Responds to NRC Request for Clarification of 840831 License Amend Request Re Generator Time Overcurrent Protection for Diesel Generators.Amend Seeks to Implement Generator Time & Instantaneous Overcurrent Protection
ML20093C968
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 10/04/1984
From: Tucker H
DUKE POWER CO.
To: Adensam E, Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20093C971 List:
References
TAC-55787, TAC-55788, NUDOCS 8410110023
Download: ML20093C968 (1)


Text

g._._..-

y .*

A

~ Duxe Powen GOMPANY P.O. DOx 33189 CHARLOTTE. N.C. 28242

. HAL B. TUCKER vuosemmesmewr TELEPHONE uma r o.cor= ' (704) 373-4331 October 4, 1984 Mr. Harold R. Denton, Director

~ Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory C;mmission Washington,~ D. C. 20555 Attention: t Ms'.7 E.iG.-J Adensam,(Chief 3 Licensing Branch No. 4 -

Subject:

~McGuire Nuclear Station Docket Nos. 50-369 and 50-370

Dear Mr. Denton:

This lettar is in response to a request by the NRC Staff to clarify a license

- amendment request regarding Generator Time Overcurrent Protection for the diesel generators at McGuire Nuclear Station. This license amendment request

'was made in an August 31, 1984 letter from H. B. Tucker to H. R. Denton.

The proposed amendments seek to implement a Generator Time Overcurrent Protection and an Instantaneous Overcurrent Protection for,the' diesel generators. The Generator Time Overcurrent Protection trips the associated diesel generator breaker in the event of a multiphase fault on the switchgear buss to prevent destruction of the diesel generator. In the initial submittal

'of this license amendment request, the Generator Time Overcurrent Protection

. was described as a diesel generator trip similar to engine overspeed lube oil pressure and generator differential. However, it is a diesel generator breaker trip. Likewise the Geaerator Instantaneous Overcurrent Protection will protect the diesel generators during testing periods, be bypassed in the' event of an accident condition, and trip only the diesel generator breaker.

The proposed technical specification has been revised to clarify this (see attached). All other justifications and analyses continue to be valid with this clarification incorporated.

Please contact us if there are further questions regarding this matter.

.Very truly yours, h$. ? /&

Hal B. Tucker 4

WHM/mj f cc: Mr. James P. O'Reilly, Regional Administrator Mr. W. T. Orders U. S. Nuclear Regulatory Commission Senior Resident Inspector Region II McGuire Nuclear Station 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

)

8410110023 e4too4

$DRADOCK 05000369 ((/ofi PDR ,jl

_ _ _ _ - - _ - - _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _