Deficiency Rept,Item 155 Re Min Wall Thickness on Chill Water Return Valve Mfg by Itt Hammel Dahl Co.Initially Reported on 831121.Deficiency Determined Not Reportable Per 10CFR50.55(e) & 10CFR21
ML20083B148
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 12/09/1983
From: Chiangi N
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, 155, MQAH-83-389, NUDOCS 8312200541
Download: ML20083B148 (1)


Text

.- - - - - - - --- -- - - - - - - - - _ - - - - - - - -

Cp&L Carolina Power & Light Company P. O. Box 165. New Hill, North Carolina 27562 December 9, 1983 FILE: SH N-2/18 MQAH 83-389 Item 155-

.Mr.:' James P. O'Reilly

--United States Nuclear Regulatory Commission.

Region II 101 Marietta Street, Northwest Atlanta, Georgia 30303.

SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO.'1 DOCKET No. 50-400

~ CHILL WATER RETURN VALVE - MINIMUM WALL

Dear Mr. O'Reilly:

This is to. confirm the December 8, 1983 telephone conversation between Mr. N.' J. Chiangi (CP&L) and Mr. P. Bemis (NRC) . Mr. Bemis was informed that the November -21,1983 potentially reportable item, pertaining to a possible violation of minimum wall thickness on a valve (3CX-W16-5A-1) manufactured by ITT Hanunel Dahl Company, has been evaluated and considered not to be reportable per the provisions of 10CFR50.55(e) and 10CFR, Part 21.

Thank.you for your consideration in this matter.

Yours very truly, NJC/mt b. -

cc: Mr.-R. C. DeYoung N. J. iangi - Manager Mr. G. Maxwell Quality Assurance / Quality Control