ML20096F459

From kanterella
Jump to navigation Jump to search
Addendum to Final Deficiency Rept,Item 76 & Part 21 Rept Re Welding on 6.9 Kv Switchgear Supplied by Siemans Allis, Purchase Orders NY-435112 & 435113.Corrects Second Sentence in Paragraph 1 Under Corrective Action
ML20096F459
Person / Time
Site: Harris 
Issue date: 08/13/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-253, REF-PT21-84, REF-PT21-85-067-000 76, PT21-85-067-000, PT21-85-67, NUDOCS 8409100028
Download: ML20096F459 (2)


Text

..

. 7, CP&L Carolina Power & Lig pgn P. O. Box 101, New Hill, N. C. 27562 August 13,1984 Mr. James P. O'Reilly NRC-253 United States Nuclear Regulatory Commission Region II 101 '4arietta Street, Northwest (Suite 2900)

At' Anta, Georgia 30323 CAROLINA POWER & LIGHT COMPANY SIIEARON HARRIS NUCLEAR POWER PLANT 1986 - 900,000 KW - UNIT 1 WELDING ON 6.9 KV SWITCHGEAR PURCHASE ORDERS NY-435112 AND NY-435113, ITEM 76

Dear Mr. O'Reilly:

Attached is Addendum No. I to the Final 10CFR50.55(e) and 10CFR, Part 21 Report issued to the NRC on October 29,1982 for the above subject deficiency. This addendum clarifies our corrective action concerning site QA inspections.

If you have any questions regarding this matter, please contact me.

Yours very truly, flP7 MM R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/sh Attachment cc:

Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. R. C. DeYoung (NRC) 8409100028 840813 PDR ADOCK 05000400 4

S PDR OFFICIAL COPt' f674f,[,

5 C_

  • ~

SHEARON HARRIS NUCLEAR POWER PLANT UNIT 1 WELDING ON 6.9 KV SWITCHGEAR PURCHASE ORDERS NY-435112 AND NY-435113 ADDENDUM NO.1 TO FINAL REPORT -ITEM 76 ISSUED OCTOBER 29,1982 AUGUST 13,1984 Under Corrective Action, paragraph 1, the second sentence should be changed to read as follows:

Other equipment on site, supplied by Siemans Allis, will be inspected by Site QA.

i l

l