ML20091A638
| ML20091A638 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 03/20/1992 |
| From: | Office of Nuclear Reactor Regulation |
| To: | |
| Shared Package | |
| ML20091A633 | List: |
| References | |
| NUDOCS 9203300072 | |
| Download: ML20091A638 (16) | |
Text
.
lpa a'cq 0,
3#( 'j UNITEC STATES E'
NUCLEAR REGULATORY COMMISSION g
y.;
WASHINGTON, o C. 20%5 I
g o,gv...../
SAFETYEVALUATIONBYTHEOFFICEOFNUCLEARREACTORREGULATig RELATED TO AMENDMENT NO.178 TO FACILITY OPERATING LICENSE DPR-57 AND AMENDMENT NO. 119 T0 FACILITY OPERATING LICENSE NPF GEORGIA POWER COMPANY. ET AL.
EDWIN 1. HATCH NUCLEAR PLAflT. UNITS 1 AND 2 DOCKET N05. 50-321 AND 50-366
1.0 INTRODUCTION
10, 1990, as supplemented January 21 and December 16, By letter dated January 1991, and March 5, 1992, the Georgia Power Company, et al. (the licensee),
submitted a request for changes to the Edwin 1. Hatch Nuclear Plant, Units 1 dDd 2, Technical Specifications (TSs). The requested changes would change TS 3.9/4.9, " Auxiliary Electrical Systems," (Unit 1) and TS 3/4.8.1, "A.
C.
Sources," (Unit 2) regarding emergency diesel generator (EDG) testing.
The proposed change', are intended to eliminate discrepancies between the plants' TSs and Regulatory Guide 1.108, " Periodic Testing of Diesel Generator Units i
Used As Onsite Electric Power Systems At Nuclear Power Plants," and to conform to the guidance contained in Generic letter (G.L.) 84-15, " Proposed Staff Actions to improve and Maintain Diesel Generator Reliability," dated July 2, 1984. The January 21, 1991, letter, in response to the staff's December 14, l
1990, request, the December 16, 1991, and the "HL-2075, Forwards Response to NRC 901218 Request for Addl Info Re 900110 Application for Amends to Licenses DPR-57 & NPF-5, Changing TS to Revise Testing Requirements on [[system" contains a listed "[" character as part of the property label and has therefore been classified as invalid.s|March 5, 1992, letter]]s provided additional ano clarifying information and proposed additional changes to the i
plants' TSs for EDG testing that did not change the initial proposed no significant hazards consideration determination.
2.0 EVALUATION The asterisks that appear in the revised TS pages are discussed separately from the text later on in this section.
I Change IA:
In TS 4.9.A.2.a.1 (Unit 1), add:
A steady-state voltage of 4160 1 420 volts and a steady-state frequency of 60 t 1.2 Hz will be maintained.
in TS 4.9.A.2.a.2 (Unit 1), add:
The test will verify the diesel generator will achieve and maintain a steady-state voltage of 4160 1 420 volts and a steady-state frequency of 60 1.2 Hz.
9203300072 920320 PDR ADOCK 05000321 P
. in TSs 4.9. A.7 b.1 and 4.9. A.7.c.1 (Unit 1), adds and achieve and maintain a steady state voltage of 4160 1 420 volts and a steady state frequency of 60 t 1.2 112, in TS 4.0.1.1.2.d.0 b (Unit 2), delete:
ena gating the auto-connected shutdown loads through the iond sequencer and operates for ) $ minutes while its generator is loaded with shutdowii loads and substitute:
energizes the 6uto-connected shutdown loads through the load sequencer, operates for > 5 minutes while its generator it luaded with shut 30w. loads, schieves ano miintains a steady-state voltage of 4160 a 420 volts tod e steady-state f requency of 601 1.2 Hz.
InTS4.8.1.1.2.d.8.b(Unit 2), delete:
}
energizetheauto-connectedemergency(accident) loads through the load sequencer and operates for.+ 5 minutes while its generator is loaded with mergency" loads and substituttt energizes the au':.-connected shutdown (emergency) loads through the load sequent.er, operates for > 5 minutes while its generator is loaded with emergeWey loads.
achieves and maintains o steady-state voltage of 4160 1 420 volts and a steady-state frequency of 60 1 1.2 Hz.
In TS 4.8.1.1.2.a.4 (Unit 2), add:
and maintains a steady-state voltage of 4160 1 420 volts and a steady-state f requency of 601 1.2 llz.
InTS4.8.1.1.2.b(Unit 2), add:
achieves and inaintains a steady-state voltage of 4160 1 420 volts _and a steady-state frequency of 60 1 1.2 Hz.
The above changes are proposed to add acceptance criteria for CDG voltage and frequency following the guidance contained in G.L. BA-16. These changes add consenatism to the TS and are, therefore, acceptable.
3 C',ynge 10:
In TSs 4.8.1.1.2.d.5.b and 4.8.1.1.2.d.B.h (Unit 2), add:
inj12 seconds after:
energizes the emergency busses with permanently
'i connected loads Hodify TS 4,9.A.7.b.1 (Unit 1), to read:
the emergency busses are deenergized, and that the diesel generators will start, energize the emergency busses with permanently connected loads in 4 12 seconds, energize the auto. connected shutdown ~10 ads through the load sequencer, operate for > 5 minutes while the diesel generators are loaded ~with the shutdown loads after:
to demonstrate that Hodify TS 4.9.A.7.c.1 (Unit 1), to read:
- and the diesel starts on the auto-start signal with permanently connected loads in ( 12 seconds, energizes the auto-connected shutdown (emergency) loads through the load sequencer, operates for ) 5 minutes while its generator is loaded with the emergency Toaos after
load shedding from the emergency buses The above changes are proposed to add an acceptance.iterion to the start time of the EDGs (with the 12 seconds being consistent with the plants' fin.: Safety Analysis Report and other current TSs for the plants) followins the guidance contained in G.L. 84-15.
Also the wording of the Unit 1 TSs is made consistent with the Unit 2 TSs. These changes add conservatism and censistency to the plants' TSs and are, therefore, acceptable.
Change 10:
In TS 4.9. A.2.a.1 (Unit li, delete:
During the generator test, the starting air compressor shall be checked for operation and for its ability to. recharge the air system and substitute:
Verify the pressure in both diesel air start receivers to be 2 225 psig.
The above change is proposed to add consistency between both uMts' 15s.
Also, this change represents a more definitive e,uie ment. On this basis, the NRC staff finds it acceptable.
1 i
l i
4 i
Change 2:
la TS 4.8.1.1.2.d.9 (Unit 2), delete:
> 2950 kW for diesel generator 2A, 2547-kW for
' diesel generator 1B and 2 2928 W for diesel generator 2C
~
and substitute:
g
> 3000 kW.
s Also, delete:
2764 2825 kW for diesel generatur 2A, 2360-2425 kW
[
for diesel generator 18-and 2745 2825 kW for diesel generator PC and substitute:
1 2775 282S kW.
in TS 4.9.A.2.a (Unit 1), add the following as a 6:
At least once per 18 months during shutdown, verify l
the diesel generatur operates for at least 24_ hours.
During the first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of this test, the diesel generator shall be loaded to A 3000 kW* and during the remaining 22_ hours of this teit, the diesel generator shall be loaded I.
to 2775-2825 kW*
The asterisk refers to a new footnote that reads:
Momentary _._ variations outside this band shall not invalidate the. test.
The above loading changes represent higher loading than those currently contained in the Unit 2 TSs, are more conservative, and are, therefore, acceptable. Also, the new Unit 1 TSs are identical r
to the modified Unit 2.TSs. represent added conservatism, and'are therefore, acceptable.
Change 3:
InTS4.8.1.1.2.d.3(Unit 2), delete:
a load of ? 798 kW while maintaining voltage at 4160 t 400~ volts and a frequency at 60 2 2 Hz-and substitute:
i its largest singic.nutdown (emergency) load while maintaining voltage at 4160 t'420 volts.
For diesel generator 2A this will be the 2A Residual Heat RemovalServIceWater(RHRSW)-pumpat.ratedflow; for diesel generator _IB, this would~be either IC or _
2C_RHR$W pump at rated flow; for diesel generator 20,
,,-----.,w--
wee...
,a--.
e, me..
.mu,me.
w w w m,
,%,rsv.
