ML20093M783

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept (55(e)-84-38) Re Impact Test Data Not Recorded for Check Valves Supplied by Anchor Darling Valve Co.Initially Reported on 840907.Matter Still Under Investigation.Final Rept Will Be Submitted by 850121
ML20093M783
Person / Time
Site: Nine Mile Point 
Issue date: 10/09/1984
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
(55(E)-84-28), (NMP2L-0194), (NMP2L-194), NUDOCS 8410230284
Download: ML20093M783 (2)


Text

7....

_n5 NUMOHAWK Y NIAGARA NBAGARA MOHAWK POWER CORPORATION /300 ERIE BOULEVARD WEST, SYRACUSE. N.Y.13202/ TELEPHONE (315) 4741511 October 9, 1984 (NMP2L 0194)

S Mr. R. W.' St'arostecki, Director U. S. Nuclear Regulatory Comission i

. Region I Division:of Project and Resident Programs

'631 Park Avenue 4

f:

King of Prussia, PA 19406 i

L Re: Nine Mile Point - Unit 2 Docket No.-50-410 i

i

Dear Mr.'Starostecki:

Enclosed is an interim report, in accordance with 10CFR50.55(e), for the problem concerning the check valves. This problem was reported via tel-con to l

'S. Collins.of your staff on September 7,1984 1

Very truly yours, L

C. V. Mangan Vice President Nuclear Engineering and Licensing 1.

' CVM/GG/pbd xc: Director of Inspection and Enforcement U.S. Nuclear' Regulatory Commission

. Washington, DC 20555 R. A. Granei, NRC Resident Inspector-Project File (2)

B P

P S

1 gc. 27

GP P,

NIAGARA M0 HAWK POWER CORPORATION NINE MILE POINT - UNIT 2 DOCKET NO. 50-410 Interim Report for a Problem Concerning Check Valves (55(e)-84-38)

Description of the Problem The problem pertains to the check valves supplied by Anchor Darling Valve Company.

During a review of the certified material test reports it was discovered that impact test data was not recorded for various components (gasket retaining ring, seat ring, disc) of the subject valves.

The valves

-are located in various safety-related systems (feedwater, residual heat removal, low pressure core spray, high pressure core spray, and reactor core isolation cooling).

This condition has been documented on 'Nonconformance and Disposition Report hos. Z099 and Z100 The matter is still under investigation and a final report will be submitted by January 21, 1985.

..