Responds to NRC Re Violations Noted in Insp Rept 50-400/84-23.Corrective Actions:Memo Written to Inform Site Supervisors of Protecting Equipment During Const Phase
ML20106C533
Person / Time
Site: Harris 
Issue date: 09/07/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20106C465 List:
References
CON-NRC-259 NUDOCS 8410240217
Download: ML20106C533 (2)


Text

.

l

.p v

Cp&L Carogna P er & Light Company P. O. Box 101, New Hill, NC 27562 September 7, 1984

-Mr. James P. O'Reilly NRC-259 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, GA '30323

Dear Mr. O'Reilly:

In reference to your letter of August 9, 1984, referring to RII:

GFM/RLP 50-400/84-23-05, the attached is Carolina Power and Light Company's reply to the violation identified in Appendix A.

It is considered that the corrective action taken is satisfactory for resolution of the item.

Thank you for your consideration in this matter.

Yours very truly, W

AW R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/j ed Attachment cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. B. C. Buckley (NRC) l' 8410240217 840924 PDR ADOCK 05000400 G

PDR

.d.

[(:

e Attachment to CP&L Letter of Response to NRC Report RII:

GFM/RLP 50-400/84-23-05 Meported' Violation:

10CFR50.55(f)(1) requires CP&L to implement the quality assurance program described or referenced in the Preliminary Safety Analysis Report. Section 1.8.5.13 of the CP&L quality assurance program requires that measures be established to protect equipment during the construction phase. Contrary to the above, CP&L failed to require that electrical equipment be protected in that on July 13.'1984, rainwater was allowed to enter through the reactor auxiliary building roof into the high voltage switchgear room and into a safety class IE sequencer panel 1A-SA.

This is a~ Severity Level IV violation (Supplement II).

Denial or Admission and Reason for the Violation:

The violation is correct as stated.

A blockout on the roof (305 elevation) slab was being prepared for permanent sealing by concrete pour. A temporary seal was placed over the opening when work stopped for the day. Rainfall during the night caused water to seep over and through the temporary seal.

When the leak was reported to the night shift craft, they apparently worked on minor leaks in other areas by mistake.

Corrective Steps Taken and Results Achieved:

The blockout was permanently sealed.

The equipment, Sequencer Panel IA-SA, was not damaged and no corrective action was required.

Ccrrective Steps Taken to Avoid Further Noncompliance:

A memo has been written to inform site supervisors of the problem and to require'certain preventive measures which include not making any roof or exterior wall openings or to remove waterproofing from any existing openings without written approval. When any openings are approved, the operations shift foreman shall be notified also.

Procedure WP-106 (Maintenance / Protection of Permanent Plant Equipment) was revised to assign responsibility for protecting equipment after installed and to define steps required to ensure weatherproofing is maintained.

Date When Full Compliance Was Achieved:

Full compliance was achieved on August 24, 1984.