ML20073Q806

From kanterella
Jump to navigation Jump to search
Elem Diag:Reactor Protection System. Sheet 7. Rev Date Illegible
ML20073Q806
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 04/13/1983
From:
GENERAL ELECTRIC CO.
To:
NIAGARA MOHAWK POWER CORP.
Shared Package
ML17053D680 List: ... further results
References
807E166TY, NUDOCS 8305030085
Download: ML20073Q806 (1)


Text

1 DUKE POWER GOMPAhT P.O. box 33180 CHARLOTTE, N.C. 28242 HALD. TUCKER Trazessoxz vice rammenswr po4) GTMS31 May 3, 1983

" = " ~ ~ '*"

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention:

Ms. E. G. Adensam, Chief Licensing Branch No. 4 Re: McGuire Nuclear Station Docket Nos. 50-369, 50-370

Dear Mr. Denton:

Duke Power Company has described the actions taken regarding recent problems with the DS-416 breaker undervoltage (UV) devices in a letter dated April 18, 1983 and in a meeting with the NRC Staff on April 19, 1983. The NRC reviewed the informtion provided and, in a telephone conference call on April 26, 1983, outlined additional actions it felt necessary to satisfactorily resolve the issue. These additional actions were discussed in another conference call on April 27, 1983. The purpose of this letter is to provide the additional information requested by the Staff and update our April 28, 1983 letter.

Westinghouse has been involved in the undervoltage device problems at McGuire since early in March. Duke and Westinghouse personnel have worked together in the identification and resolution of the UV devices. With one exception, the deficiencies noted in the DS-416 UV device have been discovered on the breakers at McGuire. Thus, the recommendations that have been issued by Westinghouse have been implemented at McGuire. These include:

1) ~ Replacement of UV devices with new devices with all manufacturing problems corrected and with modified grooves to accommodate the new retaining rings.
2) Installation checks on UV attachment to verify proper alignment and interface with the breaker trip shaft.
3) Alerting operators to potential problems relative to reactor trip switchgear.
4) Re-emphasize to the operators indications available to detect failure of rods to insert into the core.

Westinghouse also recommended in a March 31, 1983 letter that the operators initiate a manual trip following any reactor trip from the reactor protection system. Duke did not implement this recommendation since 1) existing procedures (Reactor Trip and ATWS procedure) require a manual trip if reactor trip does not occur, and 2) a modification to the reactor trip breakers was made such 8305110085 830503 g

PDR ADOCK 05000369 S

PDR j

Mr. Harold R. Denton, Director May 3, 1983 Page 2 that the shunt coil is energized as a result of any reactor trip signal'from the reactor protection system. This automatic shunt trip of the reactor trip breaker obviates the need fer a follow-up manual trip by the operator.

(Note:

copies of the Reactor Trip Procedure and the ATWS Procedure were sent to the NRC by letter dated May 2, 1983.)

Thus, with all the actions taken by Duke, the potential safety problems identified by Westinghouse in its Part 21 notification and its letter of March 31, 1983 to the NRC have been addressed.

The NRC Staff identified additional surveillance that should be performed to assure the operability of the reactor trip breakers. Duke evaluated the Staff's proposed testing and discussed this testing in a conference call on April 27, 1983. As a result, the following testing will be performed in addition to that required by Technical Specifications. It is proposed that these additional tests be added to the Technical Specifications only after the program has had the benefit of additional review to determine the generic applicability.

Test Frequency 1.

Independent test of UV and Every startup if not performed shunt trip.

within previous 7 days.

2.

Test of Manual Trip from Every startup if not performed Control Room.

within previous 7 days.

3.

Response time test of reactor Every 31 days.

trip breaker on UV signal from l

RPS.

4.

Functional test of shunt trip Every 31 days.

of reactor trip breakers.

5.

Force test on trip bar and UV Every 6 months.

device of reactor trip breakers and bypass breakers.

6.

Response time test of bypass Every 6 months.

breaker on UV signal.

l 7.

Functional test of shunt trip Every 6 months.

l on bypass breakers.

The startup testing and monthly testing specified will be performed at this i

frequency for at least 6 months. This will include trending of breaker response times. After 6 months an evaluation of the benefits versus the impact of the testing will be made. A decision on the need to change the frequency would then be made and appropriate changes proposed. Accordingly, the following is

.- ~.

~. _.

4 Mr. Harold R. Denton, Director L

May.3, 1983 Page 3

- a recommended license condition for inclusion in the McGuire Units 1 and 2 l

Facility Operating Licenses:

i "The licensee shall hnplement the reactor trip breaker and bypass breaker testing as described in Mr. Hal B. Tucker's i

letter of May 3,

1983.

The licensee shall not make

~

any major modifications to this program unless prior NRC approval is received.

Major modifications are defined as:

I a.

Elimination of any identified testing, b.

Changes in the frequency of performing the identified testing, and Reduction in the scope of any of the required testing."

c.

[

Curing the meeting with the NRC Staff on April 19, 1983 a copy of several test

~. procedures and a maintenance proce.it.re were previded. The Staff, in reviewing the maintenance procedures, did not see evidence of adequete QA involvement.

In a conference call on April 27, 1983 it was explained that the maintenance procedure by itself was not the only document that controlled QA/QC activities.

The scope of QA coverage is specified in Maintenance Management Procedures which.

j described the work request system and QA requirements detailing specific irspection requirenents for electrical equipment including circuit breakers. Copfes of the' following documents were sent to the NRC Staff on April 27, IS83.ty express package service.

l-l

1) Copy of McGuire Nuclear Station Work Request Form
2) Procedure' describing work request

- Maintenance Management Procedure 1.0

- Maintenance Management Procedure 3.0

3) QA/QC requirements for inspection of electrical equipment l
4) Revised copy of Air Circuit Breaker Maintenance Procedure Duke is pursuing with Westinghouse a follow-on evaluation and reliability program for the DS-416 UV attachment. The scope and objectives of this program are being developed and will be provided to the NRC Staff by June 3,.1983.

l.

- Duke Power Company believes that the actions taken to date at McGuire in response l

to the DS-416 UV device problems and the commitments made for future actions-provide a sufficient basis for operation of.both McGuire units. All of these actions have been discussed in some detail with the NRC Staff and general

' agreement reached on the essential points. Accordingly, it is our intention l

to proceed with startup of both units consistent with the plant schedule (currently criticality of both units is scheduled for May 4, 1983). However, operation will i

I m m,~,

m.--

,_._,..,._.-.,.-,__m,__-,-.,--

m._., ~,...... -,, _ _ -. - - _ _ - - _ _. -., _ - -

s Mr. Harold R. Centon, Director i

l

'May 3, 1983 Page 4 be limited tc zero power physics testing on both units until receipt of the NRC Staff Safety Evaluation Report on the reactor trip breakers.

Please advise if there are any questions regarding this matter.

Very truly yours, d

/

-/

Hal B. Tucker CAC/php Attachment i

cc:

Mr. James P. O'Reilly, Regional Adtainistrator U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 i.

Mr. W.T. Orders.

NRC Senior Resident Inspector McGuire Nuclear Station i

4

_,,_,,___,___..,-.y.._

_