Third Part 21 & Deficiency Rept,Item 95 Re Shop Welding Defects in Seismic I Pipe Hangers Supplied by Bergen- Patterson & Item 72 Re Undersized Skewed Tee Fillet Weld on Hangers.Final Rept by 841201
ML20087M549
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/21/1984
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-196, REF-PT21-84-259-000 72, 95, PT21-84-259, PT21-84-259-000, NUDOCS 8403300043
Download: ML20087M549 (5)


Text

^

. iD

.CP&L Carolina Power 4 Ught Company s:nz:en:3fcznew-u P. O. Box 101, New 11111, N. C. 21562 March 21,1984 Mr. James P. O'Reilly NRC-196 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30303 CAROLIN A POWER & LIGHT COMPANY '

SilEARON IIARRIS NUCLEAR POWER PLANT 1986 - 900,000 KW - UNIT 1 SHOP WELDING DEFICIENCIES IN SEISMIC I PIPE HANGERS SUPPLIED BY BERGEN-PATERSON, ITEM 95 UNDERSIZE SKEWED TEE FILLET WELDS ON SEISMIC I PIPE HANGERS, ITEM 72

Dear Mr. O'Reilly:

Attached is our third interim report on the subject items which were deemed reportable per the provisions of 10CFR50.55(e) and 10CFR, Part 21, on August 13, 1982 (Item 95) and November 5,1982 (Item 72). The purpose of this report is to inform you of changes which have occurred since our second interim report dated October 3, 1983. Carolina Power and Light Company is pursuing this matter, and it is currently projected that corrective action and submission of the final report will be accomplished by December 1,1984.

Thank you for your consideration in this matter.

Yours very truly, f  :'&~

R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/sh Attachment ec: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. R. C. DeYoung (NRC) 0FFICIAL COP ^

Q 8403300o43 040321

oaanocxosooog pt, 5[T
  1. t

CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT UNIT NO.1 INTERIM REPORT NO. 3 SHOP WELDING DEFICIENCIES IN SEISMIC I PIPE HANGERS SUPPLIED BY BERGEN-PATERSON ITEM 95 UNDERSIZE SKEWED TEE FILLET WELDS ON SEISMIC I PIPE HANGERS ITEM 72 MARCH 21,1984 -

l l

l REPORTABLE UNDER 10CFR50.55(e)

REPORTABLE UNDER 10CFR21 l

1 l

\

1

~

SUBJECT:

D:ficient shop welds on pipe hang:rs previously acc pted by Bergen-Paterson (B-P) and Ebasco Welding Inspectors.

ITEM: Seismic Pipe Ilangers SUPPLIED BY: Bergen-Paterson Pipe Support Corporation, Laconia, New llampshire NATURE OF DEFICIENCY:

1. Missing and undersized welds
2. Cosmetic weld defects
3. Undersized skewed tee welds
4. Deficient welds accepted by B-P inspectors and Ebasco Vendor Quality Assurance (VQA) inspectors DATE PROBLEM OCCURRED: Prior to October 1,1982 DATE PROBLEM i REPORTED: On August 13,1982 CP&L (Mr. N. J. Chiangi) notified the NRC (Mr. A. Hardin) that this item (Item 95) was reportable under 10CFR50.55(e) and 10CFR, Part 21. In our November 5,1982 letter, CP&L (Mr. R. M. Parsons) notified the NRC (Mr. J. P.

O'Reilly) that this item (Item 72) was reportable under 10CFR50.55(e) and 10CFR, Part 21.

SCOPE OF PROBLEM: Seismic Category I pipe hangers which were inspected at the source of fabrication prior to October 1,1982.

SAFETY IMPLICATIONS: Deficient welds could cause a safety-related pipe hanger to fall under seismic conditions. As a result, if not corrected, they could adversely affect the safe operation of this facility.

However, no hangers evaluated to date with the above type deficiencies have been found to adversely affect the safe operation of this facility.

REASON THE DEFICIENCY IS REPORTABLE: The conditions reported in Item 95 and item 72 represent breakdowns in B-P and Ebasco QA programs which allowed supports to be shipped with welds which were not in accordance with design criteria. This incident was identified as reportable under 10CFR50.55(e) and 10CFR, Part 21, due to the extensive evaluation required and the breakdown in the QA programs.

CORRECTIVE ACTION: 1. Hangers with shop weld deficiencies were identified during the following processes:

A. Receipt Inspection.

B. Inspection in the warehouse prior to hanger issuance to the field.

C. Inspection in the field of installed hangers which had not been previously inspected by CP&L for shop weld deficiencies (does not include those hangers that were in Reinspection - See D).

CORRECTIVE ACTION (cont'd.):

D. Reinspection of pipe hangers that were installed or partially installed and inspected prior to June 26, 1982. This includes the 347 hangers which were previously reinspected as part of the Corrective Action to NRC Report 50-400/82-03. The June 26, 1982 date was selected because the QC weld inspection program was expanded to include shop welds. 346 hangers which had been installed and inspected prior to June 26,1982 were removed, voided, or declassified to non-seismic by a subsequent drawing revision and therefore were not reinspected.

2. 449 hangers with defective shop welds were identified by processes A and B (see above).

1862 hangers were reinspected by Processes C and D. 728 were identified with shop weld deficiencies.

l Deficiencies were resolved as follows:

Welds were cut out.

Design drawing revisions were issued as a result of Engineering evaluation.

Welds were reworked and upgraded to meet the acceptance criteria of FCR-H-979.

Some hangers ware on hold due to engineering problems which precluded rework at this time.

These hangers will be dispositioned in accordance with the appropriate drawing revision when the engineering holds are removed.

3. Those hangers remaining in the warehouse and which were received prior to implementation of the 100% Ebasco VQA weld inspection are being controlled as follows:
a. Hangers are on QA Hold; no credit is being taken for shop welds (al) are assumed to be unaccepted).
b. When the hanger is requisitioned for field installation, it is inspected for compliance to the site weld acceptance criteria.

c.- Weld deficiencies are identified on a Seismic Weld Data Report (SWDR) for repair or rework. (The SWDR will become a part of the work package and used to document weld inspections.)

- d. The hanger is released for disposition of any weld deficiencies.' Welds will be reworked, inspected,' and

. acceptance documented on the SWDR.

. - - . _ _ _ _ _ _ _ _ 1

a PREVENTIVE MEASURES TAKEN TO AVOID FURTHER NONCOMPLIANCE: 1. Field Change Request (FCR)11-979 was developed and issued to provide weld inspection acceptance criteria for both field and shop welds based on the AWS Dl.1 code and B-P design criteria.

2. Ebasco VQA began performing in-process inspections and 100% inspection of hanger welds on October 1,1982. This is to be performed throughout the remainder of the B-P purchase order.
3. Ebasco VQA management regularly visits the B-P Laconia facility to confer with the Ebasco VQA representative and to witness the VQA inspector's activities.
4. B-P welders and inspectors and Ebasco VQA inspectors have received additional training in weld acceptance criteria.
5. 100% shop weld inspections will continue until all shop welds are inspected by our quality control organization.

FINAL REPORT: Corrective action has been completed on all active hangers.

Those hangers on engineering hold will be reinspected and reworked when they become active again, or they will be cancelled if they are voided. For this reason, we cannot close this item until December 1,1984.