ML20101E405
| ML20101E405 | |
| Person / Time | |
|---|---|
| Site: | Farley |
| Issue date: | 05/31/1992 |
| From: | Hill R SOUTHERN NUCLEAR OPERATING CO. |
| To: | |
| Shared Package | |
| ML20101E395 | List: |
| References | |
| NUDOCS 9206230188 | |
| Download: ML20101E405 (8) | |
Text
._.
i JOSEPH M. FARIEY NUCLEAR PLANT UNIT 2 MARRATIVE
SUMMARY
OF OPERATIONS May,.1992 The cycle 8-9 refueling outage continued through the month of May.
Power operation began at 0652 on 5-12-92.
The generator was taken off line at 1050 on 5-14-92 to perform a turbine overspeed trip test. The unit returned to povet operation at 0211 on 5-15-92.
The reactor remained crit-leal during the test.
There vere sour reactor trips during the montn of May.
At 1331 on 5-12-92, with the up*'
in mode 1 operating at 12 percent power, the L
reactor tripped due to lov vater level in the 2C steam generator coincident with l.
a feedvater flow less than steam flov signal. The unit returned to power operation at 0822 on 5-14-92.
On 5-15-92 at 2004, while operating at 35 percent power the reactor tripped on a lc power range high flux signal due to control power fuses blowing and the subsequent loss of control pover to power range nuclear instruments NI-41 and NI-43.
The nnit returned to power operation at 1743 on 5-16-92.
.At 0545 on 5-25-92. While operating at 100% power the reactor was manually tripped due to the loss of 2A steam generator fecd pump (SGFP). The unit
. returned co pover operation at 0549 on 5-26-92.
At 1818 on 5-26-92, while operating at 45 percent power, a negative flux rate reactor trip occurred due to the de-energization of the rod centrol power cabinet IED stationary gripper coils. The unit was returned to power operation at 0132 on 5-28-92.
For the remainder of the month the unit was at approximately 58% power dus to tt:e monitoring of the 2A SGFP.
The tollowing major safety-selated maintenance vas performed during the month of Pays p
- 1. Rodded out and cleaned the service water side of 2A, 2B, 2C and 7D containment cooler.
l
- 1. Completed hydrotest of 2A and 2B contaiament spray system, i,
i L5
- 3. Performed various corrective and preventive maintenance on the post accident hydrogen analyzers.
l l
- 4. Replaced actuator cylindecs on various MSIVs.
- 5. Performed STP-608.1 " Main Steam Line Safety Valve Test" on the main f
steam line safety valves.
t-L 9206230188 920615
-(DR ADOCX 05000364 p
- g.,,
[-.
i'-
- 15. _ Performed various corrective. maintenance on the auxiliary feedvater -
pumps.
- 7. Performed corrective maintenance and testing on the containment y
purge dampers.
- 8. Inspected-various service vater pump discharge check valves.
I
- 9. Performed Local Leak Rate Testing (LLRT) on s the cor.tainment personnel and auxiliary hatches.
- 10. Miscellaneous corrective and preventive maintenance vas performed on the diesel generators.
f ;-.
{..
L i
(5 i
E l -.
l i
t l.
l l
l l,
.i.
>m+.
4 A
,m 4 9 OPERATING DATA REPORT DOCKET No. 50-364 DATE June 8, 1992 COMPLETED BY R. D. Hill TELEPHONE (205)899-5156 OPERATING ETATUS Notes
.1. Unit Name:
Joseph M. Farley - Unit 2
- 1) Cumulative data since
- 2. Reporting' Period
~~May 1997 7-30-81, date of 3.'Licenced Thermal Power (HWtJ:
2,652 commercial operation.
- 4. Nameplate Rating-(Gross MVe):
850
- 5. Design Electrical Rating (Net MVe):
829
- 6. _ Maximum Dependable Capacity :(Gross MWe):
864.3
'7.
Maximum Dependable Capacity (Net MVe):
824.0
- 8. It Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons: N/A 9 Power Level To Whi!E Restricted,-If Any (Net MVe):
N/A
~~
-10. Reasons For Restrictions, If Any:
N/A L
t This Month Yr-to-Date Cumulative
- 11. Hours In' Reporting Per'od 744.0 3,647.0 95,016.0 32..Numoer Of-Hours Rteactor Vas Critical 476.1 2,041.2 80,905.5
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 138.0
- 14. Hours Generator On-Line 346.9 1,893.0 79,821.5
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MVH) 513,303.9 4,579.532.2 203.538,853.8
- 17. Grass Electrical Energy Generated (MVH) 153,454.0 1,493,22176 66,789,306.0
- 18. Net Electrical Energy Generated (MUH) 128,290.0 1,393,444.0 63,327,506.0
- 19. Unit Service Factor 46.6 51.9 84.0 20.LUnit Availability Factor 46.6 51.9 84.0 L21._ Unit Capacity Factor (Using MDC Net) 20.9 46.4 81.3 22.; Unit-Capacity Factor (Using DER Net) 20.8 46.1 80.4
- 23. Unit Forced Outage Rate 25.'
