Responds to NRC Re Violations Noted in Insp Rept 50-400/84-23.Corrective Actions:Coatings Discipline Engineer Assumed Responsibility of Reviewing & Approving Certifications
ML20106C478
Person / Time
Site: Harris 
Issue date: 09/07/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20106C465 List:
References
CON-NRC-263 NUDOCS 8410240191
Download: ML20106C478 (3)


Text

...

st CD&L Carolina Power & Light Company P. O. Box 101, New Hill, NC 27562 September 7, 1984 r

i Mr. James P. O'Reilly NRC-263 i

United States Nuclear Regulatory Commission

- l Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, GA 30323'

Dear Mr. O'Reilly:

In reference to your letter of August 9, 1984, referring to RII:

GFM/RLP 50-400/84-23-02, the attached is Carolina Power and Light Company's reply to the violation identified in Appendix A.

It is considered that the corrective action taken is satisfactory for resolution of the item.

Thank you for your consideration in this matter.

Yours very truly,

'g f&

R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/j ed Attachment cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. B. C. Buckley (NRC) 0410240191 e409p4 DR ADOCK 05000400 PDR t

b

=

c e,

y -,

--w 7-y-,y eaw--e

.rw P

-w--

z, L..

y

.~

-Attachment to CP&L Letter of-Response to NRC Report RII:

GFM/RLP 50-400/84-23-02 Reported Violation:

10 CFR 2.201 requires the licensee to submit to the NRC a written

-reply to a Notice of Violation.. This reply shall include both corrective steps which will be.taken to avoid further violations and the date when full compliance'will be achieved.

Contrary to the above, your response to viole. tion 400/84-10-01,

' dated June 1, 1984, stated that'all painter certification records were reviewedEand updated as necessary. A review of'these certification recordsaon June 29, 1984, demonstrated that all painter certification records had not been reviewed and updated.

This is a Severity Level IV violation (Supplement VII).

Denial or Admission and Reason for the Violation:

2 The violation is admitted with the following clarification:

The violation report correctly describes the condition'of the painters certification records. The following discussion is offered a

inasmuch as there is a distinction between adequacy of records development (Violation 400/84-23-01) and absence of records in the QA vault (Violation 400/84-10-01).

The correction and preventive steps for violation 400/84-10-01 were taken with the understanding that the point of issue was that records known to exist were not in the QA vault.- Consequently, the missing painter certification records were retransmitted to QA records (correction of missing record); and refinement of 'the -

records transmittal process, plus instructions of cognizant-i personnel, was made (prevention of further loss of records). The action of checking and updating the painter certification records (referred to in the response to Violation 400/84-10-01) was-for the purpose of ensuring that the records in the discipline files were on file in the QA vault.

In summary, the actions taken and the response to violation

-400/84-10-01 were based upon our understanding of the violation, its cause, and the needed corrections and preventive actions.

Corrective Steps Taken and Resulte Achieved:

l The painters that are applying Service Level I coatings have undergone certification /re-certification to bring the records up-to-date and in compliance with procedure requirements. Copies of the records have been transmitted for filing in the QA vault.

=

e.

_2_

Corrective Steps Taken to Avoid Further Noncompliance:

To ensure that painter certification records are in compliance with' procedure requirements, the coatings discipline engineer now has the responsibi'ity of reviewing and approving the certifications.

Site procedureqJP-44 (Painter Certification) has been revised to provide for this action.

Date When Full Compliance Was Achieved:

Full compliance was achieved on September 7, 1984.

!