 858-2688.

Very truly yours, TENNESSEE VALLEY AUTHORITY p s W-hfLL, M. Mills, Manager i

Nuclear Licensing oc:

Mr. Richard C. DeYoung, Director Office of Inspection and Enforcement

)

U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Records Center 4

Institute of Nuclear Power Opemtions 1100 circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 gigg7Jg OFFiCTAt l,Ory An Equal Opportunity Empl,er

[