.,--.m...%~e
,,,a,-,w__-.,--
,--,.,re,,+.-.--%.,
-p p e n m,-
.-my--:a.-9e'<
w Y t e v ' '1er ' *e ww* 1+T i OWMT'
this would be either the 20 or 2D RHRSW pump at rated i
flow. During these load rejection tests, the diesel 1
generat r shall not exceed the nominal speed plus 757 of the difference between nominal speed w d the
-overspeed trip setpoint, or 15% above nominal speed, whichever is lower.
In TS 4.8.1.1.2.d.4 (Unit 2), after the words:
t reject a load of modify the original wording to read:
at least 2775 kW without tripping. The generator voltage shall not exceed 4800 volts during and h 110 wins the load rejection.
In TS 4.9.A.2.a (Unit 1), add the following as a.4 and a.$,
respectively At least once per 18 months during shutdown, verify the diesel generator capability to reject its largest single shutdown (emergency) load while maintaining voltage at 4100 t 420 volts.
For diesel genert,hr IA, this would be CS [ core spray] pump 1A at rateo f'ow.
For diesel generator IB, this would be either the IC or 2C Residual Heat Removal Service Water (RHRSW) pump at rated flow.
For diesel generator IC, this would be CS pump 1B at rated flow.- During the load rejection test, the diesel generator shall not exceed the nominal speed plus 75% of the diffwence between nominal speed and the overspoed trip setpoint,-or 15% above nominal speed, whichever is less.
At least once per 18 months during shutdown, verify ~
diesel generator capability to reject a load of at least 2775 kW without tripping. The generator voltage 4
shall not exceed 4800 volts during and following the load rejection.
The above changes to the Unit ? TSs follow the guidance contained in G.L. 84 15 for partial and full load rejection I
testing and are, therefore, acceptable. Also, the.new TSs added for Unit I are similar to the modified Unit 2 TSs, represent added conservatism, and are, therefore, acceptable.
i f
_ _ _ ~ _. _ _.
l
. Change 4:
At the end oi TS 4.8.1.1.2.d.9 (Unit 2), add "*"" that refer $ to the following new footnote:
If the diesel generator fails this test, a retest may be performed after the diesel generator has been operated for 2 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at 2 2565 kW.
In TS 4.9.A.7 (Unit 1), add the following as A.7.b.2:
Within 5 minutes after completing the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> load test specified in Surveillance Requirement 4.9 a.2.a.6, repeat Surveillance Pequirement 4.9 A.7.b.1 with a simulated loss of offsite power start signal and ruti the diesel for at least 5 minutes while loaded with shutdown loads.* This test is to be performed every 18 months.
Also, renumber existing TS 4.9.A.7 b.2 as 4.9 A.7.b.3.
The above asterisk refers to the following new footnote:
li *he diesel generator falls this test, a retest may be perTormed af ter the diesel generator has been operated for 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> at 12565 kW.
Originally the Unit 2155, but not the Unit 1 TSs, required that a loss of offsi'.e power test be performed irinediately f ollowing the EDG 24-hour test.
Because the revised T$s added for Unit 1 are the same t the Unit 2 TSs and represent added conservatism, we find the c'ennge acceptable.
The new isotnote added to the TS is consistent with the current staff pcsition that the whole 24-hour test does not need to be repeated if the diesel just failed the loss of offsite power test; only the loss of offsite power test needs to be repeated after the diesel generator has been operated for > 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at full load.
Therefore, we find this change acceptabTe, Change SA:
In TSs 3.8.1.1.b 2 and 3.8.1.2.b.2 (Unit 2), delete:
32,000 and substitute:
33,000.
7 In TSs 3.9.A.2.d (Unit 1), delete:
80,000 and substitute:
99,000.
In Bases 3/4.8 (Unit 2o M W Mi- #69 Each of the five diesel guerators is provided The 33 000 with a storage tank and s t!ny tank.
gallonsrequiredtobemaintiinedineachcdthe fuel oil tanks represents a total volume of oil sufficient to operate any four diesel generators at 3250 kW for a period of 7 days. This is based on a conservative expected fuel consumption of 240 gallons per hour per engine.
The onsite fuel capacity will last longer than the tirne it would take to replenish the onsite supply from off site sources (which is ( 7 days).
Valving is available 50 that fuel oil can be transferred between fuel oil storage tanks.
However, administrative controls shall be in place to limit long-term total diesel generator load to 4 13,000 kW and to limit individual diesel generator loading to ( 3250 kW.
In Bases 3.9 A.2.d (Unit 1), delete the original first paragraph and substitute:
Each of the five diesel generators is provided with a storage tank and a day tank.
The 33,000 gallons required to be maintained in each cf the fuel oil tanks represents a total volume of cil suf ficient to operate any four diesel generators at 3250 kW for a period of 7 days. This is based on a conservative expected fuel consumption of 240 gallons per hour per engine.
The onsite fuel capacity will last longer than the time it would take to replenish the onsite supply from offsite sources (which is ( 7 days).
Valving is available so that fuel oil can be transferred between fuel oil storage tanks.
However, administrative controls shall be in place to limit long-term total diesel generator load to ( 13,000 kW and to limit individual diesel generator loading to < 3250 kW.
The above changes represent an increase in the amount of diesel fuel stored in the diesel fuel storage tanks and clarify'the bases for the amount of fuel required. Because these changes add conservatism to the plants' TSs, we find them acceptable.
8 Change SB:
In TS 3.9. A.P.d (Unit 1), add:
and a minimum of 900 gallons in each diesel fuel day tank.
In TS 4.9.A.2.d (Unit 1), delete the original first paragraph and substitute the following:
The quantity of diesel fuel available in each fuel storage tank and fuel day tank shall be measured and recorded concurrently with the operability test specified for that diesel in Specification 4.9 A.?.a.1, and renumber the existing second paragraph.
The above chances are sim;1er to existing Unit 2 TSs. represent added conservi.tism, and are, therefore, acceptable.
Change 6A:
In TS 4.9. A. 4 (Unit 1), renuner the original paragraph as "a" and add the following as "b":
Demonstrate manual and automatic transfer of un't power supply from the normal circuit to alternate circuit for each of the required circuits from offsite at least once per 18 r.snths.
This change is a new surveillance requirement similar to a Unit 2 surveillance, represents added conservatism, and is, therefore, acceptable.
Change 68:
In TS 4.9.A.2.s (Unit 1), add the following as a 3:
At least once per 18 months during shutdown, subject the diesel to an inspection in accordance with procedures prepared in conjunction with its manufacturer's recommendations for this class of standby service.
This change is a new surveillance similar to a Unit 2 surveillance, represents added conservatism, and is, therefore, acceptable.
Change 6C:
In TS 4.8.1.1.2.d.10 (Unit 2), delete:
2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating of 3135 kW and substitute:
2000. hour rating of 3100 kW
.in TS 4.9.A.2.a (Unit 1), add the following as a.7:
At least once per 18 months during shutdown, verify that the auto-connected loads to each diesel generator do not exceed 3100 kW.
.g.
The Unit 2 change follows the guidance for this surveillance requirement contained in G.L. 84 15 and is, therefore, acceptable. The Unit 1 change is a new surveillance requirement equivalent to the modified Unit 2 surveillance, represents added conservatism, and is, therefore, acceptable.
Change CD:
In TS 4.9.A.P.a (Unit 1), add the following as a.8:
At i ast once per 18 months during shutdown, verify the diesel generator's capability to synchronire with the offsite power source while the generator is loaded with its emergency loads upon a simulated restoration of offsite power, to transfer its loads to the offsite power source, and to proceed through its shutdown sequence.
This change is a new surveillance requirement similar to a Unit 2 surveillance, represents added conservatism, and is, therefore, acceptable.
Change 6t:
In TS 4.9.A.2.a (Unit 1), add the following as a.9:
At least once per 18 months during shutdown, verify that with the diesel generstor operating in the test mode (connected to its bus), a simulated LOCA actuation signai overrides the test mode by returning the diesel generator to standby operation and automatically energizes the emergency loads with offsite power, inTS4.8.1.1.2.d.12(Unit 2), delete:
safety injection signal overrides the test mode by and substitute:
LOCA actuation signal overrides the test mode by:
The Unit 1 change is a new surveillance requirement similar to a Unit 2 surveillance, represents added conservatism, and is, therefore, acceptable. The Unit 2 change is editorial in nature and is considered acceptable.