7.6 4.2
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, E~nd Duration of Each):
N/A
~
- 25. If Shut Down At End Of Report Period, Estimated Date af Startup: N/A
- 26. Units In Test Status (Prior to Commercial Operation)
Forecast Achiev53' p
INITIAL CRITICALITY 05/06/81 05/08/81 INITIAL ELECTRICITY 05/24/81 05/25/81 COMMERCIAL OPERATION 08/01/81 07/30/81 l-Form 2/30 l
-? '
. DOCKET NO.
50-364 UNIT 2_
DATE June 8, 1992 COMPLETED BY R. D. Hill TELEPHONE (205)899-5156 MONTH' May1
-DAY AVERAGE DAILY POVER LEVEL DAY
' AVERAGE DAILY POVER LEVEL (MVe-Uet)
(MVe-Net)
-- 1 0
17 167 2
0-18 183 3
0 19 270 4:
0 20 359 5
0=
21 571
- 6-0 22 651
'7 0 _ _
23 761 8
0 24 805 9
0 25 168 10.;
O 26 54 11 0 --
27 0
12 0
28 296 13 O
29 449 14-9 30 440 15 83 31 448 16 0
INSTRUCTIONS On this format, list the average daily unit power level in MVe-Net for each-day in
--the reporting month. Compute to the nearest whole megawatt.
i<
I l
l.-
4
11 NIT SIRRTIMNS MD POWE2 REECITIONS DOCEET m.
l50-304 IIIIT NVIE J. M. FARIZT - tMIT 3 '
~
InTE.
June 8, 19D2 C[PG'IETED ST R. D. HILL REPORT M3fTH MAI TEIKFtmE (205)S99-5156 I
I i
1 1
InErmDor ~
l LICENSEE I I
I CwsE. amnCrIvE l
l l
l l mRmen l 2 l Smarrm l Ear i srs = l a n - tr l
Actron so 1
2 5
lm.
IimTE l Trre l ormS) lREAsen l com uAcroR 1 morr e I cDoE' :lcDoE l
rREvENr neuRect l
l003 l*20512 l 5 l 270.9 l
C l
1 l
N/A lN/A l N/A l h Cycle S-9 Refueling continued from 7-6-92.
l l
l l
l l
l l
l l
l Power operation began at 0652 >n 5-12-92.
l I
I I
I I
I I
I I
I i
l004 l920512 l T l
42.9 l
G l
3 l 92-005-40 l AB ' l N/A l At 1331 on 5-12-92, with the unit in sm>de 1 l
1 l
l l
l l
l l
l l
jeperating at 12 peront power, the reactor trigged l l
l l
l l
l l
l l
jdue te low water level in the 2C steam generator l
l l
l l
l l
l l
l l coincident with a feedwater flow less than steam l
l 1
l l
l l
l l
l lflowsignal. h low level in c.he steam generator l l
l l
l l
l l
l l
loccurredbec*weofaplanttransientinducedfroml l
l l
l l
l l
l l
la main generator trip that occurred at 1243 on l
l 1
I i
l i
l i
i 15-12-92.
l I
i l
i i
i l
i I
I I
l l
l l
l l
l l
l lThis event u caused by personnel er or in that l
8 l
l l
l l
l l
l lthe control room crew did not dampen J eam l
j l
l l
l l
l l
l l
l generator lent oscillations. A critique was l
l l
l l
l l
l l
l l con &cted with the Shift Supervisor and Plant l
l l
l l
l l
l l
l l Operator m drty at the time of the trip.
-l l
l l
l l
l l
l l
lOpertrors.
ta reir.structed e options availat-:=
l l
l l
l l
l l
l l
lwhen steam generator level cwitrol cannot be l
l l
l l
l l
l l
l lmaintainedinautomatic. The unit returned to l
l l
l l
l l
l l
l l power operation at 0822 on 5-14-92.
l I
I I
I I
I I
I I
i I
l095 l920514 l
5 l
6.4 l
B l
N/A N/A l N/A l
N/A lThegenerato? was taken off line for a turbine l
l l
l l
l l
l l
l loverspeed trip test. The reactor remained critica1l l
1 i
I i
I I
I l
larinsthetest.
l l
}
F: Forced Reason:
Method; Exhibit G-Instructions S Scheduled A-Equireent Failure (Explain) 1-Manual for Preparation of Data B-Maintenance er Test 2-E?snual Scras Entry Sheets for Licensee
?
C-Refueling 3-Automatic Scram.
