Southem Califomia Edison Company 23 PARKER STREET IRVINE. CALIFORNIA 92718 December 29, 1994 WALTER C, MARSH WNAGER OF NUCL F AR R,GULATORY AFF AIR $
(714)454-4403 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C.
20555 Gentlemen:
Subject:
Docket Nos. 50-361 and 50-362 Eleventh Edition of the Integrated Implementation Schedule (IIS)
San Onofre Nuclear Generating Station Units 2 and 3
Reference:
Letter from W. C. Marsh (SCE) to Document Control Desk (NRC),
dated July 11, 1994; Tenth Edition of the Integrated Implementation Schedule (IIS).
Enclosures 1 through 3 provide the Eleventh Edition of the Integrated Implementation Schedule (IIS) for the San Onofre Nuclear Generating Station (SONGS), Units 2 and 3. updates the Schedule A, B, and C projects listed in the Tenth Edition of the IIS (referenced) for SONGS 2 and 3. provides the current Schedule A, B, and C projects for SONGS 2 and 3 for Cycles 7, 8, and 9. lists the ongoing evaluations for major issues for SONGS 2 and 3.
The Westinghouse Analytical Ranking Program (WARP) was not used to rank the relative safety significance of each Schedule A and B modification because their implementation schedules have been established in separate correspondence.
If you have any questions on the Eleventh Edition of the San Onofre Units 2 and 3 IIS, please let me know.
Very truly yours,
$0h Enclosures cc:
L. J. Callan, Regional Administrator, NRC Region IV A. B. Beach, Director, Division of Reactor Projects, Region IV K. E. Perkins, Jr., Director, Walnut Creek Field Office, NRC Region IV J. A. Sloan, NRC Senior Resident Inspector, San Onofre Units 2 & 3 M. B. Fields, NRC Project Manager, San Onofre Units 2 and 3 f
9501040171 941229 PDR ADOCK 05000361 1
I P
PDR v -
t
ENCLOSURE 1 SCIIEDULE A, B, AND C UPDATES (10th Edition IIS dated 7/11/94)
. - 10th Edition IIS Schedule Updates Schedule A Updates Update Unit Due DCP Description Comments Date Number mmmmmmmes Add C
2/29/96 7044 Vehicle Security Rule change affecting Barriers 10 CFR 73 Schedule B Updates i
l Update Unit Due DCP Description Comments Date Number i
No Change 2
Cycle 8 6910 Upgrade Target Rock Generic Ixtter 91-15 Solenoid Valves No Change 2
Cycle 8 6988 Addition of Valves Generic Letter 89-04 and Drains for In Service Test Completed 2
Cycle 8 6999 Intake Structure SCE to NRC letters Security Barriers February 12, 1993 and July 15, 1993
, Schedule B Updates Update Unit Due DCP Description Comments Date Number mummmmmmmmmmmme No Change 2
Cycle 8 2060.00 Degraded Grid PCN 429 submittal Voltage to NRC September 30, 1993 No Change 3
Cycle 8 6910 Upgrade Target Rock Generic Letter 91-15 Solenoid Valves No Change 3
Cycle 8 6988 Addition of Valves Generic Letter 89-04 and Drains for In-Service Test Complete 3
Cycle 8 6999 Intake Structure SCE to NRC letters Security Barriers February 12, 1993 and July 15,1993 I
s
. Schedule C Updates Update Unit Due DCP Description Date Number unusammmmmmmmmmu-umummmmmmmma No Change 2
Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms From Cycle 2
Cycle 7 6605.08 Control Room Human Factors 7 to Cycle 8 Complete 2
Cycle 7 6742.07 CCW Seismic Makeup Complete 2
Cycle 7 6888.00 Modify 90-minute Emergency Control Room Lighting Battery Backup No Change 2
Cycle 7 6869 Auxiliary Feedwater Overspeed Trip Setpoint No Change 2
Cycle 8 6683.04 Snubber Reduction No Change N/A Cycle 8 2066.00 EOF Diesel Modification No Change 2
Cycle 8 6716.00 Modify Plant Monitoring System and core Operating Limit Supervisory System Back-up Computer System Schedule 2
Cycle 8 2005.00 In-containment Post Accident Monitoring Change C to Instrumentation Improvements B
No Change 2
Cycle 8 2012.00 F020 Filter Replacement No Change 2
Cycle 8 2061.00 Component Cooling Water Fuses No Change 2
Cycle 8 2063.00 Steam Generator Distribution Box Replacement
. Schedule C Updates Update Unit Due DCP Description Date Number mmmmmmmmmmmmmmm--
No Change 2
Cycle 8 2067.00 Main Steam Isolation Valve Bypass Line Modification No Change 2
Cycle 8 6735.03 Ladders and Platforms No Change 2
Cycle 8 6851.00 Replace Loose Parts and Vibration Monitoring System No Change 2
Cycle 8 6855.00 Install Removable Digital Polar Crane Controls l
No Change 2
Cycle 8 6864.00 Install Removable Refueling Machine Controls i
No Change 2
Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor No Change 2
Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation No Change 2
Cycle 8 6914.00 Turbine Governor Valve Modifications From Cycle 2
Cycle 8 6926.00 Replace Nuclear Monitoring Corporation 8 to 9 Radiation Monitors No Change C
Cycle 8 6933.00 Toxic Gas Isolation System Instrument Replacement No Change 2
Cycle 8 6946.00 Automatic Voltage Regulator Replacement Complete 2
Cycle 8 6963.00 Replace Circ Water Delta "T" Inst.