Change 6F:
In TS 4.8.1.1.2.d.13 (Unit 2), add " associated" between "each" and " fuel storage tank."
This change is editorial in nature, is added for clarification and is, therefore, acceptable.
In TS 4.9 A.2.e (Unit 1), add the following as e.2:
The operation of the diesel fuel oil transfer pumps to transfer fuel from each associated fuel storage tank to the day tank of each diesel via the installed cross connection lines shall be demonstrated at least once per 18 months during shutdown.
. e.,
This change is a new surveillance requirsment similar to a Unit 2 surveillance, represents added conservatism, and is, therefore, acceptable.
l gange6G:
In TS 4.9.A.2.a (Unit 1), add the following as a.10 At least once per 10 years, or af ter any modifications which could affect diesel generator interdependence, verify that all three diesel generators start simultaneously during shutdown, and accelerate to synchronous speed in 3 12 seconds.
This change is a new surveillance requirement similar to a Unit ?
Surveillance, represents added conservatism, and is, therefore, acceptable.
f Change 6H:
In TS 3.9.A.2 (Unit 1), add the following as A.2.e:
f fuel 011 Transfer pumps _
A fuel oil transfer pump shall be operable and capable of transferring fuel oil from the storage system to the day tank.
t In TS 4.9.A.2.e (Unit 1), delete the original paragraph and substitute-the following as A.2.e.1:
The operation of the diesel fuel oil transfer pumps to transfer fuel from the storage system to the day tank I
shall be demonstrated concurrent with the operability test specified for that diesel in Specification 4.9.A.2.a.1.
The above changes add a new limiting cond'. ion for operation (LCO) and a new surveillance requirement for the fuel oil transfer pumps similar to a Unit 2 surveillance, tepresent added conservatism, and are, therciore, acceptable.
Change 61:
InTS4.9.A.7.b.1(Unit 1), add"also"between"thetestingof the undervoltage logic shall" and " demonstrate the operability."
Also, substitute:
4160-volt load shedding and auto bus transfer circuits, with the design requirements (g is in accordance and that the subsequent loadint10% of its design interval) for:
4160-volt load shedding, auto bus transfer circuits, This change is a new surveillance requirement similar to a Unit-2 surveillance, represents added conservatism, and is, therefore, acceptable.
c.
11 -
Also delete TS 4.8.1.1.2.d.7 (Unit 2) in its entirety to elimInateunnecessarytestingoftheEDGspertheguidance 1
contained in G.t.
83-30,
- Deletion of Standard Technical l
Specification Surveillance Requirements 4.8.1.1.2.d.6 for Diesel Generator Testing."
Change 6J:
In TS 4.9.A.7.c.1 (Unit 1), delete:
4 hnth loss of offsite power and a degraded voltage condition and substitute:
InTS4.8.1.1.2.d.8(Unit 2), delete:
r with sepcrate tests a 1) degraded voltage condition and
).
This change is intended to reduce unnecessary testing, is consistent with current Standard TS (STS) and is, therefore, acceptable.
t Change 6K:
In TS 4.9.A.7.c (Unit 1), add the following as c.3:
Verify once per 18 months during shutdown that all diesel generator trips except engine overspeed, low lube oil pressure, and generator differential are automatically bypassed upon loss of voltage on the emergency bus concurrent with an ECCS actuation signal.
This change is a new surveillance requirement similar to a Unit 2 curve 111ance, represents added conservatism, and is, therefore, acceptable, Change 6L:
DeleteTSs3.9.A.7.dand4.9.A7.d(Unit 1)intheirentirety.
The surveillance of the 600.V load shedding logic system covered by the above TSs are explicit and unique to the Unit 1 TSs. Since equivalent surveillance requirements are implicitly contained in Unit 1 TS 4.9. A.7.c.) and the change adds consistency with the Unit 2 TSs,_we find the change acceptable.
Change 6M:
In TS 4.9,A.7.b.1 (Unit 1), delete:
scheduled refueling outage and substitute:
18 months during shutdown in the first line.
I
--me-*
v r m ?