Event Report (12R) File OPJREG-D.-Regulatory Restriction 4-Other (Explain) 0161)
E-Operator Training. License Examination F-Administrative Exhibit I -Same Source G-Operational Error (Explain)
( 9/'4 7 )
H-Other (Explain).
Page 1
a tmT Samown anD nowER REIcenms m:EET m.
So-r4 WIT NAME J. M. FARIKT - tMIT 2 mrE aune 8 Im2 C2TLETED BT R. D. FTIL REPORT MMIN MAY TE1ZPHOttE (2051899 5156 1
1 I
I i
i 1
I ne:mo or ir.IcEnsEr l l
l cauSE s muECnvE l
l l
l l DURATION l l SmTTIm lEVEP?r l SYSTEM l COMPONENT l
ACTIm to j
g co,4,coc,5
,,,,,,,cy,,,c, 3
Im.
l mrE I mE l(muRS) l rex:ca2 ;,,,,,y,,,3 2
l I
l 21.6 l
F l
3 l92-006-00l IG l
N/A Ls'n 5-15-92 at 2004, while operating at 35 percent l l006 l920515 l
?
l l
l l
l l
l j
l l power,thereactertrippedonapowerrangehigh l
l l
l l
l l
l l
l jflumsignalduetocontrolpowerfusesblowingandl l
l l
l j
l l
l l
lthe subsequent loss of control power to power range l A
l l
l l
l l
l l
l l
lnuclearinstrumentsNI-41andNI-43.
l l
l l
l l
l l
l l surveillance test procedure was in progress at the l
(
l l
l l
l l
j l
ltimeofthetripwithdigitalvoltmetersconnectedl l
l l
l l
l l
l l
lto all four pcwor range NI drawers. The use of l
l l
l l
l l
l l
l l unshielded leads on the digital voltmeters allowed l l
l l
l l
l l
l l
la 60 herts signal to be superimposed at thenormall l
l l
l l
l l
l l
lDCsignalfromthepowerrangedetectorsinthe l
l l
l l
l l
l l
l lNuclearInstrumentationSystem. Because the plant l l
l l
l l
l l
l l
lpowerlevel(35%)vssatapowerpermissive l
l l
l l
l l
l l
l lsetpoint, the superiaposed signal caused the l
l l
l l
l l
l j
j lbistablesiliconcontrolrectifiersto l
l l
l l
l l
l l
l jrapidlyturnonandoff. This cycling action l
l l
l l
l l
l l
lcausedincreasedcurrentthroughthecontrolpowerl l
l l
l l
l l
l l fuses of the power range NIs. The high current l
l l
l l
l l
l l
lcausedthecontrolpowerfusestobeatupand
[
l l
l l
l l
l l
l lsubseg.tently blow on NI-41 and NI-43.
The test l
l l
l l
l l
l l
l l procedure was revised to allow instrumentation to l l
l l
l l
l l
l l
lbe connected to only one powe range drawer at a l
l l
l l
l l
l l
l l time. Furtherere, the proce.12re was revised to l
Exhibit G-Instructio6 Method:
F: Forced Reason:
S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data 2-ttanual Scram.
Entry Sheet s for I.icensee 84%sintenance or Test 3-Autoastic S"rha.
Event Report (LER) File (NUREG-C-Refueling D-Regalatory Restriction 4-Other (Explain) 0161)
E~ operator Training & License Examination Exhibit I -Same Source F-Administrative G-operational Error (Explain)
(9/77)
H W.or (Explain)
Page 2
tsIT SHtmpetS AND POWE1. LEDGCTIONS-DCtIET m.
'50-364 tK2IT NAME J. M. FARIET - IN2T 2 IATE ' June 8, 1992 CEPTIJ.TED BY
' R. D. HIII REPCRT NTTE MAY TELEPHONE
'(205)S99-5156 I
I i
1
.I I nETH m or iLIcENSEE I' l
I c m sE s c= REcrIvE I
l l
l lIRJRATF*J l l SHtfTrING l EVENT l SYSTDI l LOMPONENT l
ACTI N TO
.l 1
3 i
5 Im.
l tate lrrpE 1 in0mS>
l Rrucu2 l cx3n REacwR lREroRTe l cIxm lcooE l
rREvENr REcuRREncZ 1
l 006 (con't) l
'l l
l l
l l
l require the use of shielded leads for connecting.l l
l l
l l
l l
l l
l test instrumentation to prevent irdaced voltages l
l l
l l
l l
l l
l lfromaffectingNISperformance. All control l
l j
l l
l l
l l
l lpo m r fuses for the four power range NIs were l
{
l l
l l
l l
l l
l l replaced. We unit returned to power operation at l 6
I i
i i
i i
i l
i 11743 on 5-16-92.
l l
l 1
1 I
I I
I i
l l 007 l920525 l
F' l
24.1 l
A l
2 l92-007-00l SL l
N/A lAt0545on5-25-92,whileoperatingat100 percent l l
l
.l l
l l
l l
l l power,thereactorwasmanuallytripped<ksetothel l
l l
l l
l l
l l
l loss of the 2A steam generator feed pump (SGFP).
l l
l l
l l
l l
l l
lThe2ASGFPtrippedduetolowautostopoil l
l l
l l
l l
j l
l l pressure. S e low auto stop oil pressure was l
l l
l l
l l
l l
l lcausedbydegradationofthelubeoilpumpsand l
l l
l l
l j
l l
l l excessive water in the lube oil system for the 2A l l
l l
l j
l l
l l
lSGFP. The 2A SGFP lube oil was drained dad the oil l l
l l
l j
l l
l l sung was c] wned. The lube oil pumps were l
l l
l l
l l
l l
l
!overhauledandreinstalled. Weunitwasreturnedl l
l l
l l
l l
l l
lto power operation et 0549 on 5-26-92.
l l
1 I
I I
I I
I I
l 008 l 920526 l
F l
31.2 l
G j
3 l92-003-00l AA l
N/A lAt1818on5-26-92,whileoperatingat45 pere.ent l l
l l
l l
l l
l l
l power, a negative fluz rate reactor trip occurred l l
l l
l l
l l
l l
ldue to the de-energization of the rod control power l i
l l
l l
l l
l l
l lcabinetIBDstationarygrippercoils. his event l l
l l
1 I
I I
I I
Iwu.:aused by per=-1 error in that the 1
l l
l l
l l
l l
-l l individual mistakenly opened the disconn ct which l l
l l
l l
l l
l l
lsuppliedpowertothe1BDstationarygrippercoils.l F: Forced Reason:
Method:
Exhibit G.-Instructious l
S: Scheduled A-Equipment Failure (Esplain) 1-Manual for Prvaratice of Data B-Maintenance or Teit 2-Manual Scram.
Entry Sheets for Licensee C-Refuelf r.!!
3-Automatic Scram.
Event Report (i.ER) File (NUREG-D-Regulatic' Restriction 4-Other (Explain) 0161)
E-Operator Training & License Examination F-Administrative Exhibit I -Same Source G-operational Error (Explain)
(9/77)
HHXher (Explain)
Page 3 i
a
m--,;
TNT 4 SHirfDOWits AND PMER REDUCTIONS DocxET too.
50-364 UNC NAfE J. M. FARLEY - TRIT 3 DATE
'.hnw 8, 199 2 N BY R. D. RIII REPORT MDerfH mar TEID904E (205)899-5156 s
i I
I I
1 I ME ve or i ucENsEE I I
cause a cDamEcrnE I
l-1 I
IcuaArrow I I swrrim iEmr-I SrSm I cama:rr i AcTuw To i
2 5
Im.
I mE I mE
- 1. (nwnSt I un,2 I a m arx zca' Iauere IceEe* I axz i
r Evorr mEcunaEn:E I
l008(c<.,n't) l l
l l
l l
l lTheindividualsirvolvedinthiseventhavebeen l
l l
l l
l l
l l
l
- l coached. Theunitwasreturnedtopoweroperationl l
l l
l l
l l
l l
lat 0132 on 5-2S-92.
l l
l l
l l
l l
l l
lror the renautder of the month the unit was at l
l l
l l
l l
l-l l
lapproximately58%powerduetothemonitoringof l
i 1
1 I
.I I
I I
I Ithe2ASGFP.
l l
l 1
I i
i 1
1 I
I I
I I
I I
I I
l I
i l
l I
I I
I l
1 l
I I
I I
I I
I I
I 1
1 1
1 I
i 1
.I I
I I
i i
l i
l 1
1 I
I I
I I
I i
i l
i i
i l
I 1
1 I
I I
I I
I I
I I
I I
i 1
I I
I I
i i
l I
i l
I i
i i
I i
l i
l I
I I
I I
I l-1 I
I I
I I
I I
I I
I i
I I
I I
I I
I I
I I
I I
i l
1 i
i i
i i
I I
i i
i I
I I
I I
I I
I I
I I
I l
I I
I I
I I
I I
i i
l I
I I
I I
I I
I I
I I
I i
i I
I I
I I
I I
I I
i l
I i
l i
l i
F: F;<ced Reason:
Method:
Ezhibit G-Instructions S: Scheduled A-Equipmer't Failure (Explain) 1-%nual for Preparation of Data S-Maintenance or Test 2-Manual Scram.
Entry sheets for 1.icense.
C-Refueling 3-Automatic Scram, Event Report (123t) File (NUREG-D-Regulatory Restriction 4-Other (Explain) 0161)
E-Operator Training & I.icense Examination F-Administrative Exhibit I -Same source G-Orsrational Error (Explain)
(9/77) ff4h her (Explain)
Page 4
..