ML20093F087

From kanterella
Jump to navigation Jump to search
Forwards Responses to Request for Addl Info Re Unresolved Safety Issue A-46 Summary Rept, Per GL 87-02
ML20093F087
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 10/11/1995
From: Dennis Morey
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR GL-87-02, GL-87-2, NUDOCS 9510170277
Download: ML20093F087 (9)


Text

_

i Southern Nuclxr Operating Company Post Offica Box 1295 Birmingham. A11bama 33201 Telephone (205) 868-5131 f

Southern Nudear Operating Company o m uor.,

1 Vice President Farley Project the southem electnc system October 11, 1995 i

Docket No.:

50-348 N

U. S. Nuclear Regulatory Conunission ATTN: Document Control Desk Washington, D. C. 20555 Joseph M. Farley Nuclear Plant - Unit 1 Response to Request for Additional Information

" Unresolved Safety Issue A-46 Summary Report" Generie Letter 87-02 Ladies and Gentlemen:

By letter dated September 5,1995 the NRC requested additional information regardmg tie

" Unresolved Safety Issue A-46 Summary Report," prepared by Southern Nuclear Operating Company (SNC) in response to Generic Letter 87-02. The response to the NRC request is provided in Attachment I as Questions 1,2 and 3. In addition, tie NRC informally requested further information to be included in this submittal. This additional information is provided as the response to Questions 4 through 11.

If you have further questions, please advise.

Respectfully submitted, fR 77)4s!

u Dave Morey DPItmar A-46RAI. DOC I'

Attachments ce:

Mr. S. D. Ebneter Mr. B. L. Siegel Mr. T. M. Ross

$ !000.$

9510170277 951011 PDR ADOCK 05000348 8

P PDR.

l.

e J

f ATTACHMENT 1

  • l

\\

{

a e

l l

Question 1:

1 Section 2.6, " Plant Operations Department Review of Safe Shutdown Equipment List,"

refers to a memo from the plant operations manager (reference 13) which described operations conunents regarding the SSEL, all of which have been addressed. Please provide the staff with the referenced memo and a description of how each comment was addressed.

1 SNC Response A thorough review of the Units 1 and 2 Safe Shutdown Equipment List (SSEL) was performed by the Plant Farley operations department per section 3.7 of the Seismic Qualification Utility Group (SQUG) Generic Implementation Procedure (GIP). The results of the operations department review are documented in a memorandum from the Plant Farley operations manager, Mr. Phil Crone. A copy of this memo is provided as Attachment 2. This nanorandum concludes that, following incorporation of conunents stated in the memorandum, procedures exist which will allow 1

- the safe shutdown of the plant, assuming only the equipment on the SSEL: remains available and operable. Resolution of the operations review comments are stated below:

l.

MOV disconnects should be included on the Unit I SSEL 1.

The disconnect switches listed below were added to the appropriate SSEL:

QlR188029-A QlR18B030-A QlR18B031-A QlR18B032-A 2

QlR18B033-B QlR188034-B QlR18B035-B QlR188036-B QlR18B038-A QlR18B039-A QlR18B040-A QlRl8B041-B QlR18B042-B QlRl8B043-B Q2R18B029-A Q2R18B030-A Q2R18B031-A Q2R18B032-A Q2R18B033-B Q2R18B034-B Q2R18B035-B Q2R18B036-B Q2R18B038-A Q2Rl8B039-A Q2R18B040-A Q2Rl8B041-B Q2R18B042-B Q2R18B043-B 2.

The cabinets for RAD monitors R27A and B should be included:

Control room panels QlH1INGR25041-AB and Q2H1INGR25041-AB, which contain monitors R27A and B, are included on the Units 1 and 2 SSELs, respectively.

3.

Room cooler thermostats should be included on the Unit I list:

'Ihe room thermostats in the battery charger, MCC, and switchgear rooms were added to the Unit 1 SSEL.

Al-1 l

'4.

steam generator blow down (SGBD) contamment isolation valves are required to be added to the Unit I list:

SGBD valves QIR24V003A, B, and C were added to the Unit 1 SSEL.

5.

FCV-605 and the hot-leg recirculation valves should be added to the Unit 2 list:

RHR heat exchanger bypass valves Q2ElIFCV605A and B and hot-leg recirculation valves Q2E21MOV8884 and Q2E21MOV8886 were =Med to the Unit 2 SSEL.