- t--*em ee
+-I
- --v-<e
+rm----r:
we
,--e..--m-_ez-*
r*=e=ci,rme
--+e--
--w--w.-
w*w---=w,aw-+mm%-
< s e-*
v e n -er
- -W
~
t~-m
.c In TS 4.9.A.7.c.) (Unit 1), delete:
per operating cycle and substitute:
every 18 months dt:t ing shutdown in the first line.
These changes are intended to add consistency between Unit 1 and Unit 2 TSs. Therefore, we find this change acceptable.
Change 6H:
In the Bases 3.9.A.2 (Unit 1), delete:
a 2750-KW continuous rating and substitute:
a 2850-KW continuous rating.
This change adds the correct continuous rating and is acceptable.
Change 60:
In TSs 4.8.1.1.2.d.5.b and 4.8.1.1.2.d.8 b (Unit 2), delete from the first line:
from ambient conditions.
In TS 4.9.A.7.c.1 (Unit 1), delete:
from ambient conditions.
These changes are consistent with current STS and are, therefore, acceptable.
Change 6P:
In TS 4.9.A.7.a (Unit 1), delete:
core spray system l
l and substitute:
ECCS.
Also, add at the end of the paragraph Each diensel generator shall operate on standby for15 minutes.
This change is consistent with the Unit 2 TSs and cur'/ent stb and is, therefore, acceptable.
___.___.____.___.___.__.__._m._
. 4 t
13 -
Change 7A:
In TS 4.9.A.2.a.1 (Unit 1) after " Staggered Test Basis." add an "** that refers to a new footnote shown below.
In TS 4.8.1.1.2.a.4 (Unit 2), add 6 "" at the end that refers to the same footnote, for the 10 (swing) diesel, a single test 9411 satisfy the requirements for Unit 1 Specification 4.9.A.2.a.1 and Unit 2 Specification 4.8.1.1.2.a.4 with the diesel connected to one unit's emergency bus for one periodic test and connected to the emergency bus in the other unit during the next l
i periodic test.
The above change is intended to reduce the unnecessary double monthly testing of the swing EDG 10 that results from requirements in Unit I and Unit 2 TSs.
With this change, EDG 10 will only be tested once a month although operability is still required for both units. This meets the intent of the recorrnendations for reduced EDG testing contained in G.L.
84-15 and is, therefore, acceptable.
Change 70:
At the end of TS 4.9.A.2.a.2 (Unit 1), add an '*" that refers to the new footnote shown below.
At the end of Specification 4.8.1.1.2.b (Unit 2), add a "**" that refers to the same footnote.
A single 6-month (184-day) test for the IB diesel will-satisfy the requirements for Unit 1 Specification 4.9.A.2.a.2 and Unit 2 Specification 4.8.1.1.2.b.
The 6-month test will be performed using the starting circuitry and emxrgency bus from one unit. The next 6-month test will be performed using the starting circuitry and emergency bus from the other unit.
The above change is intended to reduce the unnecessary double testing every 6 months of the swing EDG 1B resulting from surveillance requirementi contained in both the Unit I and Unit 2 TSs. With this change. EDG 1B will be tested only once-during the 6-month testing. This change meets the intent of the recommendations for reduced EDG testing contained in G.L. 84-15 and is, therefore, acceptable.
l
. ~,,, _.. -
..--_.-_..-.,---...-.-.~,.,-_---,--._.,__.-.,,_..,..,,...--,_,,,,,_-,-,-,_.,,,,.,...-,.r,..,..
e Change 7C:
At the end of revised TSs 4.9. A.2.a.3, 4.9. A.2.a.4, and 4.9. A.2.a.S l
(Unit 1), add an "*" that refers to the following new footnote:
l for the 1B diesel generator, a single full load rejection test evety 18 months will satisfy-the requirements of Unit 1 Specifi-cation 4.9.A.P.a.S and-Unit 2 Specification 4.8.1.1.2.d.4 A single partial load rejection test every 18 months will satisfy the require-n1ents of Unit 1 Specification 4.9. A.2.a.4 and Unit 2 Specification-4.8.1.1.2.d.3. A single diesel inspection will satisfy the requirements of Unit 1 Specification 4.9.A.2.a.3 and Unit 2 Specification 4.8.1.1.2.d.1.-
i At the end of revised TS 4.9.A.P.a.6 (Unit 1),-add a "**" that refers to the following new footnote:
For the IB diesel generator a-single 24-hour load test every 18 months wIl1 satisfy the requirements of Unit 1 Specification 4.9.A.P.a.6 and Unit 2 Specification 4.8.1.1.2.d.9.
