Interim Deficiency Rept,Item 143 Re Weld Deficiencies in Sections of Ducts CC-1 & CC-2 & Transformers 1D1,1D2,1E1 & 1E2 from Gould & Brown-Boveri.Util Awaiting Vendor Response.Also Reportable Per Part 21
ML20080P172
Person / Time
Site: Harris  Duke Energy icon.png
Issue date: 09/29/1983
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-124, REF-PT21-83 10CFR-050.55E, 10CFR-50.55E, 143, NUDOCS 8310060336
Download: ML20080P172 (1)


Text

- -

CP&L Carolina Power & Light Company

'D$C A g ,. 4 P. O. Box 101, New Hill, N. C. 27562 September 29,1983 Mr. James P. O'Reilly N RC-124 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30303 CAROLINA POWER & LIGilT COMPANY SHEARON IIARRIS NUCLEAR POWER PLANT 1986 900,000 KW - UNITS 1 & 2 BUS DUCT AND TRANSFORMER WELD DEFICIENCIES, ITEM 143

Dear Mr. O'Reilly:

On September 2,1983, Mr. K. V. Hate' notified the NRC (Mr. P. Bemis) of a potentially reportable item per the provisions of 10CFR50.55(e) and 10CFR, Part 21.

The NRC was informed that vendor weld deficiencies were noted by CP&L in sections of Bus Duct numbers CC-1 and CC-2 and Transformer numbers IDI, ID2, IEl, and IE2 received from Gould-Brown-Boveria, Chalfont, Pennsylvania.

CP&L is currently investigating this item and awaiting a response from the vendor.

It is projected that the vendor will require until January 1984 to respond with their evaluation. For this reason, we will require until January 13,1984 for submitting a report on the reportability of this item.

Thank you for your consideration in this matter.

Yours very truly, g A:M R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant l RMP/sh cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)