ggeec'a'nds CML Carolina Power & Light Company g'j jl}{. b ox 101, New hill, North Carolina 27562 July 15, 1983 U
MQAH 83-177
~'
FILE:
SH N-2/18 j,
Ite n 121
~
x O'Reilly Mr;_ Janes,Pp United Statea Nuclear Regulatory Ccimmission Region II
-101 Marietta Street, Northwest Atlanta, Georgia 30303 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET UO. 50-400' WELDING DEFICIENCIES IN THE MAIN STEAM /FEEDWAIER SUPPORT FRAMES r.
,a
Dear.Mr. O'Reilly:
a This is to confirm the July 15, 1983 telephone conversation between Mr. N.~J. Chiangi and Mi. A. Hardin.
Mr. Hardin was informed that the March 18, 1983 potentially reportable item, pertaining to two Main 4 Steam /Feedwater Support Frames (Nos. C-1-189 and C-1-195) that were received and accepted from PX' Engineering and were placed on hold due to information received from Ebasco (on March 17, 1983) that Frame No.
C-1-188 scheduled for SHNPP had welds that were " slugged", has been evaluated and considered not to be reportable per the provisions of 10CFR50.55(e) and 10CFR Part 21.
Thank you for your consideration in this matter.
Yours very truly, i
~ NJC/mt Q,
cci Mr. R. C. DeYoung N. J.