At the end of TS 4.8.1.1.2.d.1 (Unit 2), add a "*"" that l
refers to the following new footnote:
For the 1B diesel generator, a single diesel inspection every 18 months will t
l satisfy the requirements of Unit 1 Specification 4.9. A.2.a.3 and Unit 2 Specification 4.8.1.1.2.d.1.
At the end of the TS 4.8.1.1.2.d.3 (Unit 2), add an "*" that refers to the following new footnote:
For the 18 diesel generator, a single partial load rejectice test every 18 months will satisfy the requirement.i cf Unit 1 Specification 4.9.A.2.a.4-and Unit 2 Specification 4.8.1.1.2.d.3.
At the end of TS 4.8.1.1.2.d.4 (Unit 2), add an "*" that refers to the following new footnote:
for the IB dieci generator, a single full load rejection test every 18 months will satisfy the requirements of Unit 1 Specifi-cation 4.9.A.2.a.5 and Unit 2 Specification 4.8.1.1.2.d 4 At the end of the second sentence in TS 4.8.1.1.2.d 9_(Unit 2),
add a "**" that refers to the following new footnote:
l l
- <*o 15 -
For the 10 diesel generator, a single 24-hour load test every 18 months will satisfy the requirements of Unit 1 Specifi.
cation 4.9.A.2.a.6 and Unit 2 Specification 4.8.1.1.2.d.9.
The above thenges are intended to reduce the unnecessary double testing of the swing EDG 10 during the 18 month inspection, 24-hour load test, and parti 61 and full load rejection tests required by the current Unit 1 and Unit 2 TSs. These changes meet the intent of the recorrnendations contained in G.L. 84-15 and are, therefore, acceptable.
Change 70:
In the original TSs 4.9.A.2.a.1 and 4.9.A.2.a.2 (Unit 1), replace the "*" with "**" that refers to the original footnote:
"Homentary variationt..."
This is an editorial change related to Change 7C. Therefore, it is acceptable.
Chance 8:
Delete the original TS 4.8.1.1.2.e (Unit 2) and renumber original TS 4.6.1.1.2.f (Unit 2) as 4.8.1.1.2.e.
TS 4.8.1.1.2.e currently requires that every 5 years the EDGs be started at least 5 times with the air start receivers pressurized to 225 psig and their compressors secured.
Deleting this TS will reduce unnecessary EDG testing and is consistent with the intent of G.L. 84-15 and the latest staff position. On this basis, the NRC staff finds this change acceptable.
Change 9:
In the Bases 3/4.8 (Unit 2) on page B 3/4 8-1 at the end of the sixth paragraph, add:
and Generic Letter 84-15. " Proposed Staff Actions to improve and Maintain Diesel Generator Reliability," July 2, 1984 This change is editorial in nature and reflects the current staff requirements for EDG testing. On this basis, it is acceptable.
3.0 STATE CONSULTATION
l In accordance with the Comission's regulations, the Georgia State official was notified of the proposed issuance of the amendments. The State official had no coments.
4..
16 -
4.0 CHVIR0f:ftENTAL CONSIDERATION The amendments change requiremar.'.s with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes surveillance requirements. The NRC staff has-determined that the emendments involyc no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individuci or cumulative occupational The Comission has previously issued a proposed finding radiation exposure, that the amendments involve no significant hazards considerationAccordingly,ndth a
.the anendments been no public coment on such filiding (55 FR 20354).
meet the eligibility criteria for categorical exclusion set forth in 10 CFR Pursuant to 10 CFR 51.22(b) no environmental impact statement'or 51.22( c)(9).
environmental assessment need be prepared in connection with the issuance of the amendments.
5.0 CONCLU$10N 4
The Comission has concluded, based on the considerations discussed above, that:
(1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed inanner, (2) such activities will be conducted in compliance with the Comission's regulations, and (3) the issuance of the amendments will not be inimical to the comon defense and security or to the health and safety of the public.
i Principal Contributor:
F. Burrows, SEl.8/ DST Date:
March 20, 1992 l
l l
.