NPDES Noncompliance Notification:On 850121,vol of Condenser Cooling Water Being Taken in Reduced.On 850122,delta Temp Limiting Condition Exceeded.On 850125,level of Addl Tank to Turbine Bldg Excessively High
ML20107J590
Person / Time
Site: Oyster Creek
Issue date: 02/07/1985
From:
GENERAL PUBLIC UTILITIES CORP.
To:
Shared Package
ML20107J574 List:
References
NUDOCS 8502270589
Download: ML20107J590 (3)


Text

_ _

Initial Teleph:ne Date of Report Date: February 6,1985 Occurrence: January 21, 1985 4

REPORT OF NONCOMPLIANCE WITH CONDITIONS OF NJPDES PERMIT NO. NJ 000 5550 REPORT NUMBER 000 5550/85/01 1

IDENTIFICATION OF OCCURRENCE:

Noncompliance with item 9b(1)b, page 4 of the permit.

CAUSE OF NONCOMPLIANCE:

The circulating water discharge-intake temperature difference exceeded 23.00F.

DESCRIPTION OF NONCOMPLYING DISCHARGE:

As a result of severe icing and low water level at the intake structure, the volume of condenser cooling water being taken in was reduced. This condition, even with all circulating water pumps in operation, caused the 230F delta temperature limit to be exceeded from 0845 to 1030 hours0.0119 days <br />0.286 hours <br />0.0017 weeks <br />3.91915e-4 months <br />,1145 to 1245 hours0.0144 days <br />0.346 hours <br />0.00206 weeks <br />4.737225e-4 months <br />, and 1315 to 2245 hours0.026 days <br />0.624 hours <br />0.00371 weeks <br />8.542225e-4 months <br />. The maximum delta temperature recorded was 24.30F.

DURATION OF NONCOMPLIANCE:

Total time 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> 15 minutes.

CORRECTIVE ACTION TO REDUCE THE NONCOMPLYING DISCHARGE:

Upon identification of the noncompliance, station personnel worked throughout the day to try and clear the ice from the intake structure in an effort to prevent restriction of circulating water flow in order to bring the delta temperature within the permit limit.

CORRECTIVE ACTION TO PREVENT RECURRENCE:

N/A. As recognized by condition 15(3) of the permit circumstance beyond the control of the permittee may arise in which effluent limitations are exceeded as was the case with the severe icing and low water level at the intake structure.

8502270589 850219 PDR ADOCK 05000219 S PDR Date: February 7,1985

Initial Telcphone Date of l

Report Date: February 5,1985 Occurrence: January 22, 1985 REPORT OF NONCOMPLIANCE WITH CONDITIONS OF NJPDES PERMIT NO. NJ 000 5550 REPORT NUMBER 000 5550/85/02 IDENTIFICATION OF OCCURRENCE:

Noncompliance with item 9b(6)b, page 6 of the permit.

CAUSE OF NONCOMPLIANCE:

The discharge-intake temperature difference of the cooling water of the Augmented Offgas (A0G)-New Radwaste (NRW) System exceeded the permit limit of 270F. The temperature was 30.10F.

DESCRIPTION OF NONCOMPLYING DISCHARGE:

As a result of the heat load from the New Radwaste System, coupled with the availability of only one heat exchanger and one evaporator for operation, and with one heat exchanger out of service for maintenance conditions beyond the permittee's control prevailed; the delta temperature limiting condition was exceeded.

DURATION OF NONCOMPLIANCE:

The duration of the incident could not be determined.

CORRECTIVE ACTION:

As stated in our March 1,1984 letter, the major heat load on the A0G-NRW discharge is the New Radwaste System; and that there will be instances in which compliance with the 270F delta temperature would not be attainable.

Consequently, the station will operate the A0G-NRW System as efficiently as possible without causing damage to any of the system components.

Date: February 7,1985

-. - , - - , . . , - - - - . ~ . . - - ---,.y - - - - - -

--. -- . ,. , - . , , - . . , . . - - ._.,.-a,-. - ,-

Initial Telephon2 Date of R:p::rt Date: January 28, 1985 Occurrence: January 25, 1985 REPORT OF NONCOMPLIANCE WITH CONDITIONS OF NJPDES PERMIT NO. NJ 000 5550 REPORT NUMBER 000 5550/85/03 IDENTIFICATION OF OCCURRENCE:

Noncompliance with item 1, page 2 of the pemit.

CAUSE OF NONCOMPLIANCE:

The discharge of any pollutant not authorized by the pemit constitutes a violation of the tems and conditions of the pemit.

DESCRIPTION OF NONCOMPLYING DISCHARGE:

During a sampling procedure it was detennined that the level of the Turbine Building Closed Cooling Water Chemical Addition Tank was too high which would not allow the addition of new material to the tank. Consequently, fifteen (15) gallons of diluted Drewgard 4109 (Sodium borate) with a concentration of 176 ppm was inadvertently discharged to the discharge canal, instead of being pumped into the Turbine Building Closed Cooling Water System or to Radwaste per the norm. In this instance, drainage from the Chemical Addition Tank was emptied into the 1-5 sump which drains into the 30" header with the teminus of its discharge into the discharge canal.

DURATION OF NONCOMPLIANCE:

Unknown, however less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

CORRECTIVE ACTION TO REDUCE THE NONCOMPLYING DISCHARGE:

The discharge occurred before corrective action could be taken.

CORRECTIVE ACTION TO PREVENT RECURRENCE:

Valve V-29-1, which controls the drainage flow from the Chemical Addition Tank to the 1-5 sump, has been tagged to restrict use of the valve and cannot be operated without management authorization to do so.

Date: February 7,1985