._

B ALTIMortE GAS AND l ELECTRIC CHARLES CENTER

  • P.O. BOX 1475
  • BALTIMORE. MARYLAND 21203 1475 R E DENTON QENERAL MANAGER CALWRi CLNTS October 11,1991 U. S. Nuclear Regulatory Commission j

Washington,DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50 317 & 50 318 September 1991 Operating Data Reports Gentlemen:

The subject reports are being sent to you as required by Technical Specification 6.9.1.6.

Should you have an) further questions regarding this matter, please contact hit. Bruce Afrowca at (301) 2(4-39S9.

Mery4uly yours,

'N n

k hM RED /LBS/bjd Attachments cc:

D. A. Brune, E quire J. E. Silberg. Esquire R. A.Capra, NRC D. G. Mcdonald, Jr., NRC T. T. Martin, NRC L E. Nicholson, NRC R. L McLean. DNR J. IL Walter, PSC R. A. Ilartfield,.NRC J. Wheelock, INPO 6

9T10160z41 ylvysu

/

j PDR ADOCK 05000319-l R

PDN f li

Document Control Desk

+

Odtober 11,1991 Page 2 bee:

M. J. Micrnicki W. R. Corcoran C. H. Cruse /P. E. Kati.

R.C.DeYoung R. M. Dauglass/R. F. Ash R. P. lleibelff. N. Pritchett C. P. Johnson C. C. Lawrence, Ill/A. R. Thornton R. B. Pond, Jr./S. R. Buxbaum, Jr.

L E. Russell /R. E. Denton/J. R. Lemons W. A.Thornton/E,I. Bauereis A. B. Anuje G. L. Detter D. V. G raf R. C. Johnson B. S. Mon:gomery R. E Nagel K. R. Neddenien R. C. L Olson P. A. Pieringer Technical Library L O. Wenger E. K. Bewley J. E. Ringsdorf, Jr.

J. F. Lohr P. G. Chabot/U. B. Mrowca P. A. File /K. J. Allor

1. A. Liberatore/C. Behnke D. Song F. Yost File # 60.01.13 NRC Chrono File

e

eoo*************************************************************************
UNIT 1=

OPERATING DATA REPORT seco*****************************a*******************************************

Docket No. 50-317 October 11, 1991 Prepared by-Leo Shanley Telephone:(301)260-6744 OPERATING STATUS

1. UNIT NAME Calvert Cliffs Unit 1
2. REPORTING PERIOD SEPTEMBER 1991
3. LICENSED THERMAL POWER (MWT) 2700
4. NAMEPLATE-RATING (GROSS MWe) 918 5.xDESIGN ELECTRICAL' RATING (NET MWe) 845 6.' MAXIMUM. DEPENDABLE CAP'Y (CROSS MWe) 860 1

-7..-MAXIMUM DEPENDABLE CAP'Y'(NET MWe) 825 8.-CHANGE IN CAPACITY RATINGS none

.9.

POWER LEVEL TO WH1CH RESTRICTED n/a

10. REASONS;FOR RESTRICTIONS n/a Cumulative This month Year-to-Date to Date Ill. HOURS IN~ REPORTING PERIOD 720 6,551 143,748 c12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,701.0 101,217.8
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 3,019.4
14. HOURS GENERATOR ON LINE 720.0 4,672.2 98,962.0

.15. UNITLRESERVE SHUTDOWN HOURS 0.0 0.0 0.0

- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,924,121-12,170,590 249,201,304

17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 624,233 4,016,043 82,846,810
18. NET ELECTRICAL ~ ENERGY GENERATED (MWH) 598,321 3,847,046 78,737,223
19s UNIT SERVICE FACTOR.

100.0 71.3 68.8

20. UNIT AVAILABILITY FACTOR 100.0 71.3 68.8-
21. UNIT CAPACITY FACTOR (USIMO MDC NET) 100.7 71.2 66.4 12 2. UNIT CAPACITY. FACTOR (USINC DER NET) 98.3 69.5 64.8
23. UNIT FORCED' OUTAGE RATE-0.0 12.2 9.5

-24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS ~(TYPE, DATE AND DURATION):

Refuel / Test, March 6, 1992 for 77 days 25'..IF SHUTDOWN ~AT.END'OF REPORT PERIOD,

' ESTIMATED DATE OF START-UP:

N/A 9

y-y

,w--

ie

-em-er e-

+

UNIT SIIUTDOWNS AND POWER REDUCTIONS DOCKET NO.

NI317 UNITNAME Cahert Clifis-U1 DATE October 11.1991 COMPLETED BY Leo Shaniev WT FPHONE 0 011260 4744 REPORT MONTII September 1991 l

MImIOD OF CA115E & CORRECITVE SIIUTI1NG LICENSEE DURAT10N DOWN EVENT SYSTEM COMPONENT ACTION TO d

CODES PREVENT RECURRENCE I

REAC DR3 REPORT #

CODE NO.

DATE TYPEI (IlOURS)

REASON There were no significant power reductions this month.

i l

l L.

7 l

l 9

5 l

1, i

u 4 Exhibit F -Instructions 3 Method:

2 Reason:

I F:

Forced 1-Manual for Preparation of Data S:

Scheduled A-Eqtdpment Failure B-Maintcaance or Test 2-Manual Scram.

Entry Sheets for License 3-Automatic Scram-Event Report (LER) File C-Refueling 4-Continucd (NUREG-e 61)

D Regulatory Restriction E-OperatorTraining & License Examination 5-Reduced Load 5 Exhibit II-Same Source l

F-Administrative 9-Other G-Operational Error II-Other

.. ~. ~ ~ - ~.

4 ff.

1 '

AVERAGE' DAILY-UNIT POWER LEVEL

-oco*********************************************************************

Docket No. 50 317-Calvert Cliffs-Unit.No.

1-

~

October 11,.1991 Completed.by Leo Shanley

-Telephone:.(301) 260-6744 e

SEPTEMBER 1991 1-. m Average Daily Power Level Average Daily Power Level Day-(MWe-Net)

Day (MWe-Net)

'3 1=

830-17 833

-2

833 18 834 3

835 19 835 4

835 20 840 5

833 21 842 6-833 22 823=

-7 832-23 840 8

-833' 24.

840 9

834 25, 841 10-834 26 84"

-11

'833 27 844 g

12 833 28 844 13 834 29

~776 14-835 30 759 15 834 16 ' -

e33 n+--

n a4,-

,a

.nv e

e--n-u--N'-

em-4

,.,-,a-N c,..,-

~q

~

DOCKET d'50-317 CALVERT CLIFF 0 UNIT 1 October 11,1991

SUMMARY

OF OPERATING EXPERIENCE September 1991, ne unit began the month at 100% powcr (R30 MWe).

Power was reduced to 94% (790 MWe) from 0520 to 1440 on September 22 to perform testing on the Auxiliary Feedwater (AFW) System.

Power was reduced to 93% (770 MWe) at 0520 on September 29 to perform AFW testing and clean Main Condenser 11 and 13 waterboxes. Return to full power was delayed due to the failure of 13A Waterbox Inlet MOV.

The unit ended the month at 93% power (760 MWe).

l l

l l

A October 8, 1991-EEEUNG INFORMATION REQR$I 1.

liame of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 1.

2, Scheduled date for next refueling shutdown:

March 6, 1992.

3.

Scheduled date for restart follownng refueling: day 23, 1992.

4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

Resumption of operation after refueling will require changes to Technical Specifications. The anticipated changes will effect consistency between the Unit ? Cycle 9 Tech Specs and the Tech Specs for Unit 1 Cycle 11, 5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

November 8, 1991.

6.

Important licensing considerations associated with t' refueling.

None identified at this time.

7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.

(a) -217.

(b) 1326.

' Spent fuel pools are comon to Units 1 and 2.

8.

(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase ia licensed storage capacity that has b requested or is planned, in number of fuel assembites.

l (a) 1830.

(b) 2880.

L 9.

.The projected date of the last refueling that can be discharged to the l

Spent Fuel Pool assun,ing the present licersed capacity and maintaining space for one full core off-load.

March 1992.

I

l owo*************************************************************************

UNIT 2 OPERATING DATA REPORT occ*********************************************************=***************

Docket No. 50-318 October 11, 1991 Prepared by Leo Shanley Telephone: (301) 260-6744 OPERATING STATUS

1. UNIT NAME Calvert Cliffs Unit 2
2. REPORTING PERIOD SEPTEMBER 1991 3.

LICENSED THERMAL POWER (MWT) 2700

4. NAMEPLATE RATING (GROSS MWe's 918 5.

DESIGN ELECTRICAL RATING (NET HWe) 845 6.

MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860 7.

MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825 8.

CHANGE IN CAPACITY RATINGS none 9.

POWER LEVEL TO WHICH RESTRICTED n/a

10. REASONS FOR RESTRICTIONS n/a Cumulative This month Year-to-Date to Date
11. HOURS IN REPORYING PERIOD 720 6,551 127,103
12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 3,298.5 90,735.8
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 1,296.6
14. HOURS GENERATOR ON LINE 720.0 3,173.9 89,402.8
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,921,598 8,162,073 226,551,491
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 618,901 2,614,427 74,899,059
18. - NET ELECTRICAL ENERGY GENERATED (MWH) 593,369 2,498,929 71,541,500
19. UNIT SERVICE FACTOR 100.0 48.4 70.3
20. UNIT AVAILABILITY FACTOR 100.0 48.4 70.3
21. UNIT CAPACITY FACTOR (USING MDC NET) 99.S 46.2 68.2
22. UNIT CAPACITY FACTOR (USING DER NET) 97.5 45.1 66.6
23. UNIT FORCED OUTAGE RATE 0.0 13.0 5.6 il'
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

Mai.tenance/ Test, October 18, 1991 for 34 days

-25.

IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

N/A 1

UNIT SIIUTDOWN3 AND POWER REDUCTIONS DOCr*k':.T NO.

3 318

~

[

UNITNAME Cahrrt Clifts-U2 DATE October 1 i.1W1 COMPLETED BY Leo Shaniev l

TELEPHONE 02n!)2fM744 l

REPORTMONTII Septemberla91 l

l METilOD OF S!!UTTING LICENSEE CAUSE & CORREC1IVE DURATION DOWN EVENT SYSTEM COMPONENT ACTIONTO N O.

DATIE TYPEI (IIOURS)

REASON 2 REACTOR 3 REPORT

  • CODE 4 CODES PREVENT RECURRENCE There were no signifr_ art power reductkms this month.

I 1 F:

Forced 2 Reason:

3 Method:

4 Exhibit F-Instructions S:

Scheduled A-Equipment Failure 1-Manual for Preparation of Data B-Maintenance er Tst 2-Manual Scram.

Entry Sheets for License C-Refueling 3-Automatic Scram.

Event Report (LER) File D-Regulatory Restriction 4-Continued (NUREG-0161)

E-Operator Training & License Examination 5-Reduced Lead F-Administrative 9-Other S Exhibit H-Same Source G-Operational Error H-Other

= -

r

-...n

~

m 9-

. AVERAGE DAILY: UNIT POWER - LEVEL ~

ce&*********************************************************************

Docket No. 50-318 Calvert Cliffs Unit No. 2 October.11, 1991 Completed by-Leo Shanley Telephone:.(301) 260-6744 4

SEPTEMBER 1991.-

Average Daily Power Level Average Daily Power. Level

,MWe-Net).

Day

-(MWe-Net)

(

Dhy 1

830 17 829 2

834-18 830 a

i L

3-

-833 19 829 li L

4 833-

-20 825' P

t 5

-832 21-695 y

6 -'

831 22 754 7-

-833'

'43 837 L-8

'834 24 836 L

'9.

833'-

25 838 g

o-

.10

.833:

26

=840 ln-11' 832:

27 840-p

!f 12l 830:

28-840 L

13' 832' 29 783-

. r:

l J-

"14 831-30.

837 i?

15 831 s

16.

'830 f

i.

I li l

I

+

r r.

DOCKET #50 318 CALVERTCLIFFS UNIT 2 October 11,1991

SUMMARY

OF OPERATING EXPERIENCE September 1991 The unit began the month at 100% power (830 MWe).

Power was reduca.1 to 93% (755 MWe) fiom 0210 to 0535 on September 20 to investigate clogging of 23A Amertap.

Power was reduced to 88% (720 MWe) nt 0400 on September 21 to test Main Turbine Control Valves and clean Main Condenser waterboxes. Power was further reduced to 8(We (W) MWe) at 0610 due to the failure of 21 Moisture Separator Reheater Reheat Stop Valve (20RL) to reopen following valve testing. The test solenoid valve for 20RL.wr.s replaced to correct the problem and power was returned to 88% (720 MWe) at 2210. 'the unit returned to full power (830 MWe) at 2020 on September 22.

Pcwer was reduced to 88% (730 MWe) from 0630 to 1725 on Septemh r 29 for Auxiliary Feedwater testing.

The unit ended the month nt 100% power (835 MWe),

i 1

4 4

~*

I October 8, 1991 REEMELili9 1NE0]LIMILQtLAEQUE11 1.

Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 2.

2.

Scheduled date for next refueling shutdown:

March 5, 1993.

3.

Scheduled date for restart following refueling:

May 17, 1993.

4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

Not identified at this time.

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

November 17, 1992.

6.

Important licensing considerations associated with the refueling.

None identified at this time.

7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.

(a) 217.

(b) 1326.

Spent fuel pools are conmon to thits 1 and 2.

8.

(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.

(a) 1830.

(b) 2880.

9.

The projected date of the last refueling that can be discharged to the Spent fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.

March 1992.

_