Question 2:

Section 3.0, " Relay Evaluation Report," contains a summary of results which indicate that all applicable relay / component combinations were evaluated and categorized into one oiseveral groups. One of these groups specifies " resolved by operator action." Please provide a list of each relay / component which was categorized in this group and describe the specific operator 4

actions required to resolve each, and the method (s) used to identify each.

I SNC Response

]

Resolution by operator action was a potential categorization for a relayk=,m-t component combination. 'Ihis is the reason it was listed in the report. However, no relays were accepted based on using this method. All relays were resolved by one ofother A-46 acceptable methods i

j Question 3:

For the operator actions specified in (b), above, are any of these actions time critical? If so, what analyses were performed to verify that these operations could be accomplished in the timeframe required to facilitate safe shutdown? Ilow were potentially harsh environmental conditions factored into these analyses?

i SNC Response As noted above, no operator actions due specifically to potential relay malfunctions are required.

Question 4:

Provide a complete list of sources of water (tanks, etc.) available for cooldown, including capacities and seismic qualification.

Al-2 I

5 SNC' Response

'Ihe Safe Shutdown Equipment List (SSEL) provided as part of the Unresolved Safety Issue (USI) i A-46 Summary Report, includes a 500,000 gallon Coedensate Storage Tank (CST) and a 500,000 i

gallon Refuchng Water Storage Tank (RWST) for each unit. All four of these tanks are seismically qualified. 'Ihe RWST provides borated water for makeup to the RCS subsequent to a seismic evcat, while the' CST provides non-borated water for makeup to the secondary side of the steam generators via the Auxiliary Feedwater System (AFW) 'Ihe Service Water System provides a backup source of water to the AFW pumps should the contents of the CST be depleted. The Service Water System is comprised of a 100 acre storage pond with a seismically qualified dam, i

pumphouse, and distribution piping. All the Service Water pumps and ***d'u equipment are provided with Class IE power supplies. Use of these water sources is proceduralized in emergency i

and abnormal operatmg procedures, and traimng in use and implementation of the procedures is provided to all licensed operators.

Other sources of water,.which are not included in the SSEL, are available for makeup to the i

primary and secondary systems Exclusion of equipment from the SSEL does not prevent l

operators from using the equipment if available. Each unit has a 200,000 gallon Reactor Makeup Water Storage Tank and two 21,000 gallon Boric Acid Storage Tanks which can provide RCS i

makeup. These tanks are seismically qualified. In addition to providing AFW, the CST is the normal source of makeup for the enruhta and feedwater system. Inventory in this tank is usually l

maintained near capacity, but a low level alarm is provided on the CST at the 196,000 gallon level, at which point procedures direct that makeup to the CST be initiated from the Demmeralized l

Water System. There are several sources of water which may provide makeup to the Demineralized

]

Water System.

i Question 5:

l Are emergency air compressors seismically qualified and provided with safety related power?

SNC Response Yes, the compressors and associated distribution piping are seismically qualified. The compressors are provided with Class IE power supplies.

,1 j

Question 6:

The report mentions a Train "D" of CCW as an alternate path for decay heat removal in section 2.5.4. Is this correct?

SNC P~==>

'the reference to Train D was a typographical error. FNP included two trains of CCW in the SSEL. The appropriate wording should refer to Train "B."

A 1 -3

Ques

  • tion 7:

I

~ Are procedures established for all shutdown paths mentioned in the SQUG Report?

j'

'i SNC Response

{

. Yes.. One of the esiteria used for selection of equipment on the SSEL was that the systems and components specified would be equipment expected to be used by operators in established plant procedures. SNC did not develop a new group of seismic shutdown procedures, but instead relied on existing emergency and abnormal operating procedures. Plant operators are routinely trained in the use of these procedures and practice.with them on the plant simulator regularly. 'Ihe plant Operations Manager provided a letter, referenced in the SQUG Report, which stated that plant operators could safely shutdown the plant using only the equipment on the SSEL if ne==ary, using established procedures.

