Second Interim Deficiency Rept Re Welding in Class IE Auxiliary Control Panel (Item 125).Initially Reported on 830426.Welds Repaired Per Field Change Request FCR-AS-2879. Final Rept Expected by 830923
ML20077F853
Person / Time
Site: Harris 
Issue date: 07/25/1983
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-100 10CFR-050.55E, 10CFR-50.55E, NUDOCS 8308030087
Download: ML20077F853 (4)


Text

.

llc!Oy,.

A.

83 [/[

' n i*

c t/

Carolina Power & Light Company y

  • +-

4

    • gg P. O. Box 101, New Hill, N. C.

27562 July 25, 1983 Mr. James P. O'Reilly NRC-100 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite.2900)

Atlanta, Georgia 30303 CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT 1986 900,000 KW - UNITS 1 & 2 WELDING DEFICIENCI2S IN CLASS lE AUXILIARY CONTROL PANEL, P"RCHASE ORDER NY-435190, ITEM 125

Dear Mr. O'Reilly:

Attached is our second interim report on the subject item which was deemed reportable per the provisions of 10CFR50.55(e) on April 26, 1983. CP&L is pursuing this matter, and it is currently projected that corrective action and submission of the final report will be accomplished by September 23, 1983.

Thank you for your consideration in this matter.

Yours very truly, R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/sh Attachment cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)

Mr. R. C. DeYoung (NRC)

(

8308030087 830725

.i gDRADOCK05000g

//

i

{

CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT UNIT NO. 1 INTERIM REPORT NO. 2 WELDING DEFICIENCIES IN CLASS lE AUXILIARY CONTROL PANEL ITEM NO. 125 JULY 22,1983 REPORTABLE UNDER 10CFR50.55(e) i f

i

(

i t

i

o s

1 6-SUBJE CT:

Shearon Harris Nuclear Power Plant Unit' l 10CFR50.55(e) reportable deficiency in the Auxiliary Control-Panel supplied under Purchase Order NY-435190 ITEM:

Structural welding SUPPLIED BY:

. Reliance Electric Company,. Stone Mountain, Georgia

. NATURE OF DEFICIENCY:

The subject Unit 1 equipment has been received at the site.

Several welding deficiencies were noted when the-equipment was inspected as compared to the vendor drawings.

DATE PROBLEM-

~

OCCURRED: -

-The problem was identified during receipt inspection on March 17, 1983.

DATE PROBLEM' REPORTED:

On April 1,1983, CP&L '(Mr. K. V. Hate') notified the NRC (Mr. A. Hardin) that this item was potentially reportable under 10CFR50.55(e).

On April 26, 1983, CP&L (Mr. N. J. Chiangi) notified the NRC (Mr.~ A. Hardin) that this item was reportable under 10CFR50. 55(e).

4 SCOPE OF PROBLEM:

'The equipment was manufactured in three (3) sections.

It.

will be bolted together and installed as a single unit.

Deficient. welds were identified in each section; eight (8) welds, total.

1 SAFETY IMPLICATIONS:

Seismic qualification of the subject panel is required to assure structural-integrity during a seismic event.

Safety-related components are located in the cabinet; i-thus, structural failure would jeopardize operation of.

[

the safety-related equipment.

REASON DEFICIENCY IS REPORTABLE:. Welding inspection at the site was done using the vendor's QA manual (QCP 5.3).

Deficient welds did not adhere to i

the manual.

.. -.,. _. ~... - -.. - _.. _. _ -,,,...

l CORRECTIVE A CTION:

CP&L originated a Field Change Request (FCR-AS-2879) to have the welds repaired by site personnel. The welds have been repaired.

The vendor has been given a copy of the weld deficiency report, the rework done, and has been requested to provide comment and an analysis.

CP&L letter with this information and request is HO-83158 dated May 9,1983.

PREVENTATIVE ACTION:

The vendor has been instructed to rigorously follow his QA manual for Unit 2 equipment.

FINAL REPORT: A final report will be issued when the vendor completes his comments and analysis. Efforts to complete this analysis have been delayed by the vendor's external analyst facility. Completion is scheduled for August 31, 1983.

A final report will he issued after CP&L review.

Scheduled report date is September 23, 1983.