No Change 2
Cycle 8 6974.00 load Center Transformer Replacement
. Schedule C Updates Update Unit Due DCP Description l
Date Number i
i No Change 2
Cycle 8 6984.00 Ex-core Neutron Detectors Cancelled 2
Cycle 8 6986.00 Reorient / Replace Component Cooling Water j
Containment Isolation Valves J
No Change 2
Cycle 8 6990.00 Reactor Coolant Pump Design Changes No Change C
Cycle 8 7032.00 Replace HP1000 Computer and Meteorological Equipment Enclosure Complete C
Cycle 8 7034.00 Replace High Flow Makeup Demineralizer Chemistry Analyzers ADD C
Cycle 8 7041 800 MHz Cabinet Replacement ADD C
Cycle 8 2071 Instrument Air Modifications No Change 3
Cycle 7 6605.08 Control Room Human Factors No Change 3
Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms Complete 3
Cycle 7 6742.07 Component Cooling Water Seismic Makeup Complete 3
Cycle 7 6888.00 Modify 90-minute Emergency Control Room Lighting Battery Backup No Change 3
Cycle 7 6869 Auxiliary Feedwater Overspeed Trip Setpoint No Change 3
Cycle 8 6683.04 Snubber Reduction
-1
. l Schedule C Updates Update Unit Due DCP Description Date Number Schedule 3
Cycle 8 2005.00 In-containment Post Accident Monitoring Change C to Instrumentation Improvements B
No Change 3
Cycle 8 2012.00 F020 Filter Replacement No Change 3
Cycle 8 2061.00 Component Cooling Water Fuses No Change 3
Cycle 8 2063.00 Steam Generator Distribution Box Replacement No Change 3
Cycle 8 2067.00 Main Steam Isolation Valve Bypass Line Modification No Change 3
Cycle 8 6683.04 Snubber Reductions No Change 3
Cycle 8 6716.00 Modify Plant Monitoring System and Core Operating Limit Supervisory System Back-up 1
Computer Systems No Change 3
Cycle 8 6735.03 Ladders and Platforms No Change 3
Cycle 8 6851.00 Replace Loose Parts and Vibration Monitoring System No Change 3
Cycle 8 6855.00 Install Removable Digital Polar Crane Controls No Change 3
Cycle 8 6864.00 Install Removable Refueling Machine Controls No Change 3
Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor
En, closure 1 Schedule C Updates Update Unit Due DCP Description Date Number
-ummmmmmm-No Change 3
Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation No Change 3
Cycle 8 6914.00 Turbine Governor Valve Modifications From Cycle 3
Cycle 8 6926.00 Replace Nuclear Monitoring Corporation 8 to 9 Radiation Monitors No Change 3
Cycle 8 6946.00 Automatic Voltage Regulator Replacement Complete 3
Cycle 8 6963.00 Replace Circ Water Delta T Data Logger No Change 3
Cycle 8 6974.00 Load Center Transformer Replacement No Change 3
Cycle 8 6984.00 Ex-core Neutron Detectors Cancelled 3
Cycle 8 6986.00 Reorient / Replace Component Cooling Water Containment Isolation Valves No Change 3
Cycle 8 6990.00 Reactor Coolant Pump Design Changes ADD 2
Cycle 9 6863.05 Snubber Reduction - Phase VI ADD 3
Cycle 9 6863.05 Snubber Reduction - Phase VI
9 9
O O
O 1
ENCLOSURE 2 ELEVENTII EDITION IIS (SONGS 2 AND 3)
SONGS 2 & 3 Integrated Implementation Schedule Eleventh Edition Schedule A Unit Due DCP Description Comments Date Number C
2/29/96 7044 Vehicle Security Barriers Rule change affecting 10 CFR 73 unum l
Schedule B l
Unit Duc DCP Description Comments Date Number 2
Cycle 8 6910 Upgrade Target Rock Solencid Generic Ixtter 91-15 l
Valves l
2 Cycle 8 6988 Addition of Valves and Drains Generic Letter 89-04 for In-Service Test 2
Cycle 8 2005.00 In-Containment Post Accident SCE to NRC letter Monitoring Instrumentation March 28,1994 Improvements Note 1 2
Cycle 8 2060.00 Degraded Grid Voltage PCN 429 submitted to NRC September 30,1993 l
Enclosur6 2 l 1
i Schedule B Unit Due DCP Description Comments Date Number 3
Cycle 8 6910 Upgrade Target Rock Solenoid Generic Letter 91-15 Valves 3
Cycle 8 6988 Addition of Valves and Drains Generic Letter 89-04 for In-Service Test 3
Cycle 8 2005.00 In-Containment Post Accident SCE to NRC letter Monitoring Instrumentation March 28,1994 Improvements Note I f
Note 1:
This modification will be completed by the end of the Cycle 9 refueling outage, as committed in the March 28,1994 letter. Edison's internal schedule is to complete this modification in Cycle 8.
r Schedule C Unit Due Date DCP Number Description m mmmmmemmmmmmmmmmmumummmmmmmmmmmmma i
2 Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms 2
Cycle 7 6869 Auxiliary Feedwater Overspeed Trip Setpoint 2
Cycle 8 6605.08 Control Room Human Factors
. 2 Schedule C Unit Due Date DCP Number Description mmmmun 2
Cycle 8 6683.04 Snubber Reduction N/A Cycle S 2066.00 EOF Diesel Modification 2
Cycle 8 6716.00 Modify Plant Monitoring System and Core Operating Limit Supervisory System Back-up Computer System 2
Cycle 8 2012.00 F020 Filter Replacement 2
Cycle 8 2061.00 Component Cooling Water Fuses 2
Cycle 8 2063.00 Steam Generator Distribution Box Replacement 2
Cycle 8 2 % 7.00 Main Steam Isolation Valve Bypass Line Modification 2
Cycle 8 6735.03 Ladders and Platforms 2
Cycle 8 6851.00 Replace Imose Parts and Vibration Monitoring System 2
Cycle 8 6855.00 Install Removable Digital Polar Crane Controls 2
Cycle 8 6864.00 Install Removable Refueling Machine Controls 2
Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor 2
Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation 2
Cycle 8 6914.00 Turbine Governor Valve Modifications 2
Cycle 8 6946.00 Automatic Voltage Regulator Replacement
)
, Schedule C Unit Due Date DCP Number Description 2
Cycle 8 6974.00 lead Center Transformer Replacement (SR portion completed) 2 Cycle 8 6984.00 Ex-core Neutron Detectors 2
Cycle 8 6990.00 Reactor Coolant Pump Design Changes C
Cycle 8 6933.00 Toxic Gas Isolation System Instrument Replacement C
Cycle 8 7032.00 Replace HP1000 Computer and Meteorological Equipment Enclosure C
Cycle 8 7041 800 MHz Cabinet Replacement I
C Cycle 8 2071 Instrument Air Modifications 3
Cycle 7 6605.08 Control Room Human Factors 3
Cycle 7 6191.00 Turbine Building Sump Radiation Monitor Low Flow Alarms 3
Cycle 7 6869 Auxiliary Feedwater Overspeed Trip Setpoint 3
Cycle 8 6683.04 Snubber Reduction 3
Cycle 8 2012.00 F020 Filter Replacement 3
Cycle 8 2061.00 Component Cooling Water Fuses 3
Cycle 8 2063.00 Steam Generator Distribution Box Replacement 3
Cycle 8 2 % 7.00 Main Steam Isolation Valve Bypass Line Modification
. Schedule C Unit Due Date DCP Number Description summmmmmm 3
Cycle 8 6683.04 Snubber Reductions 3
Cycle 8 6716.00 Modify Plant Monitoring System and Core Operating Limit Supervisory System Back-up Computer Systems 3
Cycle 8 6735.03 Ladders and Platforms 3
Cycle 8 6851.00 Replace Loose Parts and Vibration Monitoring System 3
Cycle 8 6855.00 Install Removable Digital Polar Crane Controls 3
Cycle 8 6864.00 Install Removable Refueling Machine Controls 3
Cycle 8 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor 3
Cycle 8 6885.00 Replace Turbine Plant Secondary System Chemistry Instrumentation 3
Cycle 8 6914.00 Turbine Governor Valve Modifications 3
Cycle 8 6946.00 Automatic Voltage Regulator Replacement i
3 Cycle 8 6974.00 lead Center Transformer Replacement 3
Cycle 8 6984.00 Ex-core Neutron Detectors 3
Cycle 8 6990.00 Reactor Coolant Pump Design Changes 2
Cycle 9 6863.05 Snubber Reduction - Phase VI 2
Cycle 9 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors
~
i h
! l l
Schedule C Unit Due Date DCP Number Description 3
Cycle 9 6863.05 Snubber Reduction - Phase VI 3
Cycle 9 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors l
)
ENCLOSURE 3 ONGOING EVALUATIONS OF MAJOR ISSUES (SONGS 2 AND 3)
ONGOING EVALUATIONS OF MAJOR ISSUES (SONGS 2 and 3) i GL 88-20, SUP 4 Individual Plant Examination of External Events (IPEEE), to be completed by 6/01/95.
GL 89-10 The initial safety related Motor Operated Valve (MOV) Testing and I
Surveillance will be completed for Units 2 and 3 by the end of their respective Cycle 8 refueling outages. Periodic verifications of MOV operability will follow.