2 i

Question 8:

Discuss time available for use of qualified water sources before depletion (RWST, CST). Are there calculations to document the time that qualified water sources would be available?

d SNC Response Per the guidelines of GL 87-02, SNC was not required to assume the occurrence of a LOCA in conjunction with a scismic event. GL 88-20 however, does assume a concurrent LOCA, which was addressed in the FNP Individual Plant Examination of External Events (IPEEE) Report. The i

SSEL equipment was selected in order to satisfy both generic letters. In a large break LOCA scenar o with maximum ECCS injecton, the RWST would be depleted to a level that would require initiation of actions to establish recirculation in approximately 20 minutes. Consistent with the FNP design basis, existing plant procedures establish recirculation cooling from the 1

containment sump after drawdown of the RWST. This capability is confirmed through plant j

testing and operator training The Emergency Procedure that addresses natural circulation cooldown to prevent reactor vessel head voiding, directs operator actions based upon available CST inventory. The procedure contains tables with allowable time delay prior to beginning a controlled cooldown, based on CST inventory as well as availability of control rod drive mechanism cooling fans to cool the Reactor Vessel upper head. The procedure also contains a table with CST inventory requirements versus, transfer time to other procedures which allow voiding in the vessel head. The Demineralized Water System has the capability of making up to the CST at a rate of 360 gpm, which is adequate for AFW system requirements. Thus, if the Domineralized Water System is available, the CST can bc

)

filled at a rate equal to or greater than AFW pump demand and avoid %%g the CST. If not, procedures require the AFW pump suction be shifted to service water when the CST nears depletion. 'Ihe Service Water pond is the plant ultimate heat sink and is assumed to be available at

alltimes, w

A1-4 J

s w

1

, ueition 9:

Q Does FNP plan to use the " Bleed & Feed" method described la EOPs for decay heat removal?

SNC Response GL 87-02 (SQUG) requires two " redundant" safe shutdown paths. These paths may employ the same cooldown technique. Thus, the SQUG Report takes credit for two trains of AFW and heat removal via steammg the steam generators. No credit is taken for RCS Bleed and Food for the GL 87-02 response GL 88-20 (IPEEE) requires two " diverse" safe shutdown paths, which can not

]

employ the same cooldown technique. Thus, for the IPEEE submittal, FNP has taken credit for RCS Bleed and Feed as one safe shutdown path. There is sufficient equipment included in the Safe Shutdown EquW List to satisfy both generic letters Question 10:

The Support Systems section of the report did not include instrument air, emergency air compressors, or the control rod drive system. Explain.

l.

SNCPa m He instrument air system is not safety related or seismically qualified. Air operated valves are designed with a fail-safe position which does not depend on an operable air supply. Although the emergency air compressors are not discussed in the Support System text of the Summary Report, they are included in the SSEL for support of the main steam atmospheric relief valves. As mentioned in response to Question 2, the emergency air compressors are seismically qualified and provided with Class IE power supplies. %c control rods fall into the reactor core via gravity upon l

loss of power to the rod drive system. %us, the control rod drive system is not required to be functional for the rods to insert negative reactivity and take the reactor subcritical. Even if the control rods fail to insert, there is sufficient boron in the RWST to insure suberiticality.

Question 11:

Does a reactor trip (with or without a loss of offsite power) result in lifting of main steam safety valves for FNP7 SNC Response A loss of offsite power with an accompanying reactor trip would, by design, result in lifting of the main steam safety valves. Lifting of main steam safety valves in response to a reactor trip without a loss of offsite power is possible, although the transient would likely be adequately r=W_ to by the _=*==ph-ic relief valves and steam dump valves.

Al-5

4' m

l T

i ATTACHMENT 2 9

Memorandom DATE:

February 21 1995 TO:

Keith Wooten 7YW b FROM:

Phil Crone RE:

Plant Cpera ions Review of Farley Units 1 and 2 USl A 46/IPEEE Safe Shutdown Equipment List cc:

Robert Fucich, Randy May -

FNP Operations has icnewed the lists and assumptions furnished by Randy May on the above subject and, based on the incorpo ation of the following conunents. we agree that procedures exist which will allow the safe shutdown of the pant, assuming only the equipment on the lists remains available and operable. We further agree that operatars we trained on the use of these procedures. This review was based on the -

" desk top" method.- Our comments are as follows:

1. MOV Disconnects should be included on the Unit i list.
2. The cabinets for Rad Monitors R27A&B should be included.

3 Room cooler thermostats need to be included on the Unit I list.

4. SGBD containment isolation valves need to be added to the Unit I list.
5. FCV-605 and the hot leg recire valves need to be added to the Unit 2 list i

GPC/RSF

+

r.

. -