Interim Deficiency & Part 21 Repts,Item 186 Re Inadequate Clearance at Sides of Siemens-Allis 6.9 Kv Circuit Breakers & Switchgear Cubicles.Initially Reported on 840907.Util Awaiting Siemens-Allis Response
ML20093M252
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 10/05/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-280, REF-PT21-84 186, 286, NUDOCS 8410220016
Download: ML20093M252 (1)


Text

q m.

.~

j CNLL I

Carolina Power & Light Company M7 0 7 P. O. Box 101, New Hill, NC 27562 October 5, 1984 Mr. James P. O'Reilly NRC-280

-United States Nuclear Regulatory Commission Region 11 101 Marietta Street, Northwest-(Suite 2900)

Atlanta, Georgia 30323 CAROLINA POWER & LIGHT COMPANY SHEARON HAARIS NUCLEAR POWER PLANT 1986 - 900,000 KW - UNIT 1 6.9 kV SWITCHGEAR CIRCUIT BREAKERS, ITEM 186

Dear Mr. O'Reilly:

On September 7, 1984, Mr. N. J. Chiangi notified the NRC (Mr. A. Hardin) of a potentially reportable item per the provisions of 10CFR50.55(e) and 10CFR, Part 21.

The NRC was informed that inadequate clearances at tne sides of Siemens-Allis 6.9 kV circuit breakers and switchgear cubicles had resulted in problems such as bent terminal lugs and chafed wiring.

CP&L is currently awaiting a response from Siemens-Allis on their review and recommendation for corrective action. We will complete our evaluation of this item upon receipt and review of Siemens-Allis' response.

It is projected that a report on the reportability of this item will be issued by November 30. 1984.

Thank you for your consideration in this matter.

Yours very truly, 1.

g R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant l