Final Deficiency Rept,Item 167 Re Conflict Between Pipe Wall Thickness Specified on Ebasco Stress Isometrics & Shown on Piping Line List.Initially Reported on 840314.Item Not Reportable Per 10CFR50.55(e)
ML20084H155
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 04/16/1984
From: Chiangi N
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
167, MQAH-84-168, NUDOCS 8405070463
Download: ML20084H155 (1)


Text

. . . _ _ - _ _ - _ - _ _ _

CP&L Carolina Power & Light Company P. O. Box 16 ina 27562 April 16, 1984 FILE: SH N-2/18 MQAH 84-168 Item 167 -

Mr. James P. O'Reilly United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest Atlanta, Georgia 30303 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 MINIMUM WALL FOR SAFETY RELATED PIPING

Dear Mr. O'Reilly:

This is to confirm the April 13, 1984 telephone conversation between Mr. K. V. Hate' (CP&L) and Mr. A. Hardin (NRC) . Mr. Hardin was informed that the March 14, 1984 potentially reportable item, pertaining to the conflict between the pipe wall thickness specified on the Ebasco stress isometrics and that shown on the piping line list to which mcterial is manufactured / installed, has been evaluated and considered not to be reportable per the provisions of 10CFR50.55(e) and 10CFR, Part 21.

Thank you for your consideration in this matter.

Yours very truly,

/AD NJC/mt s ,

l$ f klfff cc: Mr. R. C. DeYoung N. J. Chiangi - Manager Mr. G. Maxwell Quality Assurance / Quality Control Mr. R. L. Prevatte Harris Plant i