Advises That Containment Spray Sys & Reactor Bldg Closed CWS Mods Will Be Completed During Present Outage,Per 841026 Response to Insp Rept 50-219/81-08.Svc Water Sys Mod Deferred to Following Outage
ML20108B662
Person / Time
Site: Oyster Creek
Issue date: 11/14/1983
From: Fiedler P
GENERAL PUBLIC UTILITIES CORP.
To: Martin T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8411160137
Download: ML20108B662 (2)


Text

--

s GPU Nuclear Corporation PU luclear la;'g8r3SS Forked River, New Jersey 08731-0388 609 971 4000 Wnter's Direct Dial Number.

Novmber 14, 1983 Thomas T. Martin, Director Division of Engineering and Technical Programs Region I U.S. Nuclear Regulatory Comission 631 Park Avenue King of Prussia, PA 19406

Dear Mr. Martin:

Subject:

Oyster Creek Nuclear Generating Station Docket No. 50-219 IE Inspection 50-219/81-08

References:

1.

IE Inspection 50-219/81-08 Dated September 24, 1981, from R.R. Keimig to Philip R. Clark 2.

Response to IE Inspection 50-219/

81-08, dated October 26, 1981 from Philip R.

Clark to R.R. Keimig 3.

IE Inspection 50-219/81-08, dated January 7, 1982 from Thomas T. Martin to Philip R. Clark In our response to IE Inspection 50-219/81-03 (reference 2), we committed to modify the Reactor Building Closed Cooling Water (RBCCW) system, the Service Water System (SW), and the Containment Spray System (CS) in order to comply with the inservice test requirements of 10 CPR 50.55 a (g)(4) and Section XI of the ASME B&PV Code, subarticle IWP-3100. Reference 3 acknowledged our ccxrmitment to complete the modifications during our cycle 10 refueling / maintenance outage.

[

'Ihe specific modifications included the installation of flow measuring instrumentation on both the SW and RBCCW systems and pressure monitoring instrumentation on the inlet to the CS pumps. The CS and RBCCW modifications will be completed this outage. By this letter, we are deferring the SW modification to the following outage.

'Ihe execution of this project requires that the SW system be out of service for an extended period of time and alternate provisions for the 8411160137 G31114 PDR ADOCK 05000219 0

PDR GPU Nucle.it Corporabon is a subwhaty of the General Pubhc Uhhties Corponition a

~ ~ -

. ~ -

Thomas T. Martin, Director U.S. Nuclear Regulatory Connission November 14, 1983 Page 2 required cooling capabilities would be provided via the completion of two major modifications which are titled "RBCCW System Upgrade" and " Alternate Decay Heat Removal".

In light of the extensive outage workscope, both modifications have been deferred to the following outage. Because all three modifications constitute an integrated project, it is not cost effective to pursue the SW modification at this time.

If there are any questions, please contact Mr. Michael Laggart of my staff at (609) 971-4643.

Very truly yours, gs

~

Peter B. Fiedler Vice President and Director Oyster Creek PBF:ML: dam cc: Dr. Thomas E. Murley, Administrator Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 NRC Resident Inspector Oyster Creek Nuclear Generating Station Forked River,1U 08731 I